Professional Documents
Culture Documents
Submitted By
P S ARUN
SNG18NS026
In partial fulfilment of the requirement for the degree
of
I undersigned hereby declare that the project report “Preliminary design of 1300
dwt Platform Supply Vessel of 12 knots service speed”, submitted for partial
fulfilment of the requirements for the award of degree of Bachelor of Technology
of the APJ Abdul Kalam Technological University, Kerala is a bonafide work
done by me under the supervision of Asst.Prof. Jofin Lukose of NASB
department, SNGCE Kadayiruppu. I also declare that I have adhered to ethics of
academic honesty and integrity and have not misrepresented or fabricated any
data or idea or fact or source in my submission. I understand that my violation of
the above will be a cause for disciplinary action by the institute and the University
and can also evoke penal action from the sources which have thus not been
properly cited or from whom proper permission has not been obtained. This
report has not been previously formed the basis for the award of any degree,
diploma or similar title of any other University.
Kadayiruppu Signature
17/01/2022 P S Arun
SREE NARAYANA GURUKULAM COLLEGE OF
ENGINEERING
KADAYIRUPPU, KOLENCHERY
CERTIFICATE
I would like to thank all the teaching staffs and colleagues of NASB
Dept for supporting and guiding me thought-out the project till its completion.
ABSTRACT
This is a design project of 1300 dwt platform supply vessel with 12 Knots which
service in the Mumbai , Arabian sea (INDIA). It originates its service from
Jawaharlal Nehru Port Mumbai, India and provide supplies to high field oil
platforms operated under ONGC located 95 nautical miles away from the port.
The design process consists of fixing of main dimension, form coefficients, initial
stability, design equation, sectional area curve, lines plan, offset generation,
general arrangement, rudder and propeller design, stability and hydrostatics,
resistance, power estimation, engine selection, scantling of mid-ship section,
general arrangement, trim and stability.
TABLE OF CONTENTS
Acknowledgement
Abstract
List of figures
List of tables
Chapter 1. Introduction
1.9 Support
3.2 Iteration
11.1 Introduction
11.2 Procedure
11.4 Conclusion
12.1 Introduction
13.2 Classsification
Conclusion
Reference
Appendix
LIST OF FIGURES
LIST OF TABLES
ABBREVIATIONS AND NOTATIONS
CHAPTER 1
INTRODUCTION
1. AIM OF THE PROJECT AND MISSION ANALYSIS
Range : 230 NM
The owner’s requirements are fixed in consultation with the guide and according
to recent trends in OSV productions. The following vessel parameters are
selected as being most suitable to supply cargo to the operating Offshore rigs.
a. Supply deck cargo, drill pipe casings, gas containers for welding, cutting etc.,
cementing equipment’s, oil pipes and food articles in refrigerated
containers.
b. Supply cement, barites, methanol, diesel oil, fresh/drill water etc. to
offshore installations.
c. Perform fire-fighting.
d. Supply crew required on the field.
3. ENDURANCE CALCULATION
4. SERVICE ROUTE
A Platform supply vessel (PSV) is a ship specially designed to supply offshore oil
and gas platforms. These ships range from 50 to 100 meters in length and
accomplish a variety of tasks. The primary function for most of these vessels is
logistic support and transportation of goods, tools, equipment and personnel to
and from offshore oil platforms and other offshore structures. In the recent years
a new generation of platform supply vessel entered the market, usually equipped
with Class 1 or Class 2 dynamic positioning system.
They belong to the broad category of offshore vessels (OSVs) that include
platform supply vessels (PSV’s), crane vessels (C/V) and well stimulation vessels
(WSVs), anchor handling vessels (AHTSVs) and offshore construction vessels
(OCVs).
Advantages of PSV’s
•A unique eye-catching design
•Excellent fuel efficiency
•Deep water and long-distance supply
•High standards of crew comfort
Usually when the vessel approaches the rig it drops its own anchor at suitable
position depending upon the prevailing weather and manoeuvres astern to the rig
in positions where mooring ropes can be lowered by crane and used to secure to
the belt on its port and starboard quarters. Good manoeuvrability and station
keeping is to be achieved by using a DP system on board, which enables the ship
to be at exact position even during extreme waves or heavy operations. After the
positioning, the rig crane unloads the deck cargo. If the rig requires any of the
pump able commodities available, it lowers hose (usually 100 mm bore), which is
connected to appropriate discharge conditions, and pumping is commenced as
soon as possible. After the process, DP system disables and the vessel returns to
the base port.
9. SUPPORT
Common and specialty tools are carried on the large decks of these vessels. Most
carry a combination of deck cargoes and bulk cargo in tanks below deck. Many
ships are constructed to accomplish a particular job. Some of these vessels are
equipped with a fire-fighting capability and fire-monitors for fighting platform fires.
Some vessels are equipped with oil containment and recovery equipment to assist
in the clean-up of a spill at sea. Other vessels are equipped with tools, chemicals
and personnel to “work-over” existing oil wells for the purpose of increasing the
wells production.
Normally cargo is carried on the flat afterdeck and in the tanks below this. The
main types of cargo carried by an OSV are as follows:
• Cement
•Liquid mud
•Brine
•Freshwater, drinking water, fuel, lube oil
•Methanol
•Personnel
•Other equipment’s to be carried are: -
a) Drill bits
b) Pipes of various diameters
c) Refrigerated containers
d) Oil pipes
e) Casings
f) Gas containers for welding, etc.
a. Drilling mud
Drilling mud is a fluid pumped through the inside of the drill pipe that flows out
through the drill bit and back to the rig through the riser, thereby cooling the bit
and removing cuttings. The mud is chemically engineered to prevent well
collapse and blowouts and its required composition changes as the well is drilled
and different kinds of substrate are encountered.
b. Brine
Brine is extremely concentrated salt water, which is used to create salt solutions to
pump into wells whenever the substrate is salt. Since salt dissolves easily in
normal drilling fluid, the brine is pumped through the well and as salt comes out
of solution on the well walls, it strengthens the wells wall to prevent collapse.
c. Dry bulk
Dry bulk refers to solid cargoes carried in specialized tanks such as cement, barite,
heavy clay that makes drilling mud dense, and bentonite, a light clay that keeps
chemical in solution.
d. Deck cargo
Deck cargo includes tools and equipment’s required for drilling such as drill pipe,
casing, risers, bits, collars and blow-out preventers. In addition, offshore
containers half heights, and skips are often shipped as deck cargo and may
contain stores and provisions, or even liquid cargo in some space.
e. Methanol
In oil field methanol is mostly used as a hydrate inhibitor to prevent gas hydrate
formation in the production systems. It is also used to mitigate chilly choke
problem and equilibrate pressures across valves before opening.
