You are on page 1of 9

RELIABILITY RUN REPORT – SEPTEMBER 2023

FOR

9.0 MWac SELF CONSUMPTION LARGE SCALE SOLAR PHOTOVOLTAIC


(SELCO-LSSPV) PLANT, SUNGAI SELANGOR PHASE 2 (SSP2) WATER
TREATMENT PLANT, 45000 BESTARI JAYA, SELANGOR.

Developer:

HELIOSEL SDN BHD


34-36, Jalam SS22/21,
Damansara Jaya,
47400 Petaling Jaya, Selangor.

EPCC:

SAMAIDEN SDN BHD


7, Lorong Teknologi 3/4A Nouvelle Industrial Park 2
Taman Sains Selangor,
1, Kota Damansara, 47810 Petaling Jaya, Selangor

[Report No: SAM-SEL-AISHB-REP(RR)-0001]


Prepared by: Reviewed by:

………………………………………………… ……………………………………………………
Nurnajihah Binti Azafen Mohd Makhzumi Bin Ghazali
Technical Engineer Project Director
(Samaiden Sdn Bhd) (Samaiden Sdn Bhd)
1.0 INTRODUCTION

The 9.0 MWac Self Consumption Large Scale Solar Photovoltaic (Selco-LSSPV) plant has
operated since 20th April 2023 (from now on referred to as “the Plant”). This Selco-LSSPV
plant located in Sungai Selangor Phase 2 (SSP2) Water Treatment Plant, 45000 Bestari
Jaya, Selangor.

The maximum Plant AC Output is 9 MWac and while Plant DC capacity is 11.7216 Wdc
Peak. The generated Solar PV Energy exported to SSP2 WTP for own consumption,
through Point of Common Coupling (PCC) at 33kV SSP2 WTP Substation. The 33kV
Underground XLPE Cable is used as a medium of energy transmission from LSSPV Plant
to the Substation.

The main objective of this report is to conduct Reliability Run Test which is one of the test
requirements based on SEDA guideline. The reliability of the system is tested by using
Performance Ratio Test.

2.0 PLANT OVERVIEW

The summary of the PV system for this project is as below table: -


Overall LSSPV Plant Capacity
System Peak Capacity (DC) 11.7216 MWp_dc
System Capacity (AC) 9.0 MWac
Total No of String 555 String.
No of modules per string 32 Modules per string
String Inverter
Brand Huawei
Type SUN 2000-215KTL
Number of Units 44 nos
Unit Capacity 215 kW
PV Modules
Brand Trina
Type TSM-650DEG21C.20
Unit Capacity 650 W
Total no of module 17,760 pcs
Smart Transformer Station
Brand Huawei
Type STS 6000k-H1
Unit Capacity 6.8 MW
Number of Units 2 nos
Medium Voltage Power Transformer
Brand Huawei
Type Oil-Immersed Power Transformer,
33/0.8kV
Capacity 6800 kVA
Unit 2 nos
3.0 RELIABILITY RUN REVIEW

3.1 Performance Ratio (PR)

The performance ratio (PR) is a measure of the quality of a PV plant that depends
on the irradiance data, and it, therefore, often described as a quality factor. The
closer the PR value determined for a PV plant approaches 100 %, the more
efficiently the respective PV plant is operating. PR is calculated by following
equations:-

Item Value
Module Efficency, η𝑚𝑜𝑑 21.2%
Area of Array, 𝐴𝑝𝑣 (m2) = L x W x Qty
=1.303m x 2.384m x 17,760pcs
= 55,168.81 m2

Accept if: PR is greater than or equal 0.8.

Energy yield and Irradiation data have been collected from SCADA monitoring
system which is logging by the logger for every 5 minutes. Based on the PR
calculation, the performance of the plant from 20th August 2023 until 10th
September 2023 (22days) have been pass with the result ratio from 0.82 to 1.12
(excluding the day of irradiation data loss).
Summary of Daily Plant Performance Ratio (PR) is as follow: -

Energy Yield, Specific Irradiation, Modules Area Solar


Performance Remarks
Day Date Yf Yield, SY H Efficiency, Modules, Apv Irradiation
Ratio
(kWh) (kWh/kWp) (kWh/m2) nmod (m2) Yield (kWh)
0 18/08/2023 1,501.64 0.13 0.212 55,168.81 0.00 IOD MVS2
0 19/08/2023 35,960.47 3.07 0.212 55,168.81 0.00 IOD MVS1
1 20/08/2023 48,316.22 4.12 4,378 0.212 55,168.81 51,204.16 0.94 Pass
2 21/08/2023 23,124.85 1.97 1,778 0.212 55,168.81 20,795.11 1.11 Pass
3 22/08/2023 19,674.24 1.68 953 0.212 55,168.81 11,146.09 1.77 Irradiation Data loss
4 23/08/2023 42,205.82 3.60 3,411 0.212 55,168.81 39,894.33 1.06 Pass
5 24/08/2023 47,627.73 4.06 4,181 0.212 55,168.81 48,900.09 0.97 Pass
6 25/08/2023 38,694.62 3.30 3,079 0.212 55,168.81 36,011.33 1.07 Pass
7 26/08/2023 42,911.99 3.66 3,323 0.212 55,168.81 38,865.10 1.10 Pass
8 27/08/2023 60,558.55 5.17 5,447 0.212 55,168.81 63,706.96 0.95 Pass
9 28/08/2023 32,163.78 2.74 2,791 0.212 55,168.81 32,642.94 0.99 Pass
10 29/08/2023 41,616.33 3.55 3,513 0.212 55,168.81 41,087.30 1.01 Pass
11 30/08/2023 58,293.28 4.97 5,205 0.212 55,168.81 60,876.58 0.96 Pass
12 31/08/2023 46,761.82 3.99 4,141 0.212 55,168.81 48,432.26 0.97 Pass
13 01/09/2023 43,235.60 3.69 3,535 0.212 55,168.81 41,344.61 1.05 Pass
14 02/09/2023 49,097.77 4.19 4,208 0.212 55,168.81 49,215.88 1.00 Pass
15 03/09/2023 38,818.98 3.31 2,969 0.212 55,168.81 34,724.79 1.12 Pass
16 04/09/2023 26,941.51 2.30 1,772 0.212 55,168.81 20,724.94 1.30 Irradiation Data loss
17 05/09/2023 43,789.60 3.74 3,707 0.212 55,168.81 43,356.29 1.01 Pass
18 06/09/2023 32,984.40 2.81 2,278 0.212 55,168.81 26,643.01 1.24 Irradiation Data loss
19 07/09/2023 43,875.01 3.74 4,594 0.212 55,168.81 53,730.45 0.82 Pass
20 08/09/2023 30,427.09 2.60 2,990 0.212 55,168.81 34,970.41 0.87 Pass
21 09/09/2023 45,299.57 3.86 4,016 0.212 55,168.81 46,970.28 0.96 Pass
22 10/09/2023 50,892.84 4.34 4,484 0.212 55,168.81 52,443.91 0.97 Pass
*Data collected and downloaded from the monitoring system
Daily Energy Yield and Performance Ratio

