You are on page 1of 5

2022 8th International Conference on Information Management (ICIM)

Improving Construction Waste Management using


Transportation Management and Lean Tools at a
Construction and Hydrocarbons Company
Freddy Calluche-Avendaño Krissia Castillo-Flores Gino Viacava-Campos
Industrial Engineering Industrial Engineering Industrial Engineering
Universidad Peruana de Ciencias Aplicadas Universidad Peruana de Ciencias Aplicadas Universidad Peruana de Ciencias Aplicadas
2022 8th International Conference on Information Management (ICIM) | 978-1-6654-5174-1/22/$31.00 ©2022 IEEE | DOI: 10.1109/ICIM56520.2022.00037

Lima, Peru Lima, Peru Lima, Peru


0000-0002-0218-7492 0000-0003-1812-2092 0000-0002-0126-4126
u201312826@upc.edu.pe u20131a002@upc.edu.pe pcingvia@upc.edu.pe

Abstract—The consumption of natural gas has been increasing losses of 1.3 trillion dollars worldwide. In other words, if
in recent years. For this reason, there are a larger number of gas improvement actions are conducted, the construction industry
installation projects, which generate a greater amount of waste can increase 2% of the world’s GDP [1]. For this reason, a model
causing environmental, economic, and social impacts. Based on is proposed that integrates the use of the Lean methodology
this, companies are not prepared nor aware that they must together with the implementation of some of its tools in the
improve their waste management plans in public works. The construction industry. Even when this has not been widely
contribution of this article is to introduce a Lean model in an implemented, the research references we consulted tell us that
industry where Lean tools are not frequently used, seeking to
this model can be adapted to this industry.
increase efficiency in the Construction and Demolition Waste
(CDW) management. The proposed model is based on the Plan- II. STATE OF THE ART
Do-Check-Act cycle, and it is subdivided into two components,
starting with the 5S methodology that goes hand in hand with A. Waste Management
Transportation Management, and ending with Process The waste management problems identified from
Standardization. The results revealed that waste management construction activities represent 35% of companies at a global
efficiency increased by 9%.
scale [5]. In addition, there is a 50% increase in CDW in public
Keywords—construction and demolition waste, lean principles,
works projects due to management inefficiencies in project
waste management, waste reduction execution phases. [6] In this situation, it is necessary to consider
the following steps for efficient management: identify the types
I. INTRODUCTION of waste, set objectives for reducing waste production, conduct
measures to minimize the waste generated, transport the waste
According to [1], in 2017 an investment of 10.9 trillion
efficiently, record and verify that the change has been
dollars was achieved between goods and infrastructure projects
successfully implemented. [7] Furthermore, an efficient on-site
in the industry, which is equivalent to 13% of world’s GDP. In
waste collection also includes their transportation. To achieve
addition, it is estimated that, in the coming years, investment in
this, the weight of the collected waste must be maximized for
the construction industry will grow by 3.3% annually. This
each kilometer traveled. Here, the location and allocation of
denotes the importance and great impact of the construction
waste collection points must be considered, as well as the
industry in the development of the global and national
number of vehicles used for each collection site, their capacity,
economies. However, in 2017, more than 6.5 trillion
and the number of trips planned. Therefore, a linear
Construction and Demolition Waste (CDW) tons were
programming model would help optimize the waste collection
generated, of which 55% are construction and demolition waste
routes from waste generation points to the authorized waste
[2]. Added to this is the growth of gas excavation and installation
treatment points. So, a linear programming model would help
processes due to the consumption of natural gas that has
optimize waste collection routes from generation points to
continued to increase worldwide in 2019 with 2.6% more than
authorized waste treatment points. Then, identifying the sources
in 2018, which reported a record figure of 5.1%. [3]. In addition,
and types of waste generated in works can improve your
according to [4] at the end of 2019, natural gas service coverage
collection processes that includes the planning of waste
in Peru reached 11% compared to 8% the previous year, which
transport and that consequently if done correctly, can increase
represents a total of 1,113,983 customers, and it is expected that,
efficiency in waste management by 24.84% [8]. Likewise, with
by 2025, natural gas users nationwide will increase to 1.5 million
efficient waste management, 40.63% of these can be minimized
people with a coverage of 18% [4].
and environmental benefits can be achieved that are equivalent
Of both industries exposed, inefficiency in solid waste to a reduction in greenhouse gases of 12, 623.30 kg and
management in operations generates an excess of CDW. This reduction of the use of illegal sites as landfills [9]. On the other
problem affects the profitability of company projects, causing hand, the linear programming model for waste collection

