Professional Documents
Culture Documents
2
a. Leave the first row in your spreadsheet blank. On the second row, type in the
headers. In this example, we’re using Tasks, Responsible, Start, End, Days,
and Status. You could also add more headers for extra granularity, like Budget, Cost
and more.
b. Highlight the text and in the Alignment group, click the center icon to center the text
in the headers.
c. To format the headers for proper spacing, highlight all the text you just typed and
on the Home tab, in the Cells group, click Format. Select Column Width and set the
width for around 15-20 so you have enough space to enter in your project
information.
3
3. Add Colors to Convey Project Status at a Glance
It’s easy to customize your project plan with colors and visual hierarchy. By changing the
styling and font sizes, you can highlight key information and convey project status at a
glance.
a. To change font color, click on the cell with the text you want to change. In
the Home tab, select the color you want from the color drop-down list.
b. To change the background color of one or more cells, select the cell(s) you want to
change. Click the paint bucket icon and select the fill color.
c. To format fonts, select one or more cells. In the Home tab, you can change the font
type, font size, and make the title bold, italicized, or underlined.
We recommend adding a background color to the main header and to each group or phase
of tasks, as well as your target completion date or launch date. You can also change the
font color of in the Status column to reflect current progress (in this example, red
represents Overdue, green represents Complete, etc).
4
4. Create the Project Plan Timeline
You’ve already added all your project information to the table, now it’s time to make the
corresponding project timeline. Including a timeline in your project plan will help set
expectations and increase transparency, keeping everyone aligned around priorities and
due dates.
Add and Format Dates
a. On the same row as your table headers, in the next available column, enter the two
dates of your project timeline. Then, hold down Shift, select the two dates, and drag
the bottom right-hand corner across the row until you’ve reached your end date.
b. If you’d like to change the format of dates, select all the dates and right-click.
Select Format Cells.
c. In the pop-up box, select Date under the Category section and select the date type
you’d like.
d. You’ll notice that the cells are very wide. To make the timeline more compact, select
all the dates, and select a smaller font size. In this example, we’ve selected font size
9.
e. Then, select all the dates again and in the Cells group, click Format. Select Autofit
Column Width to automatically adjust the column width to the dates.
5
Add Colors to Make the Project Timeline
a. First, extend the same background colors and font formatting from your table to
your timeline.
b. Now, you’ve created a type of matrix. You have a row that corresponds to each task,
and on the right-hand side, on your timeline, you can simply fill in the cells that
represent each task’s start and end date. To do this, select a cell (or more than one
cell) and click the paint bucket icon. Select the color you’d like to use.
5. Final Touches
a. To add grid lines to the project plan, select the entire project plan, both the table and
the timeline, and in the Font group, click the borders icon. Select All Borders.
6
b. If you want to add more project information, select the first column, right-click and
select Insert > Entire Row. Repeat until you have 8 empty rows.
c. Then, in the first column, enter the following: Project Name, Project Manager,
Project Deliverable, Start Date, End Date, and Overall Progress. Then, fill in the
corresponding information.