You are on page 1of 1

Procedure for installation of rooftop solar plant through National

Portal
Register at National Portal through
the link https://solarrooftop.gov.in/.
Registration Follow the instructions given on the
After registration, login into the portal for registration.
account and click submit
application. Fill the information
required in the format and submit
the application. Apply for
Rooftop Solar

If all details are found correct Else

Technical
Upon TFR approval, sign
Feasibility
agreement with the selected The submitted application will reach
Approval/TFR
registered vendor and proceed for directly to the concerned DISCOM
installation of the plant. The list TFR Approved for technical feasibility approval. If
of registered vendors is visible in all the details are correct, the
the ‘vendors in my area’ tab in the Selection of application will be approved. Else,
applicant’s account on National vendor and plant the application may be rejected or
Portal. installation returned for correction.

Submit After installation of the plant,


Installation submit installation details in the
Details National Portal and upload a photo
DISCOM officials will inspect the of the applicant with the plant.
system in accordance with the These details are required for
technical criterion prescribed by inspection and net-metering of the
MNRE. Upon successful plant.
inspection, net-meter would be Inspection by
installed by the DISCOM. DISCOM

Once the net-meter has been


installed, the DISCOM official
will approve the installation
Project
details on the portal and an online
commissioning
commissioning certificate will be
status
generated. This certificate will be
visible in the applicant’s account.
After generation of commissioning
certificate, the applicant can raise
online subsidy/CFA claim request Subsidy/CFA
by providing applicant’s bank Request
details along with legible copy of Important Instruction
cancelled bank cheque or pass book.
1. The applicant shall use own mobile number
and mail id for registration on National Portal.
If all details found The applications having mail id/ mobile no. of
correct the vendor would be rejected and such vendors
would be blacklisted from further participation
If all details are correct, Central Govt. in the program/scheme.
subsidy/CFA would be released directly 2. It shall also be ensured that the electricity
into the bank account of the applicant connection and bank account is in the name of
within 30 days of submission of the applicant, else the application would be
CFA/subsidy claim. Subsidy Released rejected.

You might also like