978-1-6654-5174-1/22/$31.00 ©2022 IEEE 166


DOI 10.1109/ICIM56520.2022.00037
Authorized licensed use limited to: Universitas Brawijaya. Downloaded on September 11,2023 at 16:22:13 UTC from IEEE Xplore. Restrictions apply.
optimization demonstrates an efficiency increase of 26.08% and First, the PLAN phase is conducted by diagnosing the
decreases in costs of 44.44% [10]. company, where the initial state of the company will be recorded
to identify current problems, such as an inefficient management
B. Industry Success Stories of CDW, low truck efficiency rates, and waste generation
Mapping construction operation processes identifies estimation errors, among other problems. Based on this,
problems. In addition, an analysis tool may be used to determine different objectives will be set so we can work on them
root causes. Furthermore, a simulation can also be used to verify throughout the development of the cycle.
the effectiveness of the Lean tools in eliminating or mitigating
these root causes. [11] In this simulation, a process productivity Second, the DO phase seeks to remedy problem causes. Here,
increased 41%, processes improved 14%, and unproductive two sub-phases will be applied: Work Standardization to
times were reduced by 17%. In addition, after assessing the identify and eliminate Non-Value-Adding (NVA) activities
waste flow map to identify activities that do not add value and from the processes; and a linear transportation scheduling to
activities that add value in the construction waste processes, the optimize the transportation system and reduce travel times.
costs of construction operations were reduced by 26.78% [12]. Third, the CHECK phase. The results will be measured
A comparative study of Lean and sustainability principles in using the proposed indicators, both general and specific.
India found that their interaction is 13.5%, and that applying Likewise, a monitoring will be performed documenting the
Lean always denotes considerable achievement towards results in records, validating that the objectives proposed are
sustainability. In Saudi Arabia, the construction industry was being met.
able to improve its performance in each process by adopting the Finally, in the ACT phase, the results and the new
Lean philosophy with a yield of 0.77 to 0.86. Here, total factor observations, limitations and new points for improvement that
productivity increased by 11.45%, and the total times with added will be performed at the restart of this cycle to continue with
value and without added value were reduced by 7.5% and continuous improvement.
15.47 % respectively [13]. Finally, a study conducted in a
community in Renca, Santiago, Chile, wherein an optimization The proposed model seeks to define the tools that will be
model of solid waste collection routes was developed with the used to solve the problem of inefficiency in CDW management
help of a linear programming model with mixed integers, that brings with it the projects in External Networks.
denoted an improvement in collection efficiency by 26% and in C. Model Indicators
cost savings of 44% and a reduction of 17.60% of carbon
emissions reduction [14]. The model raises the following indicators to monitor and
control progress, as well as measuring the impact it will have on
C. Main Lean Tool Implementation Roadblocks the case study. They are also necessary to assess the changes
The literature tells us that 80% of companies that applied the performed during the application of the model.
Lean methodology failed to achieve the culturalization of their 1) Indicator 1: Waste Management Efficiency Percentage.
workers and the organization on the Lean system. Consequently,
It will measure the waste management efficiency progress. For
the Lean implementation did not achieve the expected results
since there were no effective guidelines for the introduction of this, it is necessary to estimate the amount of waste expected
this methodology. Some of the most relevant are an unfavorable and generated. This way, we can control whether the value
organizational culture, lack of technical skills, not clearly obtained is greater than or equal to 90%, which would be
understanding Lean techniques, poor training, and lack of considered as an adequate level.
knowledge of the Lean approach. Likewise, the authors claim 2) Indicator 2: Efficiency of trucks in waste collection. It
that companies are usually opposed to changes since traditional will measure the efficiency of the trucks used for waste
processes have been modified by a new working method, and by collection. To achieve this, it is necessary to have the total tons
the implementation usually takes a long time [15]. collected per month and the number of trips made per month.
III. CONTRIBUTION With this information, it is necessary to control that the
percentage is greater than or equal to 85% to conclude that it is
A. Fundamentals at an adequate level.
Throughout the years, the construction industry has been 3) Indicator 3: Pipe Damages. It will be used to monitor
constantly searching for how to improve project execution and the number of impacts per project. To achieve this, it is
make it more effective and efficient to improve productivity. necessary to determine the total number of interference effects
Therefore, an exhaustive research study was conducted to find and the total number of projects that have been conducted. With
tools that may solve and improve necessary aspects within the both data, it will be possible to arrive at a result that will allow
construction industry.
a better progress analysis. Here, a value greater than or equal to
B. Proposed Model 4 will be deemed as an adequate level.
After reviewing and assessing different scientific articles, a
IV. VALIDATION
model based on the PDCA cycle has been developed to be
applied in External Networks Projects (polyethylene projects in The model will be validated through a Pilot Plan at the XYZ
the main roads and metropolitan roads). company in its External Networks projects, which will allow us
to verify the hypothesis proposed in the research study. This
validation method is more viable since it will be applied to a