12.DEVELOPMENT OF OFFSHORE VESSELS
The oil and gas industry marked a milestone in 1947 with the drilling of the first
true offshore well. It happened in the open waters of the Gulf of Mexico, 45
miles off the Louisiana coast. And with that innovation, a new need was created
for vessels to work in the sometimes-harsh offshore environment.
Initially, fishing boats and retired World War II military vessels were pressed into
service delivering the tons of equipment, men, and supplies needed to support
offshore facilities. Then in 1955, the first dedicated offshore supply boat was
launched. Two years later, leaders of the evolving offshore vessel industry came
together to form an informal organization to promote their common interests and
represent them in Washington. By 1973, with the industry focusing more of its
efforts both nationally and internationally, the group formally incorporated as the
Offshore Marine Service Association (OMSA).
The first-generation supply vessels (circa 1965) were of 1000t DWT to supply
fixed platforms operating in 20-150 ft in coastal waters. The second generations
were designed with large engines to enable them to tow jack-up rigs in offshore.
The third generations (circa 1982) were built to operate world-wide and handle
the floating semi-submersible exploration and production platforms in towing and
anchoring. The fourth-generation supply boat (1995) is being designed for station
keeping around the deep-water tension leg platform and complaint towers. The
modern supply vessel now serves additional functions principally related to the
offshore drilling industry, such as towing and anchor and chain handling,
although supply remains a foremost purpose. A modern Supply Vessel differs
from an Anchor Handling Tug & Supply Vessel (AHTS) in that it has larger deck
area, more capacity but less machinery and no winches. This vessel would cost
approximately 25% less than the AHTS vessel.
15.CLASSIFICATION SOCIETY
SL
VE SSE L N AM E IM O N O DW T(tn) LOA (m ) LB P(m ) B(m) T(m ) D(m) SPE E D (kn)
NO
KENDRICK 8404537 1329 81 81 16 4.9 7.2 15
1
CLWYD SUPPORTER 8325406 1338 81 81 16 5 7.2 15
2
IRBIS 8422175 1329 81.2 81.2 16.3 4.9 7.3 15.3
3
E.FRANCIS 7408897 1310 84.5 84.5 16 4.8 7.8 13.8
4
DON FILI 9575905 1309 67 67 16.4 4.2 6.5 15.3
5
OCEAN SURVEYOR 9182215 1336 73 73 16 6.3 6 12
6
SAPFIR 9182057 1336 73.8 73.8 16.1 6.3 7.4 14
7
VOS HADES 9552264 1386 59.2 59.2 14.9 5 6.1 15.5
8
GEO SERVICE 1 9621546 1336 59.2 59.2 15.8 4.8 6.1 14.5
9
S K PACIFIC 9697791 1305 59.2 59.2 14.9 5 6.1 14
10
SL VESSEL DWT
L/B B/T T/D Fn L/D B/D
NO NAME (tn)
2.222222
KENDRICK 1329 5.06 3.265 0.6805 0.2737 11.25
222
1
CLWYD 2.222222
1338 5.06 3.2 0.694 0.2737 11.25
SUPPORTER 222
2
2.232876
IRBIS 1329 4.9815 3.326 0.6712 0.2788 11.123
712
3
2.051282
E.FRANCIS 1310 5.281 3.33 0.6153 0.2465 10.833
051
4
2.523076
DON FILI 1309 4.0853 3.9047 0.6461 0.3069 10.307
923
5
OCEAN 0.2306 2.666666
1336 4.5625 2.539 1.05 12.166
SURVEYOR 6 667
6
0.85135 0.2676 2.175675
SAPFIR 1336 4.5839 2.5555 9.9729
1 4 676
7
2.442622
VOS HADES 1386 3.973 2.98 0.819 0.330 9.7049
951
8
GEO SERVICE 2.590163
1336 3.7468 3.291 0.786 0.309 9.7049
1 934
9
2.442622
S K PACIFIC 1305 3.9731 2.98 0.819 0.2988 9.7049
951
10
(Table 2.2 Parent-ship ratios)
3. PARENT SHIP GRAPHS
LBP 85.55 m
L/B 5.84
B/T 1.79
B/D 1.37
B 14.64 m
T 8.18 m
D 10.68 m
CHAPTER 3
2) Δ = CB x L x B x T x Δ x (1+s) = Δ DWT + Δ LS
where, 1+s = 1.005
B →Breadth moulded in m
T →Draft moulded in m
CB →Moulded block coefficient
Δ → Full displacement in t
3) Δ LS = Δ S + Δ OU + Δ EP
Where, Δ LS →Lightship weight in t
Δ SE →Steel weight in t
Δ OU →Outfit weight in t
4) S= WS7 (1+0.5(CB1-0.70))
where, WS7 →steel weight at CB 1 of 0.7
5) WS7 = K x E1.36
Where, K →Constant (0.41 to 0.51)
E →Equipment number
6) E = L(B+T) + 0.85 x L x (D-T) + 0.85 Δ L1H1 + 0.75 Δ L2H2
L1 and H1 →Length and height of full width erections
L2 and H2 →Length and height of deck house
8) Δ OU = m x L x B
m →Constant which varies from 0.3 –0.4
9) Δ EP = 0.1087 Δ PB
2. ITERATION
The iteration method is done by taking a range of -10m to +10m of LBP obtained
from the graphical analysis. The LBP values are iterated by using the ratios and
the required service speed. The main dimensions obtained from iteration are: -
MAIN DIMENSIONS
L 54.00
B 9.24
D 6.44
T 5.16
3. ESTIMATION OF DISPLACEMENT
The calculations below have been done using the values from the iteration.
