(For Storage Machines Only) e-Print Pro + Upgrade Checklist

Date: Start date of Installation:

Machine #: Completion date of Installation:

FSE Name: Total Days:

INSTALLATION REMARKS
Site Preparation
OK NOT OK
G G AC Power

G G Isolated Transformer (optional)


G G UPS (optional)

Unpacking the e-Print Pro boxes


G Check Shock & Tilt Sensors
G Check boxes for visible damage. Make sure that the two
main boxes supplied have the same Serial No. written
on the top.
Verifying the Box Contents
OK NOT OK
G G e-Print Pro Mainframe MPS-0160-01
G G Working Surface MPU-0080-51
G G PC Tower EAS-1003-71

G G 4/Jack Mount Pads MSQ-0010-01


G G Developer Drum MPX-0095-55
G G Cleaning Station MPX-0006-55
G G Reverse Roller Unit MPX-0018-56
G G Squeegee Roller MPX-0171-52
G G Exit Tray Assy MPX-3548-52
G G Slit Assembly MPX-4944-55

G G Accessories Kit MKT-1090-01


G G 4/M6x16 Knobs MKN-0006-04
mounted underneath mainframe
G G A/C (Air Conditioner) 60 Hz MPX-0014-64

G G Scorotron MPX-0128-56

2 Aug 99 2
PROPRIETARY AND CONFIDENTIAL
(For Storage Machines Only) e-Print Pro + Upgrade Checklist

INSTALLATION REMARKS
G G Monitor 17” EBC-0110-01
G G Mouse EBC-1026-01
G G Keyboard EBC-1027-02
G G PC Computer EBC-1035-53
G G Paper Chromo 135 gr. MPR-1600-09

Unpacking the e-Print Pro Mainframe


G Remove four bolts securing the e-Print Pro mainframe
using a 13 mm wrench
G Verify that 4 screwjack mounts (M6x16 knobs) are in
highest position
G Lift e-Print Pro and stand on its four wheels
Installing the e-Print Pro
G Move e-Print Pro to fixed position
G Cut away all attached plastic strips, tags (tiewraps)
G Remove oil from Developer Station Wipers
G Remove masking tape
Positioning the e-Print Pro Mainframe
G Lower jack mounts unto pads
G Verify mainframe height is correct for PC cabinet and
about 10 mm above floor
Do not adjust e-Print Pro mainframe to a final level at
this point in the installation
Assembling the e-Print Pro

G Insert monitor in position and lock attachment screws


G Place keyboard and mouse on a Working Surface.
Connect cables to mainframe
Unpack, inspect, clean and insert the following:
G Squeegee Roller unit
G Reverse Roller Assembly
G Exit Tray Assembly
G Scorotron
G Cleaning Station
G Developer Drum
G Air Conditioner unit
G Clear area around machine

3 Aug 99 3
PROPRIETARY AND CONFIDENTIAL
(For Storage Machines Only) e-Print Pro + Upgrade Checklist

INSTALLATION REMARKS
Check & Adjust the level of e-Print Pro

G Verify level of mainframe at:


• Top surfaces of side frame where Writing Head is
aligned
• Across ruled bar above paper feeder
G Verify machine rests firmly on all jack mount pads
Attach PC Tower

G Position PC Tower and lock brackets


G Verify that all four PC Tower wheels are on the floor
G Connect following cables to PC Tower:
W18 to J2
W16 to J3
W143 to P20 at REC side
W48 to P21 at REC side
Install PC Computer

G Install the Computer to the PC Tower


G Connect the cables to the PC
G Lock the PC Tower door
Before Operating the e- Print Pro

G Verify Mains power supply is suitable for the country


G Verify receipt of correct Voltage Template
G Install Voltage Template inside Rear Electrical Cabinet
(REC)
G Set Auto Transformer (Voltage Selector) dial to correct
voltage
G Select correct Set Frequency of Inverter for country of
installation
Power Up Tests
G Verify that mains circuit breaker on e-Print Pro machine is
OFF
G Disconnect UPS bridge
G Connect machine’s mains cable to site’s power supply

4 Aug 99 4
PROPRIETARY AND CONFIDENTIAL
(For Storage Machines Only) e-Print Pro + Upgrade Checklist

INSTALLATION REMARKS
G Verify that site’s circuit breaker is ON
WARNING: System is electrically alive. Take care not
touch any live parts inside electrical cabinet

Using a Digital Voltmeter (DVM) and electrical drawings:


G Verify voltages and phases on TB1 for:
Country Voltage Conn. Phase
USA G 21B-18B 208 VAC ± 10%
G 21B-14B 208 VAC ± 10%
G 18B-14B 208 VAC ± 10%
Europe / UK G 21B-19B 220÷240 VAC ± 10%
G 18B-19B 220÷240 VAC ± 10%
G 14B-19B 220÷240 VAC ± 10%
G 21B-18B 380÷415 VAC ± 10%
G 21B-14B 380÷415 VAC ± 10%
G 18B-14B 380÷415 VAC ± 10%
IF THE ABOVE IS CORRECT
G Switch ON e-Print Pro machine’s main circuit
breaker
G Verify voltages to:
G RLA
G RLB
G RLC
G UPS
IF THE ABOVE IS CORRECT
G Switch OFF e-Print Pro machine’s main circuit breaker
G Connect UPS bridge and close cover
G Fill Separator with Imaging Oil
G Powerup e-Print Pro machine
G Insert the Technician key
Insert the Bypass Key as necessary

G Bypass Writing Head by entering Systab Editor:


EngineConfigTopic>WhifType
Change WhifType From WHIF_8051

5 Aug 99 5
PROPRIETARY AND CONFIDENTIAL
(For Storage Machines Only) e-Print Pro + Upgrade Checklist

INSTALLATION REMARKS
To WHIF_NOT_INSTALLED

Functionality Diagnostics
G Lower the Paper Feed Elevator
G Make sure that the machine is in Engaged Mode
G Open Diagnostics window
G Insert the Bypass Key
G Check following elements:
OK NOT ELEMENT MMI WINDOW
OK
G G Motor Inch Diagnostics>Substrate>Main
Motor
G G From the MMI: Diagnostics>Substrate>
Electronically engage Electronic Engage
the system (PIP &
IMP)
G G Vacuum Pump Diagnostics>Substrate>Feed
G G All Solenoids Diagnostics>Substrate>Feed
G G Lift Motor Diagnostics>Substrate>Lift
G G Drain Cooler Pump Diagnostics>Process>Machine
Temp. Control
G G Scorotron Wire Motor Diagnostics>Process>Elements
G G PTE Lamp Diagnostics>Process>Element
G G Home Wipers Diagnostics>Ink>Flow
G G Imaging Oil Add Valve Diagnostics>Imaging
Oil>Separator
G G Separator Pumps Diagnostics>Imaging
Oil>Separator

G Run main motor (Inching) and check for noise or


vibration
G Run main motor at Full Speed
G Engage press ON then OFF and check slit
movement

General Checks

G Oil the Grippers Assembly


G Oil & Grease machine according to Weekly Routine

6 Aug 99 6
PROPRIETARY AND CONFIDENTIAL
(For Storage Machines Only) e-Print Pro + Upgrade Checklist

INSTALLATION REMARKS
Adjustments and Pre-Operation Preparations
Check paper flow paths using the provided Maxpaper
for 10 sheets using:
G Simplex
G Shutdown the Machine
G Perform the e-Print Pro upgrade MKT-0820-AI

7 Aug 99 7
PROPRIETARY AND CONFIDENTIAL
UPGRADE FEEDBACK
This form should be completed immediately after implementation of the
Upgrade and sent by fax to:
ATT: Customer Support
Yiftach Estrik
Indigo
FAX: (972)-8-9381338
(972)-8-9381339
DATE (MM/DD/YY):
UPGRADE NUMBER:
MACHINE SERIAL NUMBER:
CUSTOMER NAME:
COUNTRY/STATE:
TECHNICIAN NAME:
TEL:
FAX:
TIME SPENT ON INSTALLATION:

HOW MUCH TIME DID YOU SPEND ON


THE FOLLOWING?:
• PREINSTALLATION ADJUSTMENTS
• INSTALLATION PROCEDURE
• TESTING AND FINAL ADJUSTMENTS
W ERE THE INSTRUCTIONS IN THIS
UPGRADE SUFFICIENTLY CLEAR?

DID YOU NEED ANY ADDITIONAL


TOOLS/ACCESSORIES?

W ERE THERE ANY SPECIFIC


DIFFICULTIES OR PROBLEMS IN
IMPLEMENTING THIS UPGRADE?

GENERAL REMARKS:

(For Storage Machines Only) page 8 of 9


Proprietary and Confidential
e-Print Pro+ Upgrade Checklist

Thank you for your cooperation

(For Storage Machines Only) page 9 of 9


Proprietary and Confidential