Date : 11 - 8 – 2021
Rev- 01
1.0 PURPOSE
The purpose of this document is to conducted switch gear board earthing system with
2.0 SCOPE
This procedure shall be applicable for conducting switch gear board earthing system
with acceptable values. (M.V earthing system limit less than one ohm& L.V earthing
BS 7430 -1998
5.0 RESPONSIBILITY
HSE Advisor shall be Responsible for safety related matters and all the safety
specifications.
available area for implementation earthing system, study obstacles & prepare risk
I. QUALITY CONTROL
Ensure valid calibration certificates are available with the equipment, which
inspection.
Raise risk assessment and coordinate client consultant for optimum solution
approximate Sketch)
Mention obstacles such like (not available area, high soil resistive value,
Rn = Rr * [{1−λa}/ n] (Eq-2)
1 / Rs = 1 / Rr + 1 / Rc (Eq-4)
C- Abbreviations:
Rs = Total system resistance in ohm
n = number of rods
Applying the above tabulated data, the resistance per one Rod Rr can be given by the
following equation:
Rr = 16.29 Ohm
For an array of 2 rods in one side average-spaced with 3 meters, the earth resistance of the
Rn = Rr ( 1+λ a ) / n
Rr = 9.74 Ohm
Where :
Rn = Total earthing resistance for (n) rods combined in one side.
a = ρ / {2π Rr S}
Applying the above tabulated data, the resistance of earthing strip Rc can be given by the
following equation:
Rc = 2.57 Ohm
Rc4 =2 Ohm
Rs = 1 Ohm
Calculation sheet
Soil Resistivity Rod Conductor
50 Length (Lr)meter 3 Cross Section Area(mm2) 50
Diameter (dr)meter 0.019 Diameter (uc) 0.00798
Total all number Of Rods 2 Burial Depth (hc) 0.6
Spacing Between Rods (S) meter 3 Approximate Overall Length 20
lamda 1 P 4
Q 0.9
Notes:
1- Measurement value of the earthing system overall resistance should be done
according to the specifications.