Block Coefficient
CB 0.975-0.9*Fn
Fn v/(g*L)^(1/2)
L 54.00 m
g 9.18 m/s2
v 6.1728 m/s
Fn 0.277245168
CB 0.725479349
> Displacement
∆ CB*L*B*T*ρ*1.005
CB 0.723
L 54.00 m
B 9.24 m
T 5.16 m
ρ 1.025 t/m3
∆ 1917.536578 t
∆SE Ws7*(1+0.5(CB1-0.70))
Ws7 K*(E^1.36)
E L*(B+T)+0.85*L*(D-T)+200
CB1 CB+(1-CB)*(0.8*D-T)/3T
D 6.44 m
T 5.16 m
CB 0.725479349
L 54.00 m
B 9.24 m
K 0.046
CB1 0.725337478
E 1036.352
Ws7 580.56085
∆SE 587.9158238 t
∆OU m*L*B
m 0.4
L 54.00 m
B 9.24 m
∆OU 199.584 t
PB 1.02*PD
PD (∆^0.567)*(v^3.6)/1000
∆ 1911.31 t
v 12 knots
PD 556.6308054 kW
PB 567.7634215 kW
∆EP 61.71588392 t
∆LS ∆SE+∆OU+∆EP
∆LS(actual) 1.02*∆LS
∆SE 587.9158238 t
∆OU 199.584 t
∆EP 61.71588392 t
∆LS 849.2157077 t
∆LS(actual) 866.2000219 t
DEADWEIGHT
DWT ∆-∆LS(actual)
∆ 1917.536578 t
∆LS(actual) 866.2000219 t
DWT 1051.336556 t
CHAPTER 4
PRELIMINARY CHECKS
1.FREEBOARD CHECK
OSV’s are classified as type B ships (ILLC). The steps involved in freeboard
check are: -
CB 0.725479349
Correction 16.38594191 mm
>
L/15 3.6
D 6.44 m
R L/0.48
R 112.5
Correction 319.5 mm
> (-0.3)*TF
Correction -147 mm
S 0.5*L
L 54 m
S 27
Correction 175.066 mm
D 6.44 m
T 5.16 m
1.28 m
0.853951942 m
2. STABILITY CHECK
i. The area under the righting-lever curve (GZ curve) should not be less than
0.055 meter -radians up to = 30° angle of heel and not less than 0.09
meter –radians up to = 40° or the angle of flooding f *, if this angle is
less than 40°. Additionally, the area under the righting lever curve (GZ
curve between the angles of heal of 30° and 40° or between 30° and f1,
if this angle is less than 40°, should not be less than 0.03 meter-radians.
ii. The righting lever GZ should be at least 0.20 m at an angle of heel equal to
or greater than 30°.
iii. The maximum righting arm should occur at an angle of heel preferably
exceeding 30°but not less than 25°.
iv. The initial metacentric height GMO should not be less than 0.15 m
The following equivalent criteria are recommended for Offshore Supply Vessels:
i. The area under the curve of righting levers (GZ curve) should not be less
than 0.070 meter-radians up to an angle of 15° when the maximum
righting lever (GZ) occurs at 15° and 0.055 meter-radians up to an
angle of 30° when the maximum righting lever (GZ) occurs at 30° or
above. Where the maximum righting lever (GZ)occurs at angles of
between 15° and 30°, the corresponding area under the righting lever
curve should be: 0.055 + 0.001 (30° -max) meter-radians.
ii. The area under the righting lever curve (GZ curve) between the angles of
heel of 30° and 40° or between 30° and f if this angle is less than 40°,
should be not less than 0.03 meter-radians.
iii.The righting lever (GZ) should be at least 0.20 m at an angle of heel equal
to or greater than 30°.
iv. The maximum righting lever (GZ) should occur at an angle of heel not less
than 0.15 m.
v. The initial transverse metacentric height (GMO) should not be less than
0.15m.
The comparison between stability criteria for ordinary ship and offshore supply
vessels are given below: -
GZ GM*sinθ+BM*h*
GM KB+BM-KG
KB 0.52*T
BM (C1*B*B)/(12*CB*T)
C1 CW^1.8
KG 0.57*D
T 5.16 m
B 9.24 m
D 6.44 m
CB 0.725
CM 0.985089722
Cw 0.752643966
C1 0.599599486
KG 3.6708 m
BM 1.139591476 m
KB 2.6832 m
GM 0.151991476 m
Figure above shows the prohaska’s curve for 15deg and 30deg heel angle. For corresponding
B/D and B/T values on graph, h1* is plotted. It is very much difficult to plot the exact value
from the chart, so linear interpolation have to be done where value comes in between two
values of h1*
0 0 0 0 0 0 0
0.03933828 0.22791829
15 0.26 0.26 9 0.2 5 0.27
0.07599573 0.28489786
30 0.52 0.50 8 0.25 9 0.36
-
0.10747420 0.34187744
45 0.79 0.71 3 -0.3 3 -0.23
-
0.56979573
60 1.05 0.87 0.13162848 -0.5 8 -0.44
-
0.14681249 0.79771403
75 1.31 0.97 2 -0.7 3 -0.65
-
0.15199147 0.91167318
90 1.57 1.00 6 -0.8 1 -0.76
1 Area under GZ curve upto 30° > 0.055 m-rad 0.8194 PASS
2 Area under GZ curve upto 40° > 0.09 m-rad 1.1882 PASS
3 Area under GZ curve b/w 30°&40° > 0.03 m-rad 0.3686 PASS
Vdd L*B*T*CB*(D/T)*(Cw/CB)
Cw (0.743*CB)+0.297
L 54.00 m
B 9.24 m
T 5.16 m
D 6.44 m
CB 0.725479349
Cw 0.836031156
Vdd 2686.420921 m3
Vsh 0 m3
Vht 0 m3
Vap
Kap 2.16*(2-k)
k (3.33*AB/LBP)-0.667
AB 0.523*LBP
LAP 0.06*LBP
CBD CB+(0.25/T)*(D-T)*(1-CB)
LBP 54 m
B 9.24 m
D 6.44 m
T 5.16 m
CB 0.725479349
CBD 0.742503885
LAP 3.24 m
AB 28.242 m
k 1.07459
Kap 1.9988856
Vap 17.16883272 m3
Vfp
Kfp 1.7*k*b
Lfp 0.07*L
LBP 54 m
B 9.24 m
D 6.44 m
CBD 0.742503885
k 1.07459
Lfp 3.78 m
Kfp 1.826803
Vfp 21.35689563 m3
Ver Ler*B*(D-Ddb)*CM
Ler 0.25*L
Ddb 1000*B/20
CM CB/(0.04+(0.96*CB))
LBP 54 m
B 9.24 m
D 6.44 m
CB 0.725479349
CM 0.985089722
Ddb 0.462 m
Ler 13.5 m
Ver 734.5771894 m3
Vdb V*(Ddb/T)^(Cw/CB)
V L*B*T*CB
L 54 m
B 9.24 m
T 5.16 m
CB 0.725479349
Ddb 0 .462 m
Cw 0.836031156
V 1867.843508 m3
Vdb 115.7797556 m3
V hold Vdd-Vap-Vfp-Ver-Vdb
Vdd 2686.420921 m3
Vap 17.16883272 m3
Vfp 21.35689563 m3
Ver 734.5771894 m3
Vdb 115.7797556 m3
V hold 1797.538248 m3
Speed 12 knots
Endurance 30 hours
Range 250 nm
Crew 10 persons
Volume of HFO
Vhfo Mhfo/ρhfo
Mhfo
PB PD*1.02
H 30 hrs
PD 556.6308054 kW
PB 567.7634215 kW
Mhfo 3.86306232 t
Vhfo 4.292291466 m3
Volume of diesel oil
Vdo Mdo/ρdo
X1 0.001*DWT
X2 0.001*PB
PB 567.7634215 kW
DWT 1300 t
H 30 hr
X1 1.3
X2 0.567763421
Paux 1200.22811 kW
Mdo 10.95205299 t
Vdo 13.16352523 m3
Assuming consumption
Vfw Mfw/ρfw
Mfw
crew 10 persons
consumption 20 litres/person/day
Mfw 3.22 t
ρfw 1 t/m3
Vfw 3.22 m3
Vlo Mlo/ρlo
Mhfo 3.86306232 t
Mdo 10.95205299 t
Mlo 0.511121478 t
Vlo 0.553161773 m3
Mass of crew
Mcrew 100*crew/1000
crew 15
Mcrew 1
Mass of cargo
Mcargo 1280.453763 t
Required volume for cargo
Vreq 1536.544516 m3
Thus, the same dimension is taken as the final dimension of the vessel.
