Professional Documents
Culture Documents
Submitted by,
SAGAR RATHOD
1RV16CV081
CERTIFICATE
1. Introduction
2. Objective ofstudy
3. Literature survey
4. Offshore structures
7. Case study
8. Conclusion
9. References
1.Introduction
2.Objective Of Study :
Offshore Wind Turbines are new types of offshore structure characterised by low
stiffness (as a result flexible and having low natural frequency) and therefore
sensitive to the dynamic loading imposed upon them. The article discusses the
complexity involved in designing the foundation of these structures. It has been
shown that design guidelines available for offshore oil and gas installation
foundations cannot be direct extrapolated/ interpolated to offshore wind turbine
foundation design.
2. Compliant tower
I. Compliant Tower
II. Guyed Tower
III. Articulated Tower
IV. Tension Leg Platform
3. Floating Structures
I. Floating Production System
II. Floating Production, Storage and Offloading System
1. Fixed Platforms
The fixed type of platform shall exhibit a low natural period and deflection again
environmental loads.
The steel template type structure consists of a tall vertical section made of tubular
steel members supported by piles driven into the sea be with a deck placed on top,
providing space for crew quarters, a drilling rig, and production facilities. The fixed
platform is economically feasible for installation in water depths up to 500m.
These template type structures will be fixed to seabed
by means of tubular piles either driven through legs of the jacket (main piles) or
through skirt sleeves attached to the bottom of the jacket.
Concrete gravity platforms are mostly used in the areas where feasibility of pile
installation is remote. These platforms are very common in areas with strong seabed geological
conditions either with rock outcrop or sandy formation.
Some part of north sea oil fields and Australian coast, these kind of
platforms are located. The concrete gravity platform by its name derive its horizontal stability
against environmental forces by means of its weight. These structures are basically concrete
shells assembled in circular array with stem columns projecting to above water to support the
deck and facilities.
Concrete gravity platforms have been constructed in water depths as much as 350m.
.
FIG 2.1 COMPLIANT TOWER
I. Compliant Tower
Compliant Tower (CT) consists of a narrow, flexible tower and a piled foundation that can
support a conventional deck for drilling and production operations. Unlike the fixed
platform, the compliant tower withstands large lateral forces by sustaining significant
lateral deflections, and is usually used in water depths between 300m and 600m.
Guyed tower is an extension of complaint tower with guy wires tied to the seabed by
means of anchors or piles. This guy ropes minimises the lateral displacement of the
platform topsides.
Tension Leg Platform (TLP) consists of a floating structure held in place by vertical, tensioned
tendons connected to the sea floor by pile-secured templates. Tensioned tendons provide for
the use of a TLP in a broad water depth range with limited vertical motion. The larger TLP’s
have been successfully deployed in water depths approaching 1250m.
Floating Production, Storage and Offloading System (FPSO) consists of a large tanker type
vessel moored to the seafloor. An FPSO is designed to process and stow production from
nearby subsea wells and to periodically offload the stored oil to a smaller shuttle tanker.
The shuttle tanker then transports the oil to an onshore facility for further processing. An
FPSO may be suited for marginally economic fields located in remote deepwater areas
where a pipeline infrastructure does not exist. Currently, there are no FPSO’s approved for
use in the Gulf of Mexico. However, there are over 70 of these systems being used
elsewhere in the world.
Water depth is considered shallow if the seabed depth does not exceed about 500
meters. The principal types of foundation used in this situation are:
a. Spudcans
b. Piles
c. Gravity base structures (GBS)
d. Concrete caissons
e. Steel Buckets
a. SPUDCANS
In the offshore industry an important role is played by self-elevating mobile drilling units,
commonly known as jack-ups, due to their flexibility and cost-effectiveness). It has proved to
be a very useful construction “tool”, especially when working in turbulent sea areas, or
breaking waves such as shoal or coastal waters, and in swift currents .
These structures consist of a buoyant triangular unit resting on three or more retractable
legs. This unit supports drilling and other topside equipment; it moves onto the intended
location with legs retracted, then releases the legs onto the seabed, and raises the hull out of
the water, as shown on Figure 16. On jack-ups, the foundation legs operate independently of
each other, and their foundations are usually known as “spudcans”.