167

Authorized licensed use limited to: Universitas Brawijaya. Downloaded on September 11,2023 at 16:22:13 UTC from IEEE Xplore. Restrictions apply.
realistic scenario based on the projects conducted by the TABLE II. WEEKLY EXPECTED WASTE FOR EACH MONTH
company during a minimum period of three months. The results Months Advanced Km Expected waste (m3)
from the Pilot Plan will be measured by indicators that will
provide a better understanding of the before and after. January 11.56 111.87

February 12.99 138.17


A. Proposed Process
Using the statistical formula for calculating sample size, it March 11.23 108.68
2021
was obtained that, for each indicator proposed, there must be at April 12.05 120.50
least 73 data items. Therefore, the data obtained will be from all
the projects conducted during the implementation of the model. May 11.29 109.23

To plan the transportation required for the company, the June 10.94 109.39
main processes that generate waste were identified: chopping Based on the collection truck information from 2018 and
and removal process and manual and mechanical excavation 2019, which reported 480 trips each, and according to the
process. From them, the following results were obtained, as estimated amount of waste expected for 2021 calculated, the
shown in Table I. new collection truck information would be a total of 6 trucks
with 12 weekly trips each.
TABLE I. SUMMARY TABLE OF THE YEAR 2018 AND 2019
1) Stage 1: Establishment of Systematized Collection
2018 2019 Points. After creating a database containing total waste
Projects
45 85 information, collection points were designated near the
Waste generated (m3) 36,36 91,13 worksite. Hence, when the trucks arrive at the site, they will
Expected waste (m3) 25,62 41,18 find the waste amount specified at the established place.
2) Stage 2: Optimization of waste collection routes.
Different data were collected for the programming development:
With the information presented in Table I, the forecast plan the transportation times from a garage to a construction site, the
is prepared based on the kilometers advanced as per the 2018 number of trucks available per garage, and the number of trucks
and 2019 data. that each construction site requires to collect waste. The
schedule conducted is presented below:
Indexes: i: Truck (i=1,2,3,4,5,6,7,8); j: Work site (j=1,2,3)
Variables: Xij: Number of trips made by truck "i" to the work
site “j”.
Data: Time(ij) // Capacity(i) // Demand(j) //
Model:

 minimize ∑6i=1 ∑8j=1 Xij ×Timeij  

 ∑8j=1 Xij ≤ Capacityi ∀ i=1,..,6 

Fig. 1. Linear Regression (Advanced kilometers)  ∑6i=1 Xij ≥ Demandj ∀ j=1,..,8 


After the analysis of Fig. 1, a forecast of the average monthly
kilometers that the project will progress in 2021 is performed,  Xij ≥0 ∀ i=1,..,6 ∀ j=1,..,8 
which gives a result of 306.16 km. From this, the estimated
amount of waste generated on a weekly basis is calculated as This information is then transferred to the Lingo software to
ideal numbers with the following formula, which the company obtain the results.
takes as a reference as established by the Peruvian Standard G 3) Stage 3: Standardization of work: For the
050 Safety during Construction:
standardization tool it was only applied in the manual work
performed by the operators.
Expected waste ( ) Step 1: Determine the standard time of the activities through
= 1.2m(trench height) × 0.25m(trench width) the taking of time in minutes per meter of trench.
× Km advanced × 1000
Step 2: Definition of corrective or preventive measures.
Then, the estimated results of the weekly works (Monday to
TABLE III. DEFINITION OF CORRECTIVE OR PREVENTIVE MEASURES
Friday) of the first 6 months of the year 2021 were obtained as
shown in the following table: Process Type Causes Solutions