LBP 54 m
B 9.24 m
D 6.44 m
T 5.16 m
Fn 0.3017
CB 0.7254
Cw 0.8562
Δ 1917.536578 t
ΔLS 866.2000219 t
DWT 1315.38 t
V 2686.420921 m3
Speed 12 knots
In the previous chapter we have fixed the main particulars of the vessel. In order to
create
the hull form, we have followed linear lines distortion method where the gridlines and
each offset values( of the parent ship) have to be distorted to the required vessels
dimension(our vessel) by using ratios.
i. Location of station and waterlines have to be distorted such that it suits our vessel’s
length and depth.
(D/D1)=(W/W1)
Where,
Similarly for waterlines, use the same ratio. Only change in the above equation would
ii. After fixing the gridlines for the vessel, now distort each and every offset value of the
parent vessel.
(B/B1)=(X/X1)
Where,
iii. After distortion lines plan is successfully drawn and faired in AutoCAD software
L 80 m
B 18 m
D 7.8 m
T 6 m
CB 0.74
Waterline spacing
w 1 m
Stationline spacing
h 4 m
Distance
from 19th
station
Waterline Stem
0 2
1 3.89
2 4.3
3 4.4
4 4.6
5 4.7
6 4.8
7 4.3
7.8 4.33
10.95 5.69
13.05 5.85
Distance
from 1st
station
Waterline Stern
0 12.11
1 4.75
2 1.15
3 -2.59
4 -5.49
5 -6.84
6 -7.17
7 -7.19
7.8 -7.18
Parent
ship
offset
15 3.54 5.68 6.36 7.19 7.70 8.08 8.38 8.62 8.66 8.79 8.88 9 9
16 2.40 4.52 5.16 5.90 6.38 6.81 7.24 7.65 7.72 7.99 8.21 8.84 8.96
17 1.95 3.19 3.77 4.39 4.72 5.05 5.51 6.04 6.14 6.54 6.91 8.02 8.41
18 1.43 2.77 3.23 3.75 4.07 4.34 4.62 4.96 5.06 5.46 5.91 7.30 7.83
18.5 1.00 2.22 2.69 3.25 3.58 3.81 4.00 4.22 4.27 4.50 4.79 6.30 7.01
19 0.27 1.45 1.92 2.45 2.74 2.95 3.20 3.49 3.57 3.82 4.06 5.14 5.96
19.5 0.00 0.40 0.79 1.36 1.70 1.91 2.08 2.25 2.28 2.45 2.66 4.02 4.84
20 0.00 0.00 0.00 0.05 0.13 0.21 0.21 0.36 0.43 0.52 0.65 2.04 3.06
16 3.3 6.18 6.98 7.47 7.83 7.98 8.1 8.27 8.29 8.4 8.4
17 2.24 5.03 5.78 6.35 6.81 7.03 7.23 7.6 7.66 8.12 8.36
18 1.82 3.71 4.27 4.65 5.16 5.47 5.77 6.34 6.45 7.23 7.85
18.5 1.33 3.17 3.67 3.99 4.32 4.52 4.76 5.39 5.52 6.39 7.16
19 0.93 2.68 3.21 3.51 3.74 3.86 4.01 4.42 4.53 5.52 6.34
19.5 0.25 1.95 2.44 2.73 2.99 3.1 3.21 3.49 3.57 4.46 5.41
20 0 0.69 1.46 1.74 1.95 2.05 2.14 2.42 2.48 3.35 4.33
Three sets of curves are to be drawn. First set for Bonjean curves sets, representing the
sectional area up to the given water line and second set represents the first moment this area
about the base line plotted at each station. The third is the sectional area curve upto LWL and
center of floatation, metacentric height , the form coefficients, MCT1cm , TPC, IL, IT, BML, KMT
are calculated for different waterlines parallel to the base line and spaced normally about 1m
apart. The results so obtained are plotted in a diagram with draught on the Y- Axis. The
curves drawn in this way are called hydrostatic curves.
CHAPTER 7
METHOD
The resistance prediction by Holtrop and Mennen method is done with the following
parameters. This method is more accurate than Guldhammer method since it uses actual
values of ship rather than using any reference of graphs of tanker ships like Guldhammer
method
Propeller diameter D m
1+k₂eq 1.431372549
Total resistance
Rtotal RF*(1+k1)+RAPP+RW+RB+RTR+RA
RF= (1/2)*ρ*S*(V^2)*CF
S= L*(2T+B)*(CM^(1/2))*(0.453+0.4425*CB-0.2862*CM- 0.003467*(B/T)+0.3696*CW)+
2.38*(ABT/CB)
Rn= V*L/Ṽ
RF = 32.58752524 kn
1+k1 = C13*(0.93+C12*((B/LR)^0.92497)*((0.95-Cp)^(-0.521448))*
(1-Cp+0.0225*lcb)^0.6906)
C13 = 1+0.003*Cstern
C12 = (T/L)^0.2228446
T/L 0.095555556
>0.07
LR = (1-Cp+0.06*Cp*lcb/(4*Cp-1))*L
Cp = CB/CM
c13 = 1.03
c12 = 0.704897289
Lr = 16.9081057
C12(B/Lr)^0.92497 = 0.403081117
(0.95-Cp)^-0.521448 = 2.074331337
(1-Cp+0.0225lcb)^0.6906 = 0.415055614
(1+k₁) = 1.31534901
RAPP = 0.5*ρ*(V^2)*SAPP*(1+k2)eq*CF
(1+k2)eq = Σ(1+k2)*SAPP/ΣSAPP
Rw = C1*C2*C5*∇*ρ*g*exp(m1*(Fn^d)+m2*cos(λ*(Fn^-2)))
C1 = 2223105*(C7^3.78613)*((T/B)^1.07961)*(90-IE)^(-1.37565)
C7 = B/L
C2 = exp(-1.89*(C3^(1/2)))
C5 = 1-0.8*AT/(B*T*CM)
C3 = 0.56*(ABT^1.5)/(B*T*0.31*(ABT^(1/2))+T-Hb)
IE = 1+89*exp(-((L/B)^0.80856)*((1-Cw)^0.30484)*((1-Cp-
0.0225*lcb)^0.6367)*
((LR/B)^0.34574)*((100*∇/(L^3))^0.16302))
m1 = 0.0140407*(L/T)-1.75254*(∇^(1/3))/L-4.79323*(B/L)-C16
C16 = 8.07981*Cp-13.8673*(Cp^2)+6.984388*(Cp^3)
C15 = (-1.69385)+((L/∇)^(1/3)-0.8)/2.36
Fn = V/(g*L)^(1/2)
m2 = C15*(Cp^2)*exp(-0.1*(Fn^-2))
λ = 1.446*Cp-0.03*(L/B)
L/B<12 6.551082251
C7 = 0.152646534
(L/B)^0.80856 = 4.571282715
(1-Cwp)^0.30484 = 0.551548336
(1-Cp-0.0225*lcb)^0.6367 = 0.483400086
(Lr/B)^0.34574 = 1.232338799
Ie = 21.27535965
C1 = 2.856955589
C3 = 0.013034841
C2 = 0.805911186
C5 = 0.983903421
C16 = 1.253107439
m1 = -2.186047547
C15 = -1.69385
m2 = -0.176293122
lambda = 0.820322663
d = -0.9
m1*Fnᵈ = -7.522633993
m2*cos(ʎ*Fn^-2) = -0.172126244
Rw = 20.9446711
RTR = 0.5*ρ*(V^2)*AT*C6
FnT = V/(2*g*AT/(B+B*Cw))^(1/2)
C6 = 0.2*(1-0.2*FnT)
RA = 0.5*ρ*(V^2)*S*CA
CA = 0.006*((L+100)^-0.16)-0.00205+0.003*((L/7.5)^(1/2))*(CB^4)*C2*(0.04-C4)
C4 0.04
CA 0.000612327
RA 11.36737288
RT = 75.74567773 KN
The resistance at service speed has to be overcome by the power delivered by the engine
with maximum possible efficiency. Powering, propeller design and engine selection are
interrelated and cannot be worked out independently. The derivation of the engine power