70,000 2.00

60,558.55 1.80
60,000 58,293.28
1.60
50,892.84
49,097.77
50,000 48,316.22 47,627.73 46,761.82 1.40

Performance Ratio, PR
43,875.01 45,299.57
43,235.60 43,789.60
Energy Yield (kWh)

42,205.82 42,911.99 41,616.33


38,694.62 38,818.98 1.20
40,000
32,163.78 32,984.40 1.00
30,427.09
30,000 26,941.51
0.80
23,124.85
19,674.24
20,000 0.60

0.40
10,000
0.20

0 0.00

Energy Yield PR
3.2 Capacity Test

Capacity Test is one of the requirements from the Developer to make sure plant
capacity is installed based on design at maximum output. The test is considered
pass if the plant output reached or greater than 9.0MWac at one time.

Based on the results, the plant have achieved maximum capacity test on 20 th
August 2023 and 24th August 2023. The Capacity Test have been considered
passed.

Summary of PV Solar generation is as follow: -

Max Generation Remarks


Day Date
(kW)

0 18/08/2023 1,221.53 IOD MVS2


0 19/08/2023 8,826.13 IOD MVS1
1 20/08/2023 9,283.84 Pass
2 21/08/2023 8,455.27
3 22/08/2023 4,642.88
4 23/08/2023 8,951.38
5 24/08/2023 9,180.20 Pass
6 25/08/2023 8,855.66
7 26/08/2023 8,838.64
8 27/08/2023 8,591.81
9 28/08/2023 8,849.83
10 29/08/2023 8,672.47
11 30/08/2023 8,796.15
12 31/08/2023 8,754.49
13 01/09/2023 8,603.18
14 02/09/2023 8,733.21
15 03/09/2023 8,620.61
16 04/09/2023 8,013.16
17 05/09/2023 8,747.65
18 06/09/2023 7,808.57
19 07/09/2023 8,297.29
20 08/09/2023 6,769.83
21 09/09/2023 8,890.56
22 10/09/2023 8,946.43
18/8/23 9:20:00 PM
7:25:00 AM
19/8/23 5:30:00 PM
3:35:00 AM
20/8/23 1:40:00 PM
11:45:00 PM
9283.842

21/8/23 9:50:00 AM
7:55:00 PM
6:00:00 AM
22/8/23 4:05:00 PM
2:10:00 AM
23/8/23 12:15:00 PM
10:20:00 PM
8:25:00 AM
24/8/23
6:30:00 PM
9180.2

4:35:00 AM
25/8/23 2:40:00 PM
12:45:00 AM
26/8/23 10:50:00 AM
8:55:00 PM
27/8/23 7:00:00 AM
5:05:00 PM
3:10:00 AM
28/8/23 1:15:00 PM
11:20:00 PM
29/8/23 9:25:00 AM
7:30:00 PM
5:35:00 AM
30/8/23 3:40:00 PM
1:45:00 AM
11:50:00 AM
P(kW)

31/8/23
9:55:00 PM
8:00:00 AM
1/9/23
6:05:00 PM
4:10:00 AM
2/9/23 2:15:00 PM
12:20:00 AM
3/9/23 10:25:00 AM
8:30:00 PM
6:35:00 AM
4/9/23 4:40:00 PM
2:45:00 AM
5/9/23 12:50:00 PM
10:55:00 PM
9:00:00 AM
6/9/23 7:05:00 PM
5:10:00 AM
7/9/23 3:15:00 PM
1:20:00 AM
8/9/23 11:25:00 AM
9:30:00 PM
7:35:00 AM
9/9/23 5:40:00 PM
3:45:00 AM
1:50:00 PM
10/9/23
11:55:00 PM
0
1000
2000
4000
5000
7000
8000
9000

3000
6000
10000

Power, W
4.0 CONCLUSION

As the conclusion, reliability run test have been passed as per result from the test
conducted from IOD, 20th August 2023 until 10th September 2023. Performance Ratio
have achieved above 0.8 (Pass value from SEDA guidelines) during the period of the
testing. Capacity test also have been achieved, which have reached 9.0MWac on 20th
August 2023 and 24th August 2023.