Project Risk Management

Assignment 02
Construction Project: Define baseline scope, WBS, and RBS

Submitted To: Dr. Mutahir


Submitted By: Mariam Ghaffar
2018- MBA (2.5)-304

Institute of Business Management


University of Engineering and Technology, Lahore
House Construction
Baseline scope:
Size: 494 sq feet house (26'×19')
One bedroom with attached bathroom.
Open kitchen with living room.
Time: 21 weeks.
Start: November 10, 2020.
End: April 17, 2021.
Cost: RS 9 million.
Main Deliverable: Complete house

Work Breakdown Structure (WBS)

1. House Construction 494 sq feet.


Task Duration
Project start (start milestone) November 10, 2020.
1.1 Design of structural and architectural drawings. 2 weeks.
1.2 Mobilization. 1 week.
1.3 Grading. 1 week.
Survey and mark out site.
Grade site.
1.3 Foundation. 3 weeks.
Digging of foundation pits.
Construction of foundation.
1.5 Structure. 4 weeks.
Construction of side walls.
Roofing.
Interior.
Mechanical. 1 week.
Piping and plumbing.
Electrical. 1 week.
Installing wiring and breaker box.
Finishing wiring.
Decor. 2 weeks.
Fabrication of doors and windows.
Fixing of doors and windows.
Installing door casings and baseboards.
Installing kitchen cabinets.
1.6 Flooring. 3 weeks.
1.7 Paints and fixtures. 2 weeks
1.8 Finishing. 1 week.
Project complete (finish milestone) April 17, 2021.
Risk Breakdown Structure (RBS)

House Construction (RBS)

Technical, Quality/
Project Management External
Performance
Owner involvement in design. Poor project management. Natural disasters.
Inadequate and Poorly written contracts. Safety hazards that lead to
incomplete design. Changes in the scope of worker accidents and injuries.
Incomplete or wrong surveys of project. Labor shortages.
site. Inflation. Damage or theft to equipment
Wrong selection of materials. and tools
Unexpected increases in
Labour disputes. material costs.
Defective Work.