Professional Documents
Culture Documents
Question One
J 9254846.766 532966.875
K 9254838.814 532922.762
Question Two
A 9255844.465 534582.784
B 9255877.512 534526.496
(iii) compute distance and bearing from B to C, basing on the coordinates of C obtained from
(ii) above.
Question Three
α β
A B
A 500.000 400.222
B 550.000 580.444
Question Four
A Given:
α AC = 110.567 m
BC = 106.894 m
Ϫ β
C B
A 8799.888 6780.708
B 8795.777 6895.674
A B
α β Given:
CB = 96.631 m
θ CA = 84.130 m
A 9256800.888 53678O.555
B 9256872.747 536889.450
Question Six
A α C
Given,
β Given,
A 9800.345 8769.234
B 9876.543 8765.432
Question Eight
Given,
A 9800.345 8769.234
B 9876.543 8765.432
A closed traverse was run from control point JM10 with an orientation to JM11, passing
through Pin1, Pin2 and Pin3, closing at JM13 with an orientation to JM12. The field data
obtained was as per under.
At Pin1
JM10 220 04’ 13’’
Pin 2 2180 16’ 53’’ 145.274
At Pin 2
Pin 1 160 02’ 10’’
Pin 3 2060 24’ 56’’ 148.285
At Pin 3
Pin 2 740 00’ 02’’
JM13 2740 06’ 48’’ 95.450
At JM13
Pin 3 600 02’ 11’’
JM12 1160 49’ 27’’
Question Ten
The height of a building and its elevation at the base are to be determined by Trigonometric
method. An instrument was set at a higher elevation than the base of the building, and the
following field data was obtained.
(i) The elevation at the instrument station = 44.444 m, above mean sea level (amsl).
(iii) Vertical angle at the mark on the building at a height equal to the height of the instrument
= 1110 11’ 11’’
(iv) Vertical angle at the top of the building = 550 55’ 55’’
(v) Slope length from the telescope to the mark on the building = 33.333 m.
Compute,
A 60.000 m
A 9247500.000 532600.000
B 9247420.600 532535.450
Question Twelve
The centerline of two straights is projected forward to meet at Point of Intersection, whose
chainage is 3276.78 m and the deflection angle being 30 0 00’ 00’’. The straights are to be
connected by a circular curve of radius 200 m, and is to be set by 20 m standard chord, using
Rankine’s method.
Calculate,
(ix) Midordinate
Use π = 3.1416
Question Thirteen
Calculate the setting out data by 25 m chords of a 300 m Summit curve, where two gradients
of +2 percent and -1.6 percent meet. The reduced level at the beginning of the curve at A is
27.94 m.
Use π = 3.1416
Question Fourteen
Calculate the necessary setting out data, if the speed of the motor car is 72 km / hour (20 m
tape was used).
Question Fifteen
Perform contour interpolation and draw 54 and 58 contour value, indicating the distance from
the contour to one of the reduced level along the section aa, bb, cc and dd. The reduced
levels at grid intersection were taken with 20 m by 20 m square grids.
a b c d
56.00
55.90 55.80 56.45
60.72
61.40 60.96 62.35
A b c d
Question Sixteen
A Building Economist wants to estimate the cost of building a Mall at the outskirts of a city,
including the cost of clearing a site. The North of the site has a depression, and the soil is to
be borrowed from the nearby quarry in order to fill the depression. Contouring has been done
and contours drawn. The area enclosed by each contour was obtained using a Planimeter,
as shown below.
66 60 35
62 62 42
60 64 51
64 66 63
68 68 75
(i) Compute distances from instrument station A to leveling staff stations B and C.
Question Eighteen
A Tacheometric survey was executed in order to determine reduced levels of points A, B, and
C as follows:
(a) Compute horizontal distance from the instrument station P to the points A, B, and C.
Compute State plane coordinates of points C and D, if the following State plane coordinates
of points A and B and Arbitrary coordinates of points A, B, C, and D, are provided as per
under.
Question Twenty
The following offsets, 10 m apart, were measured at right angles from a straight line to the
edge of a river as follows: 0m, 2.3m, 5.5m, 7.9m, 8.6m, 6.9m, 7.3m, 6.2m, 3.1m, 0m.
Compute the area enclosed by a straight line and the edge of a river (irregular / curvilinear
boundary) using,
A piece of land is to be covered with soil materials, so as to make it leveled and be used for
car parking at a formation level of 86.5 m above mean sea level. The figure above shows an
area concerned with square grids of 15 m.
The Drain with sight rails at chainages of 60 m and 120 m is to be set out. However, in order
to facilitate the setting out, the data below were associated with the drain in question.
Compute staff readings when placed on top of the sight rails at 60 m and 120 m.
The above levels and chainages were obtained for route construction purposes, and hence,
sectioning was required in order to establishing a formation line.
Compute,
(ii) The reduced levels on the formation line at chainage 25 m, 50 m,75 m, 100 m, and 125 m.
(iii) The depths of cutting or heights of filling at chainage 25 m, 50 m, 75 m, 100 m and 125 m.