starts from resistance at service speed
V (knotts) Rt Pe
1 0.854241105 0.439421624
2 3.231250742 3.324310763
3 7.043885805 10.87012457
4 12.24411608 25.19349326
5 18.7982119 48.34900102
6 26.69904228 82.4039241
7 36.02029772 129.701888
8 47.31858341 194.7254344
9 61.00398597 282.4240534
10 76.37554592 392.8758082
11 100.6678606 569.6190221
12 121.1407737 747.7777677
13 160.585811 1073.869436
14 214.7461409 1546.515808
(Fig 7.1 Graph speed vs resistance)
w = 1.33*(CB^2)-0.797*CB+0.215
w = 0.30773633
> Thrust deduction factor
t = 0.0665+0.62833*w
t = 0.259859968
Va = V*(1-w)
Va = 8.30716404 Knots
> Thrust
Tt = RT/(1-t)
Tt = 101.4207384 kN
Dmax = 0.5*T
Dmax = 2.25 m
(AE/Ao)min = ((1.3+0.32*Z)*Tt/2)/((Patm+ρ*g*h-Pv)*(Dmax^2))+k
Pv = 1.704 kN/m2
H = 2.25
0.55
So after taking an allowance AE/A0 was fixed at 0.55 ( The standard Kaplan 4-55series
is selected for our vessel).The number of blades was selected as 4 since keeping all
other parameters constant the 4 bladed propeller gives the maximum efficiency
7.4 FREE RUNNING CONDITION
KT/(J^2) = (Tt/2)/(ρ*(VA^2)*(Dmax^2))
KT/(J^2) = 0.7175137
KT, KQ Polynomials
J = 0-1
The resistance at service speed has to be overcome by the power delivered by the engine
with maximum possible efficiency. Powering, propeller design and engine selection are
interrelated and cannot be worked out independently. The derivation of the engine power
starts from resistance at service speed
rps
n = Va/(J*Dmax) rotations/sec
Torque
Q = KQ*ρ*(n^2)*(Dmax^5) kNm
Ηo = (KT/KQ)*(J/2π)
Delivered power
PD = 2πnQ kW
Break power
PB = PD/ηs kW
ηs=Shaft efficiency 0.97 (assumed)
rps 3.24798
rpm 194.879
Bore 210 mm
Stroke 310 mm
Power 1320 kW
Propulsion system used in this ship is Diesel – Electric system. It is the latest technology
applied in OSV in order to reduce pollution and to increase fuel efficiency. Here fixed pitch
Due to different and individual types, purposes and operational profiles of dieselelectric driven
vessels the design of a diesel-electric propulsion plant differs a lot and has to be evaluate case
by case. All the following is for information purpose only and without obligation. In general the
• Lower fuel consumption and emissions due to the possibility to optimize the loading of
diesel engines / gensets. The gensets in operation can run on high loads with high efficiency.
This applies especially to vessels which have a large variation in load demand, for example for
an offshore supply vessel, which divides its time between transit and station-keeping (DP)
operation.
• High reliability, due to multiple engine redundancy. Even if an engine / genset malfunctions,
there will be sufficient power to operate the vessel safely. Reduced vulnerability to single point
• Reduced life cycle cost, resulting from lower operational and maintenance costs.
as azimuth thrusters or pods. Precise control of the electrical propulsion motors controlled by
frequency converters.
• More flexibility in location of diesel engine / gensets and propulsors. The propulsors are
supplied with electric power through cables. They do not need to be adjacent to the diesel
engines / gensets.
• Low propulsion noise and reduced vibrations. For example a slow speed E-motors allows to
avoid gearboxes and propulsors like pods keep most of the structure bore noise outside of the
hull.
• Efficient performance and high motor torques, as the system can provide maximum torque
also at slow speeds, which gives advantages for example in icy conditions.
CHAPTER 8
PROPELLER GEOMETRY
MARIN developed a special screw series known as Ka series for the use in nozzles 19A, 22
and 24. The Kaplan (Ka) propeller series is the recognized standard in shrouded propellers
being extremely popular for trawlers, tugs and other vessels requiring high towing or bollard
pull thrust. The propeller and nozzle both contribute to the efficiency of the installation. Ka
screw series have relatively wide blade tips, uniform pitch and flat faced sections. The Kaplan
propeller is designed to operate in a nozzle and has excellent thrust characteristics in low speed
applications. The Kaplan propeller has a combination of aerofoil sections at the inner radii and
flat faced segmental sections towards the tip. The blade contour has a wide tip that is accurately
propulsion unit. A schematic view of a ducted propeller is given in Fig. 4.6. The axial force
acting on the impeller of a ducted propeller usually differs from the net thrust of the system. A
positive or negative force may act on the nozzle depending on the nozzle shape and the
operating condition. Due to the nozzle action the velocity at the impeller plane can be either
less than or greater than the velocity at the propeller plane of a conventional screw with the
same diameter and speed of advance. The ducted propeller with the accelerating flow type of
nozzle is now used extensively in cases where the ship screw is heavily loaded or where the
screw is limited in diameter. The accelerating nozzle offers a means of increasing the efficiency
of heavily loaded propellers. The nozzle itself produces a positive thrust. In the case of the
decelerating flow type of nozzle, the nozzle is used to increase the static pressure at the impeller.