168

Authorized licensed use limited to: Universitas Brawijaya. Downloaded on September 11,2023 at 16:22:13 UTC from IEEE Xplore. Restrictions apply.
Working with Operator Lack of
How-to guide
bars training X document
for using tools
Electrical Lack of use of Communication review
Interference gloves and Checklist Tools are not
Tool Checklist X
Workplace Preventive completed
conditions measures Order and Failure to
Lack of revision Show plans Cleanliness in X comply with
Pipe affectation
of plans during training the work area schedule
Tools not found Tools Support Use of
Formatting can
5s supporting X
Tool Verification Workspace be complex
(Order and documents
clutter
Cleanliness)
Leave of
absence is Tools Support B. Results
Departure without
exceeded 5s The model presented and developed in the validation section
permission
They leave (Discipline) was carried out in a period of 5 continuous months with the
without warning intention of being able to analyze the proposed indicators and be
able to keep track of these for possible changes or corrections
Step 3: Proposing solutions within the model. However, to carry out a more detailed analysis,
the segmentation technique by months is proposed, which is
TABLE IV. PROPOSED PREVENTIVE MEASURES used to obtain cases of independent studies that will be evaluated
Remove Correct
independently without affecting the other. In this way it will be
Activities Problem possible to propose improvements within the model already
Problem Action
established.
Excavation PPE Use See user
Manual The following is a comparison of the initial diagnosis with
with bars Training guide
the results of the pilot test, measured with indicators:
Runway Pipe Locate plan in TABLE VII. SCENARIO RESULTS AS IS VS PILOT TEST
Training
breakage affectation a visible place
Pilot
Indicator Name Scale As Is
Check Test
Reception and Poor Waste management
Bill of Check Percentage 81.78 91.39
delivery of location of efficiency
Materials List of
materials materials
materials Waste transport efficiency Percentage 68.18 81.94
Leaving Pipeline impacts by
Make work Meet Unit 7 4
Refreshment work project
schedule schedule

x Indicator 1, Waste Management Efficiency did not


Step 4: Register new measures achieve the expected percentage. However, an increase
of approximately 9% was achieved.
TABLE V. ACTIVITIES RECORDED TO CORRECT
x Indicator 2, Waste Transportation Efficiency did not
Activities Correct Action reach the expected percentage. However, it increased by
Excavation with bars View tool usage guide approximately 13%.
Place plan in view of x Indicator 3, Pipeline Impacts per Project reached the
Runway breakage
workers
expected value, where a difference from 7 to 4 pipeline
Reception and delivery of
Check List of Tools impacts were achieved per project.
tools
Meet established schedule CONCLUSIONS
Refreshment
per day The implementation of the proposed model based on
Transportation Management with Linear Programming and the
Step 5: Analysis and comparison of results 5S tool, and coupled with Process Standardization, has
generated significant improvements at the XYZ company. This
TABLE VI. COMPARISON OF RESULTS ACTIVITY AND EFFECT is reflected in the indicators, which in general terms means going
from having an efficiency in waste management of 81.79% to
Does 91.39%. This allows new research for future work, wherein the
Yes
Activity Not Effect Type model may be streamlined so that it may be extended to new
Meets
Comply
projects.