These foundations have a unique geometry, since they are installed relying only on the
structure’s self-weight plus an additional designed preload, which is intended to minimize
settlement and improve resistance to environmental solicitations. Spudcans are roughly
circular in plan, typically they have a shallow conical underside (in the order of 15 to 30
degrees to the horizontal) with a sharp protruding spigot. In the larger jack-ups operating
today, the spudcan diameter can exceed 20 meters, with the shapes varying with the
manufacturer and rig (Randolph et al., 2005). Figure 17 illustrates two different spudcan
shapes. The usual height of a jack-up structure is over 160 m.
b. PILE FOUNDATIONS
Piles are slender columnar elements in a foundation which have the function of
transferring load from the superstructure through weak compressible strata or through
water, onto stiffer or more compact and less compressible soils or onto rock. They may be
required to carry uplift loads when used to support tall structures subjected to overturning
forces from winds or waves. Piles used in marine structures are subjected to lateral loads
from the impact of berthing ships and from waves.
Department of Civil Engineering, RVCE, 2019-20 Page 17
Pile foundations can be used either in shallow or deep water, the link to the working
platform is what differs. In shallow water, the connection is typically made by a steel lattice
structure commonly called a jacket. This is the most used structure for fixed offshore
platforms. Piles can also be used as anchors in moored floating facilities.
There are two construction methods used for piles that are constructed offshore: driven
and grouted. The most commonly used are metallic driven piles because they are the most
reliable and have the easiest construction path.
i. DRIVEN PILES
Offshore, the most frequently used pile type is the open-ended steel pipe, which is driven into
the seabed by a hammer. Pile diameters range from 0.76 m up to 2.5 m, but exceptionally a
diameter of 5.1 m has been successfully used on offshore wind turbines. The wall thickness
may vary along the pile length, so it will be thicker where moment is greater (near the pile
head). Typical diameter to wall thickness ratios (d/t) are between 20 and 60. The lower value
represents the greatest curvature that can normally be achieved in a steel rolling machine.
The highest value represents a curvature beyond which wall-buckling or section ovalisation
effects can be common .
The process of installing an offshore driven pile through a steel jacket leg is illustrated in
Figure 18. First, the steel jacket is released onto the required location, where it will be
supported by mudmats. Mudmats are templates used in the bottom of the steel jacket to
avoid its undesirable penetration into soft soils, Figure 7 and Figure 19 shows four mudmats
at the bottom of a steel jacket structure. Then the first section of pile is lowered trough the
leg. A hammer is installed on the head of the pile, and is used to drive the first segment until
its limit, the pilling equipment is removed and another pile segment is lifted on and welded in
place. This weld is normally subjected to non-destructive testing, after which the hammer is
lifted back on, and the whole procedure starts again until the designed pile penetration is
achieved. Unless the jacket confines the pile, grout is injected into the annular space to
provide the structural connection between them.
ii. GROUTED PILES
Even though driven piles are the most common type used in the offshore environment,
there is also the equivalent of a bored pile. It involves the grouting of a steel section, which is
inserted in a previously drilled hole. Figure 21 shows the stages in construction of a drilled
and grouted pile. In order to avoid collapse of loose uncemented material near the seabed, it
is often necessary to drive a primary pile first; alternatively stabilizing mud can also be used.
GRAVITY ANCHORS
An anchoring system is normally required to provide resistance forces that are primarily
horizontal, with cyclic as well as static components. Gravity anchors consist of heavy weight steel
structures (box, or grillage), filled or covered with granular fill (either rock-fill, or heavier material
such as iron ore), and placed on the seafloor. Simply, the structural element is placed first, and
then the bulk fill is added.
Two different structures are represented in Figure , on the left is a conventional box anchor
filled with iron ore, which provides ballast, and on the right a covered grillage. The latter is
considerably more efficient in terms of quantity of steel for a given holding capacity, but is much
less efficient in terms of the quantity of ballast required. Design of this type of anchor is also more
complex since a variety of failures mode must be considered, ranging from sliding of the complete
berm, pulling out of the grillage, or combinations involving asymmetric mechanisms.