This ducted propeller system is the so called pump jet. The duct will produce a negative thrust.
This nozzle may be used if retardation of propeller cavitation is desired. For naval ships a
reduction in noise level can be obtained which may be of importance for tactical reasons.
From the theoretical calculations it was concluded that the use of an
accelerating nozzle leads to an increase of efficiency at higher screw loads, In addition, at higher
screw loadings a long nozzle is advisable, while at light screw loadings a short nozzle should be
used. At high screw loads, however, the nozzle must not have a larger L/D ratio than about 1.
Above this value the loss in efficiency due to the frictional nozzle drag will still be larger than
the gain in ideal efficiency which can be obtained by application of a nozzle
0.852823 m
0.15435 m
GENERAL ARRANGEMENT
The aim of this chapter is to serve as a prologue for the general arrangement finalization in
locating the main spaces and their boundaries within the ship’s hull and superstructure.
• Machinery Space
• Cement Tanks
• Volume requirements
• Structural integrity
The bottom shell, inner bottom and side shell are transversely framed. The transverse
bulkheads have vertical stiffeners. Longitudinal framing is adopted for the deck. Frame spacing
is given by DNV rules.
s = 0.48 + 0.002Lm
s = 616 mm
Therefore 620 mm is selected as basic frame spacing
The hull was subdivided according to the recommendations laid down by DNVGL. The
were 8.
Cargo ships the distance Xc from the forward perpendicular to the collision bulkhead is to be
taken between the following limits. For ships without bulbous bow,Xf=0
Xc-min 0.05*LLL-Xf
Xc-max 0.05*LLL+3-Xf
LLL = length of the ship as defined in the International Convention of Load Lines. The length
shall be taken as 96 per cent of the total length on a waterline at 85 percent of the least
moulded depth measured from the top of the keel, or as the length from the fore side of the
stem to the axis of the rudder stock on that waterline, if that be greater.
Therefore, the bulkhead should lie in between 3.46 and 6.46 m from FPLL. Thus the
collision bulkhead was fixed at web frame 100 at a distance 3.5 m from FPLL.
LE = 15% of L
LE = 10.2 m
Thus based on the data we fix the engine room bulkhead on web frame 65 and web frame 85.
All ships should have one aft peak bulkhead generally enclosing the stern and the rudder post.
5% of L from AP to FP = 3.4 m
The watertight bulkheads are in general to extend to the freeboard deck. Aft peak bulkheads
may, however, terminate at the first watertight deck above the waterline at draught(T).
The distribution of cargo tanks in this type of vessels is very complex, the reason being the
large number of cargo tanks. Moreover, the type of cargo carried is varied. Adding to this ,
not all of the cargo is carried on each sort to the rig. The arrangement of the cargo tanks was
analysed from the general Arrangements of the Offshore Supply Vessels. The other guideline
was the thumb rules about the arrangement of offshore supply vessels. These rules are given
below:
i. The Bulk Mud/ Cement tanks are to be arranged aft of the engine room along the centerline
of the vessel.
ii. The wing tanks are to be arranged along the side shell from the engine room to the forward,
to prevent damage to these areas when the vessel approaches the oilrig in rough weather.
These wing tanks are generally Drill water/ Ballast tanks.
iii. The fuel and lube oil tanks are generally arranged in the double bottom below of engine
room. However based on the requirement more tanks may be provided elsewhere.
iv. Fore peak and aft peak tanks are provided for Ballast/Drill water to cope up with the trim
problems.
The forepeak and aft peak bulkhead forms forepeak tank and aft peak tank. Fuel oil or
The main deck at the aft is open area for the carriage of deck cargo. The cargo area for the
carriage of items such as drill pipe, casing etc is reinforced for 5 t/m2. Except for an area right
aft, this deck has been covered with wooden planking, to prevent the cargo movements in a
seaway. Cargo rails 1.5m high have been provided on both sides of the sheathed deck, for the
same purpose- these precautions are necessary in such a ship, because the maintaining the
center of gravity is critical in rough weather.
The towing winch is in the forward part of the main deck. The towing winch is also mounted
9.4.3 SUPERSTRUCTURE
The superstructure in these type of vessels is at the forward, ahead of amidships. External
bulkheads and decks of superstructure and deckhouse are of steel construction. Navigation
bridge wings are extended to the full breadth at amidships of the vessel. The bridge of the
vessel has a specialty that it has bridge windows both facing forward and aft. The aft bridge
windows are required to monitor towing functions. Funnel has sufficient height to prevent
smoke nuisance at bridge wings and accommodation areas. The funnel is sufficiently
insulated to prevent the escape of heat and noise to the accommodation spaces.
GT = K1*V
K1 = 0.2+(0.2*log10(V))
V = 3891.463 m3
K1 = 0.271802258
GT = 1057.708431 t
Therefore crew required are:-
Rating 2
Cook 1
Passengers 5
Design of accommodation spaces is in accordance with Maritime Law of India and IMO rules
4. All bulkheads should be of steel. If in contact with weather they have to be gas tight and
5. Bulkheads connecting crew space with store, cargo spaced tanks etc should be watertight,
gastight.
6. Bulkheads connecting two galleys, sanitary space, laundry etc should be gas tight and
watertight up to a certain height.
8. Protection:
10. Side scuttles can be opened in sleeping rooms, mess rooms, smoking rooms and
recreation rooms.
11. Separate sleeping rooms for officers, petty officers, apprentices etc.
12. Mess room should able to accommodate all officers at the same time
9.6.1.1 ARTICLE 1
1) This convention applies to every sea going mechanically propelled vessel, whether
publicly or privately owned, which is engaged in the transport of cargo or passengers for the
purpose of trade and is registered in a territory for which this convention is in force.
(d) Tug
1) There shall be no direct openings into sleeping rooms from spaces for cargo and
machinery or from galley, lamp and paint rooms or from engine , deck and other bulk
storerooms, drying rooms, common wash places or water closets.
2) External bulkheads of sleeping rooms and mess rooms shall be adequately insulated.
5) Sleeping rooms shall be situated above the load line amidships or aft.
6) Permit the location of the sleeping rooms in the fore part of the ships, but in no case
forward of the collision bulkhead.
