Group members ; Ansul Agrawal, Diya Garg, Rojan Shakya, Rohit Kumar Agrawal.

Vivek Vashista.

1. Prepare a Scope Statement and a Work Breakdown Structure for the project.

Project Objective: To construct a high-quality, 2.5 storeyed home at Bhaisepati


within 12 months at a cost not exceeding Rs. 3 crore.

Scope Statement:
Project Title: Bhaisepati Home Construction Project
Project Objective: Construct a high-quality, 2.5-storeyed home at Bhaisepati within
12 months at a cost not exceeding Rs. 3 crore.
Project Justification: To provide a durable and pleasing residence within the
specified budget and timeline.
Product Scope Description: The project encompasses the construction of a 2.5-
storeyed home, complying with architectural and structural standards.
Deliverables:
1. Architectural and structural design plans
2. Clearing and preparation of the construction site
3. Foundation construction
4. Framing and construction of walls
5. Roofing installation
6. Flooring installation
7. Electrical and plumbing installations
8. Painting and finishing work
9. Landscaping
Milestones:
1. Obtain necessary permits and approvals
2. Finalize architectural and structural designs
3. Complete land preparation and clear
4. Finish foundation construction
5. Complete framing and wall construction
6. Roofing and flooring installation completed
7. Electrical and plumbing installations finalized
8. Finish painting and finishing work
9. Landscaping completed

Technical Requirements:
1. Compliance with local building codes and regulations.
2. Utilization of high-quality construction materials.
3. Implementation of energy-efficient and sustainable construction practices.
4. Incorporation of modern amenities and safety features.
Limits and Exclusions:
1. Acquisition of land is not included in the project scope.
2. Interior furniture and decoration are excluded.
3. Ongoing maintenance post-construction is not within the project scope.
Assumptions:
1. Availability of necessary permits and approvals.
2. Stable weather conditions for construction.
3. Availability of skilled labor and construction materials.
Project Stakeholders:
• Project Manager
• Architect
• Construction Team
• Suppliers
• Regulatory Authorities
• Homeowner
Work Breakdown Structure:
Home Construction

Project Initialization Design Phase

1.1 Define Project Scope 2.1 Architectural Design

1.2 Obtain Necessary


2.2 Structural Design
Permits and Approvals

2.3 Obtain Design


1.3 Set Up Project Team
Approvals

Pre-Construction Construction Phase

3.1 Land Preparation and


4.1 Framing
Clearing

3.2 Foundation Design


4.2 Wall Construction
and Construction

3.3 Utility Hookups 4.3 Roofing

4.4 Flooring

4.5 Electrical
Installations

4.6 Plumbing
Installations
Finishing Phase Landscaping

5.1 Interior Painting 6.1 Garden Design

5.2 Exterior Painting 6.2 Planting

5.3 Installation of
6.3 Hardscaping
Fixtures and Appliance

Quality Assurance and


Project Closeout
Inspections

7.1 Regular Inspections 8.1 Final Inspection

8.2 Handover to
7.2 Quality Checks
Homeowner

8.3 Document Project


Lessons Learned

This Work Breakdown Structure provides a hierarchical breakdown of the project into
phases and tasks, ensuring a systematic approach to achieving the project objective.