2.SUCTION CAISSONS
Although concrete caissons have been used, the majority of suction caissons are fabricated from
steel, which have a similar concept to steel buckets on shallow foundations. Suction caissons
operate as anchors, and vertical capacity is granted by the weight of the plug of soil inside and
the friction on the outer surfaces, and in addition, the characteristic negative end-bearing
resistance. The latter, as in a steel bucket, is the force required to separate the lower end of the
soil plug from the undisturbed soil.
Department of Civil Engineering, RVCE, 2019-20 Page 23
Typically, suction anchors are open at the bottom and closed at the top. They have large
diameters, typically more than 5 meters in diameter and are 20 to 30 meters in length, with a
length to diameter ratio (L/d) in the range of 3 to 6. Normally the cylinders have very high ratios
of diameter to wall thickness (d/t ~100 to 250), that require internal stiffeners to prevent
structural buckling during installation, and due to the large lateral loads imposed by taut
moorings. Mooring loads are applied by an anchor line attached to the side of the caisson at a
depth that optimises the holding capacity. Usually this requires the line of action of the load to
pass through a point on the axis at a depth of 60% to 70% of the embedded depth. Figure 33
illustrates the optimal depth (D*) of the padeye, from which it is possible to realise that a taut
wire does not require as deep a padeye as a catenary mooring.
7. CASE STUDY:
1. Case Study of Offshore Pile System Failure in Hurricane Ike
Platform EC368A is a 3-leg, steel jacket platform located in approximately 110 m of water
offshore the coast of Louisiana , installed in 2003 . The platform was constructed by placing the
jacket on the seafloor, driving the steel pipe piles through the jacket legs into the soils, connecting
the piles to the jacket legs with shims at the top of the legs, and then welding the platform deck
to the pile heads above the jacket legs. Piles A, B and C are all 1,220-mm (48-inch) diameter,
open-ended, steel pipe piles. The piles were fabricated using A36 steel. They were driven in
sections and welded in the field during installation. Pile A is a vertical pile that penetrates 80.8 m
below the seafloor. Piles B and C are double battered at 1-horizontal to 5-vertical (1H: 5V) away
from Pile A; they both penetrate 67.1 m below the seafloor. Platform EC368A was also equipped
with a well conductor north of Pile A. This vertical conductor, which contained an oil well, is a
508-mm (20-inch) diameter steel pipe with a wall thickness of 12.7 mm (0.5 inches). This
conductor was attached to the jacket via framing that allowed it to carry only horizontal loads. In
addition, Pile A also housed an oil well.
Department of Civil Engineering, RVCE, 2019-20 Page 26
The soil profile consists of two strata: a very soft, highly plastic, normally consolidated clay to a
depth of 4 m below the seafloor.underlain by a soft to hard, highly plastic, slightly
overconsolidated clay to the bottom of boring.
Pile Design
Ultimate Axial Capacity
The maximum side shear for undrained loading at any depth along a pile, fmax, was calculated
from
2.Failure Case Study of Offshore Battered Drilled Shafts Due to Seabed Rock Scouring
Construction of 3,440m long grand bridge crossing from A Island to B Island started in 2008 .
the foundation of bridge constructed is of group pile system.The bridge consists of a total of 38
piers with 31 of them founded on battered piles. soil is made of a layer of sedimentary sand,
weathered rock over granite and schist bedrock. The average water depth in the region of the
main bridge span is 20~23 m. The piers in the shallow depth region consist of four drilled shafts
with a diameter equal to 1.8 m. Piers in the deep regions consist of four drilled shafts with a
diameter equal to 1.8 m battered to enhance the lateral resistance.the piers supporting the main
bridge span, six 2.5 m diameter battered drilled shafts are used for high lateral resistance. In
August 2011 during construction, pier No. 21 of the 34 piers bridge, collapsed overnight. A month
later, pier No. 18 also collapsed.The pile foundation of the collapsed piers was investigated, and it
was found that the piles showed tensile failure in the bearing layer of weathered rocks. High tidal
velocities and waves also cause scour around the piles which is a potential safety hazard Due to
the high flow velocities at the construction site, seabed scour was assumed to be the main cause
of pile failure ,particularly large amount of seabed scour was observed at the location ofpier P17
through P19.