169

Authorized licensed use limited to: Universitas Brawijaya. Downloaded on September 11,2023 at 16:22:13 UTC from IEEE Xplore. Restrictions apply.
In addition, the model helped organize Transportation [5] Ajayi, S. O., Oyedele, L. O., Bilal, M., Akinade, O. O., Alaka, H. A., &
Management. In other words, each waste collection truck had a Owolabi, H. A. (2017). Critical management practices influencing on-site
waste minimization in construction projects. Waste Management, 59,
route and a defined collection point, thus reducing transportation 330–339. https://doi.org/10.1016/j.wasman.2016.10.040.
times and costs. Likewise, Process Standardization managed to [6] Yadav, O. P., Nepal, B. P., Rahaman, M. M., & Lal, V. (2017). Lean
considerably reduce the time used in each activity mentioned in Implementation and Organizational Transformation: A Literature Review.
the previous tables. EMJ - Engineering Management Journal, 29(1), 2–16.
https://doi.org/10.1080/10429247.2016.1263914.
The proposed model developed in the XYZ case study shows [7] Bajjou, M. S., & Chafi, A. (2018). Barriers of lean construction
that there is still work to be done, since in some cases it is evident implementation in the Moroccan construction industry. AIP Conference
that the expected results were not achieved and, in some others, Proceedings, 1952. https://doi.org/10.1063/1.5032018.
certain improvements are expected. This is because the [8] Sarhan, J., Xia, B., Fawzia, S., Karim, A., & Olanipekun, A. (2018).
implementation of a new philosophy to a company requires time Barriers to implementing lean construction practices in the Kingdom of
for operators to adapt to change and thus everything that has Saudi Arabia (KSA) construction industry. Construction Innovation,
18(2), 246–272. https://doi.org/10.1108/CI-04-2017-0033.
been established within the model is fulfilled. In addition, it is
[9] Shurrab, J., & Hussain, M. (2018). An empirical study of the impact of
recommended to be in constant evaluation to correct and polish lean on the performance of the construction industry in UAE. Journal of
certain aspects that can be improved to continue with the process Engineering, Design and Technology, 16(5), 694–710.
of continuous improvement. https://doi.org/10.1108/JEDT-09-2017-0095
[10] Blazquez, C., & Paredes-Belmar, G. (2020). Network design of a
The present study only considered the management of household waste collection system: A case study of the commune of
construction and demolition waste from the process of Renca in Santiago, Chile. Waste Management, 116, 179–189.
installation and laying of natural gas pipes of External Networks, https://doi.org/10.1016/j.wasman.2020.07.027.
this individual analysis and the results presented will have the [11] Tafazzoli, M., Mousavi, E., & Kermanshachi, S. (2020). Opportunities
scope to all projects carried out by companies that carry out this and challenges of green-lean: An integrated system for sustainable
work, which will help them improve working conditions, the construction. Sustainability (Switzerland), 12(11).
https://doi.org/10.3390/su12114460.
efficiency of activities in construction works and the efficient
[12] Zhang, X., Azhar, S., Nadeem, A., & Khalfan, M. (2018). Using Building
management of the waste they generate. Information Modelling to achieve Lean principles by improving
efficiency of work teams. International Journal of Construction
Management, 18(4), 293–300.
REFERENCES https://doi.org/10.1080/15623599.2017.1382083
[13] Ur Rehman, A., Usmani, Y. S., Umer, U., & Alkahtani, M. (2020). Lean
[1] McKinsey&Company. (2017). Reinventing Construction: Reinventing
Approach to Enhance Manufacturing Productivity: A Case Study of Saudi
Construction: A route to higher productivity, 3-6. Retrieved from:
Arabian Factory. Arabian Journal for Science and Engineering, 45(3),
https://www.mckinsey.com/~/media/McKinsey/Industries/Capital%20Pr
2263–2280. https://doi.org/10.1007/s13369-019-04277-9.
ojects%20and%20Infrastructure/Our%20Insights/Reinventing%20constr
uction%20through%20a%20productivity%20revolution/MGI- [14] Hannan, M. A., Begum, R. A., Al-Shetwi, A. Q., Ker, P. J., Al Mamun,
Reinventing-Construction-Executive-summary.ashx. M. A., Hussain, A., Basri, H., & Mahlia, T. M. I. (2020). Waste collection
route optimisation model for linking cost saving and emission reduction
[2] Suárez-Silgado, S. S., Quiroga, C. B., Benavides, J. M., & Vanegas, L. M.
to achieve sustainable development goals. Sustainable Cities and Society,
(2019). Villavicencio : current state, barriers and management
62(January), 102393. https://doi.org/10.1016/j.scs.2020.102393.
instruments. Entramado, 15(1), 224–244.
[15] Issa, U. H., & Alqurashi, M. (2020). A model for evaluating causes of
[3] Bandeira, S. R., Maciel, J. B. S., Carlos, J., Oliveira, S. De, & Sanches,
wastes and lean implementation in construction projects. Journal of Civil
A. E. (2019). Construction and Demolition Waste Management Practices
Engineering and Management, 26(4), 331–342.
at Construction Sites. 6495(10), 35–45.
https://doi.org/10.3846/jcem.2020.12323
[4] Promigas Peru (2020). Informe del sector gas Peru. Retrieved from:
http://www.promigas.com/Es/Noticias/Paginas/Informe-Sector-
Peru.aspx

170

Authorized licensed use limited to: Universitas Brawijaya. Downloaded on September 11,2023 at 16:22:13 UTC from IEEE Xplore. Restrictions apply.

You might also like