33kV I/C LINE FROM DARAM KHOLA HPP MINIMUM ELECTRICAL CLEARANCES 1. BETWEEN PHASE TO PHASE = 1500 mm 2. BETWEEN PHASE TO EARTH = 1500 mm 3. GROUND CLEARANCE TO ANY LIVE PART=3700mm LEGENDS LA LIGHTNING ARRESTOR 30kV, 10kA L-CT 33kV CURRENT TRANSFORMER 400-600/1/1A (NEW REQUIREMENT) CORE-1 CL. 0.5, 20VA CORE-2 CL. 0.5, 20VA PLAN OF 33KV DARAM KHOLA HPP FEEDER (NOT IN FEPL SCOPE) CORE-2 CL. 5P20, 20VA L-PT 33kV POTENTIAL TRANSFORMER 33kV 110V 110V 3 3 3 CORE-1 CL. 0.5, 50VA 33kV I/C LINE CORE-2 CL. 3P, 50VA CKT. BKR. (52L') CIRCUIT BREAKER (VCB) 33kV, 1250A, 25kA for 3 Sec. ISO. (89B) ISOLATOR WITHOUT E/S 33kV, 630A, 25kA for 1 Sec. ISO. E/S (89L) ISOLATOR WITH EARTH SWITCH 33kV, 630A, 25kA for 1 Sec. NOTES 1. DO NOT SCALE, ASK WHEN IN DOUBT. 2. ALL DIMENSIONS ARE IN MILIMETERS UNLESS NOTED OTHERWISE. 3. CONDUCTOR USED FOR BUS AND JUMPS CONNECTIONS IS "ACSR COYOTE" 4. GROUND WIRE USED SIZE 7/3.15 mm G.I. 5. GRAVEL & FENCING IS NOT IN FEPL SCOPE. 6. TERMINATION OF 33KV INCOMING AT 33kV FEEDER GANTRY TO BE DONE BY CUSTOMER. 7. ALL CIVIL WORK ASSOCIATED WITH 33KV FEEDER GANTRY & CABLE TRENCH IS NOT IN FEPL SCOPE. 8. ALL FOUNDATION WORK IS NOT IN FEPL SCOPE. 9. ALL ITEMS RELATED TO FOUNDATION (LIKE ISMC, ISMB, ANGLES, FENCING, CHEQUIRED PLATE, INSERT PLATE, FABRICATED FOUNDATIONS & LADDERS ARE IN CUSTOMER's SCOPE. SECTION - AA P2021-22 601 SKK PS F3P20221-22 601 02 SKM NTS A3 1/1 .