7) The floor area per person of sleeping rooms intended for ratings shall be not less than
• 25 sq.ft or 2.35 sq.m in vessels of 800 tons or over, but under 3000 tons
• Single berth seafarer sleeping rooms the floor area shall not be less than 4.5 sq.m in
11) The minimum inside dimensions of a berth shall be 6 ft.3 ins. By 2 ft.3ins (198cm by
80cm). Lower berth not less than 30cm above the floor.
12) The furniture shall include a clothes locker for each occupant. The clothes lockers shall
be not less than 5 ft.(152cm) in height and of a cross section area of 300 sq.in(19.30 sq.
decimeters) and shall be fitted with a self and a hasp for a padlock. The padlock shall be
provided by the occupant.
13) Each sleeping room shall be provided with a table or desk, which may be of the fixed,
dropleaf or slide out type and with comfortable seating accommodation as necessary.
These plans are the arrangements for providing accommodation area for the crew as well as
the passengers. They provide:
• Sleeping arrangements(bed)
• Locker
• Galley
• Hospital
• Entertainment rooms
• Office rooms
• Crew cabins
1) Sufficient sanitary accommodation, including wash basins and tub and /or shower baths,
shall be provided in all ships.
(b) In ships of 800 tons or over, but under 3000 tons: four;
(c) In ships of 3000 tons or over: six;
(d) In ships where the radio officers or operators are accommodated in an isolated position,
3) Sanitary facilities for all members of the crew who do not occupy rooms to which private
facilities are attached shall be provided for each group of the crew on the following scale:
(a) One tub and/or shower bath for every eight persons or less:
4) Wash basins and tub baths shall be of adequate size and constructed of approved material
with a smooth surface not liable to crack, flake or corrode.
5) All water closets shall have ventilation to the open air, independently of any other part of
the accommodation.
6) All water closets shall be of an approved pattern and provided with an ample flush of
water, available at all times.
7) In all ships facilities for washing and drying clothes shall be provided on a scale
appropriate to the size of the crew and the normal duration of the voyage.
8) The facilities for washing clothes shall include suitable sinks, which may be installed in
wash rooms, if separate laundry accommodation is not reasonably practicable, with an
adequate supply of cold fresh water and hot fresh water or means of heating water. The
facilities for drying clothes shall be provided in a compartment separate from sleeping rooms
and mess rooms, adequately ventilated and heated and equipped with lines or other fitting.
9.6.1.4 ARTICLE 14
A. Hospital facilities
1) The hospital accommodation shall be suitably situated, so that it is easy of access and so
that the occupants may be comfortably housed and may receive proper attention in all
weathers.
2) The number of hospital berths required shall be prescribed by the competent authority
3) Hospital accommodation shall not be used for other than medical purposes.
4) Approved medicine chest with readily understandable instructions shall be carried in every
1) Adequate mess room accommodation shall be provided in all ships either by the provision
of separate mess rooms for each group of the crew or a single combined mess room for all
members of the crew.
2) The dimensions and equipment of each mess room shall be sufficient for the number of
3) Mess rooms shall be equipped with tables and seats of an approved type, sufficient for the
4) The Director may permit such exceptions to this regulation concerning mess room
5) Mess rooms shall be located apart from the sleeping rooms and as close as practicable to
the galley.
6) Where available pantries are not accessible to mess rooms, adequate lockers for mess
utensils and proper facilities for washing utensils shall be provided.
7) The tops of tables and seats shall be of damp-resisting material, without cracks and capable
of being easily cleaned.
8) Mess room floor area not less than 1.5 sqm per person
9) separate mess room should be provided for master and officers, petty officers ,other
seafarer
Tier Height
EN = ∆^(2/3) + 2 B H + 0.1 A
∆ = Mass displacement
B = maximum breadth
H = a + Σh
a = distance in m from summer load waterline amidships to the upper deck at side
hi = height in m on the center line of each tier of houses having a breadth greater
than B/4. For the lowest tier, this is to be measured at center line from the upper deck, or
from a notional deck line where there is local discontinuity in the upper deck
En = Δ^(2/3)+2*B*H+0.1*A
H = a+Σhi
a = 1.7 m
Σhi = 9.6 m
A= 297.555 m2
B = 16.8 m
∆ = 2200 t
H = 11.3 m
En= 578.6
Equipment letter= p
Corresponding to the equipment number, the following anchors and accessories were selected
Number 2 units
Chain diameter 42 mm
Corresponding to the equipment number, the following mooring lines were selected:-
Number 4 units
9.8.1 INTRODUCTION
At present there is insufficient data to make reliable predictions of the vessels maneuvering
characteristics from the lines plan alone. There are of course many guidelines and ‘rules of
thumb’ for deciding on suitable rudder areas. Many of which work well on the safer side and
work out well in practice. With PSV’s, however the problem is different. Experience has
shown that in majority of the vessels the rudder has given a satisfactory control at free
running speed.
The critical regime for maneuvering PSV’s is at very low speed such as coming to or
alongside a rig. As bow thrusters are not employed at this speed, the rudder has to achieve the
required maneuvers.
The steering gear compartment shall be readily accessible and separated from machinery
spaces. (SOLAS Reg. II-1/29.13.1)
9.8.3 WHEELHOUSE
The wheelhouse has been designed in such a way as to provide visibility all around. It has
windows facing all directions inclining upwards at 45deg. The windows facing aft have a
console behind, which is positioned for towing work. Upward visibility is vital while loading
unloading high platforms. Control of main machinery can be effected from either end of the
wheelhouse, while the anchor handling winches can be operated from a comprehensive aft
facing console.
1. Masthead light - One on forward mast and one on navigational mast; visibility over an
2. Side lights – Red light on port side and green light on starboard. Fitted on the sides of
the navigating bridge; visibility over an arc of horizon of 112.5 .
4. Stern light – White light at extreme aft having visibility over an arc of horizon of 135 .
MIDSHIP DESIGN
Msw-h fsw*(171*Cw*(L^2)*B*(CB+0.7)*(10^-3)-Mwv-h
min mid)
Mwv-
h 0.19*(fR/0.85)*fnl-vh*fm*fp*Cw*(L^2)*B*CB
Cw 0.0856*L
fsw 1
(for 0.3L=<x>=0.7L)
fp 1
fm 1
Cw 5.986008
Mwv-
h 71013.48
Msw-h
Msw-s
min (-0.85)*fsw*(171*Cw*(L^2)*B*(CB+0.7)*(10^-3)+Mwv-smid)
Mwv-
s (-0.19)*(fR/0.85)*fnlvs*fm*fp*Cw*(L^2)*B*CB
fnl-vs 0.58*((CB+0.7)/CB)
fnl-vs 1.114211
Mwv- -79124
Msw-s
Z [Msw+Mwv]*(10^-3)/σperm
k 1
σperm 175
Z 0.747938 m3
10.2 THICKNESS
t a+b*L2*k^(1/2)
L = L1 = L2 69.93 m
k 1
Element a b t t
t a+b*L2*k^(1/2)
(Table 10.2 PSM thickness)
Z 83*(l^2)*s*p*wk/σ
p p1+p2
p2 g0*ρ*hs
p1 10*h0+pdp
pdp pl+135*(y/(B+75))-1.2*(T-z)
pl (ks*Cw+kf)*(0.8+0.15*(V/(L^(1/2))))
h0 1.7 m
ks 2
Cw 5.986008
pdp 21.07868 kN/m2
p1 38.07868
g0 9.81 m/s2
hs 6.2 m
p2 62.34255
p 100.4212 kN/m2
tkw 1.5 mm
l 3.1 m
s 0.62 m
wk 1.09
σ 160
Z 338.3181 cm3
Z 83*(l^2)*s*p*wk/σ
p p4
p4 k*g0*ρ*hs
wk 1+0.06*tkw
k 1.3
g0 9.81 m/s
ρ 1 t/m3
Hs 5.2 m
p4 66.3156 kN/m2
tkw 1.5 mm
L 3.1 m
S 0.62 m
wk 1.09
σ 160
Z 223.4166 cm3
Z 83*(l^2)*s*p*wk/σ
p p3
p3 k*ρ*g0*hs
wk 1+0.06*tkw
k 1.3
Ρ 1 t/m3
g0 9.81 m/s2
Hs 2.6 m
p3 33.1578 kN/m2
tkw 1 mm
wk 1.06
L 3.1 m
s 0.62 m
σ 160
Z 108.6337 cm3
Z 83*(l^2)*s*p*wk/σ
p p3
p3 k*ρ*g0*hs
wk 1+0.06*tkw
k 1.3
ρ 1.025 t/m3
g0 9.81 m/s2
hs 1m
p3 13.07183 kN/m2
tkw 1 mm
wk 1.06
l 3.1 m
s 0.62 m
σ 160
Z 42.82677 cm3
10.4 SCANTLINGS
CHAPTER 11
11.1 INTRODUCTION
The capacity plan is necessary to represent the disposition and volume of tanks or spaces and
the positions of their centers of gravity. The capacity and LCG of the tanks are obtained by
integrating the sectional areas of the tanks and the moments of these areas about the reference
point. The VCG of the tank/hold are determined from the sectional areas and sectional
moments about the reference point. Throughout the calculation 98% of the moulded volume
is taken as the volume of the tank/hold and 2% deduction is given for the structural members
inside the tank.
11.2 PROCEDURE
The capacity of the tanks was determined manually. First, the vessel was modelled in
AutoCAD and the tanks were arranged according to the following rules generally followed in
offshore Supply Vessels (Ref: Discussion in DNV).
1. The Bulk Mud/Cement tanks are to be arranged aft of the engine room along centreline of
the vessel.
2. The wing tanks are to be arranged along the side shell from the engine room to the forward,
to prevent the damage to the areas when the vessel approaches the oil rig in rough weather.
3. The fuel and lube oil tanks are generally arranged in the double bottom tanks
4. Fore peak and aft peak tanks are provided for Ballast/Drill water to cope up with the trim
problems.
5. Other tank arrangement are studied from parent ships general arrangement
(Table 11.1 Material density)
After fixing the tank dimensions and locations of the tank, these were then modelled in both
Rhino and then Maxsurf. From there, more accurate capacities were found out and it is easy
to assess stability from these software.
11.3 TANK CAPACITIES
Total = 2485.77
11.4 CONCLUSION
12.1 INTRODUCTION
Trim and stability calculation has to be examined for the following loading conditions :-
i. Lightship condition
ii. Fully loaded departure (cargo 100% (including deck cargo), fuel 100%, stores 100%,)
iii. Fully loaded arrival (cargo 100% (including deck cargo), fuel 10%, stores 10%, sewage
100%)
MSC 267(85)
1). The area under the curve of righting levers (GZ curve) should not be less than 0.07 metre-
radians up to an angle of 15° when the maximum righting lever (GZ) occurs at 15° and 0.055
metre-radians up to an angle of 30° when the maximum righting lever (GZ) occurs at 30° or
above. Where the maximum righting lever (GZ) occurs at angles of between 15° and 30°, the
corresponding area under the righting lever curve should be: 0.055 + 0.00 I (30° -- <Pmax) metre-
radians
2). The area under the righting lever curve (GZ curve) between the angles of heel of 30° and 40°,
or between 30° and <pr if this angle is less than 40°, should be not less than 0.03 metre-radians
3). The righting lever (GZ) should be at least 0.2 m at an angle of heel equal to or greater than30°
4). The maximum righting lever (GZ) should occur at an angle of heel not less than 15°
5). The initial transverse metacentric height (GMo) should not be less than 0.15 m
The VCG of the basic hull can be estimated using an equation proposed by Kupras,
2.825 m
The longitudinal position of the basic hull weight will typically be slightly aft of the LCB
LCG (-0.15)+LCB
33.15 m
12.4.1 LIGHTSHIP
12.4.2 FULLY LOADED DEPARTURE
OUTLINE SPECIFICATION
The ship is a Platform Supply vessel designed to carry 1300 DWT. The vessel is designed to
operate at a cruising speed of 12 knots. The material of construction of the vessel is Steel
grade A. The vessel is designed to operate in the route of Nhava seva port to Mumbai high
fields. The aim of the design is to provide a support service to oil rigs in India.
13.2 CLASSIFICATION
LBP 54 m
B 9.24 m
D 6.44 m
T 5.16 m
Fn 0.3017
CB 0.7254
CM 0.985089722
Cw 0.8562
Δ 1917.536578 t
ΔLS 866.2000219 t
DWT 1315.38 t
V 2686.420921 m3
Speed 12 knots
The ship is divided into 4 holds, Engine room, Aft Peak and Fore Peak. Double bottom height is
1m. The ship is transversly framed. The superstructure and engine room is on the forward part of
the vessel.
The preliminary design of 1300 DWT Platform Supply vessel with 12 knots service speed
has been completed. The main dimensions are estimated and preliminary checks are done by
using various calculated formulas. The design is formed under the rules of DNV-GL
classification society. The vessel is satisfied with various conventions of IMO. The scantlings
3. An approximate power prediction method- J.Holtrop and G.G.J Mennen RINA 1984
5. DNV-GL rules
• Lines plan
• Bonjean curve
• Hydrostatics curve
• Propeller geometry
• General arrangement
• Midship scantling
LINES PLAN
Bonjean curve
Hydrostatics curve
Propeller geometry
General arrangement
Midship scantling