Professional Documents
Culture Documents
Prepared by
Bechtel Power Corporation
San Francisco, California
I/'
D IS C L A IM E R
AF-610
State-of-the-Art 77-402
Prepared by
,5°
BECHTEL POWER CORPORATION
San Francisco Power Division
50 Beale Street
RO. Box 3965
San Francisco, California 94119
Prepared for
iii
Blank Page
CONTENTS
COMBINED CYCLE POWER PLANT
CAPITAL COST ESTIMATES
PAGES
INTRODUCTION & SUMMARY (Purpose of study, and ground
rules for establishing six plants: summary of plant xi
arrangement and design, and summary of capital cost
estimates)
1. POWER PLANT DATA (Power plant data and fuel analyses 1-1
established for the plants to be estimated)
v
Blank Page
FIGURES
TEXT
FIGURE TEXT
NO ■ PAGE
9A SIMPLE OPEN-CYCLE GAS TURBINE NET EFFICIENCY 9-2
VARIATION WITH COMPRESSOR PRESSURE RATIO
FOR VARIOUS TURBINE INLET TEMPERATURES
APPENDIX APPENDIX
FIGURE PAGE
vii
Blank Page
TABLES
TABLE PAGE
NO. NO.
ix
Blank Page
INTRODUCTION AND SUMMARY
INTRODUCTION
Electric Power Research Institute, EPRI, Palo Alto, CA has re
tained the Bechtel Power Corporation, San Francisco, CA to pre
pare capital cost estimates for standard combined-cycle power
plants in six locations of the United States. Each of the plants
will be the oil-fueled, high efficiency, preengineered and pack
aged plants commercially available in the U.S. in late 1976.
This report and the cost estimates are intended to be repre
sentative of plants offered by all U.S. suppliers and not based
on plants offered by any particular U.S. manufacturer.
Plant megawatt output was established as a nominal 250 MWe net
for the single unit plant and a nominal 500 MWe for the double
unit plant. Actual power output for a plant at a known alti
tude and ambient temperature would likely be different. For
actual future plants, of 250 MWe and 500 MWe output, other
combinations of units might be more advantageous for the Owner.
This study presents the state-of-the-art of combined-cycle plants
in 1976 as part of a broad examination of the total costs to
produce electricity by different methods now and in the next
twenty years. EPRI will use this study as a reference document
to improve industry and public understanding of such present and
future electric power costs.
Six plants were established for this study in the regions and
near the cities listed below.
Plant Region State Nearest City
xi
governing emissions than the National Standards.
All plants are to meet current (1976) requirements of the
Environmental Protection Agency (EPA) for new Source Perform
ance Standards (NSPS) or the stricter rules and regulations at
the locations of Plants 3 and 4.
SUMMARY
Plant Arrangements
Plant arrangement of the major equipment depends, on large mea
sure, on the supplier of the major equipment. For example, for
the 250 MWe plant, one major supplier would offer eight gas tur
bine generators and two heat recovery steam generators (HRSG's).
Other offerings could be three gas turbines, three gas turbine
generators and three HRSG's; or eight gas turbines, four gas
turbine generators and four HRSG's; or two gas turbines with two
gas turbine generators and two HRSG's could be developed. All
plants would have one steam turbine generator. Balance of
plant facilities are not significantly different from one manu
facturer to the other. All gas turbines would have bypass
stacks for the exhaust gas.
This report and its cost estimates cover a composite plant, rep
resentative of available technology for the major equipment and
balance of plant facilities. This report and its cost estimates
do not distinguish between the different suppliers and their
plant arrangements, or between relatively small differences in
generation output, heat rate, and control system performance.
Some of the latter facilities such as the cooling towers do re
flect site related differences in performance and cost. Site
situations requiring special equipment for handling airborne
particulates-sand and dust-or airborne chemicals-salt spray and
chemical fumes-are not considered.
xii
Requirements for Fuels
Capital cost estimates for Plant No. 2, 5% lower than Plant No.
1, reflect a large decrease in labor and labor related costs
at this location even though the site sensitive cooling towers
are estimated to be higher in cost.
Capital cost estimates for Plant No. 3 are 10% more than Plant
No. 1, if the plant is considered to be at a remote location.
These estimates reflect the site sensitive costs for a longer
access road and railroad to the site and higher labor costs for
incentives to attract and hold craftsmen in the numbers and
skills required to build the plant.
xiv
If the plant site is not in a remote location, the capital costs
estimates for Plant No. 3 are only 5% more than Plant No. 1. It
is more likely that a plant of this size and type would be lo
cated near a populated center as are the other plants in this
study.
Capital cost estimates for Plant No. 5, 9% more than Plant No.
1, reflect a significant increase in labor costs and an increase
in site sensitive costs.
Capital cost estimates for Plant No. 6, 2% lower than Plant No.
1, reflect a large decrease in labor costs and increased site
sensitive costs for a longer access road and railroad and a
larger cooling tower.
xv
1.0 POWER PLANT DATA
1-1
1.2 Plant Operation Data
1-2
Standards for sulfur dioxide emissions, as SO2, are 0.80
Ib/million Btu for Federal EPA-NSPS and 200 Ib/hour for
each release point or gas turbine for California's South
Coast Air Basin, Los Angeles Area (CA(LA)). Oregon also
has a severe restriction on SO2 emissions from plants
burning distillates of 0.50% by weight of S in the fuel.
The restrictions on plants burning residuals is the same
as NSPS.
1-3
To meet the acceptable plume opacity levels, the hydrogen
content of the fuel needs to be limited to a minimum of
not less than approximately 12% for distillate fuels and
11% for the residual fuels.
In general, the higher the hydrogen content in the fuel,
the lower the smoke level.
1-4
1.3.3 Solid Wastes and Disposal
1-5
1.5 Other Fuel Requirements
After natural gas, petroleum oils are the next most widely
used gas turbine fuels. Light distillates are preferred
for technical reasons, but because of price and avail
ability, heavy distillates and even crude oils, are being
used as fuels.
The blended residuals, crudes and heavy residuals are
rather viscous at ambient temperatures and require heat
ing systems to reduce viscosities to acceptable levels
for pumping and atomization in the combustors.
These fuels also require cleaning to reduce alkali metals
or ash content. Alkali metals can be removed by water
washing and the addition of inhibitors followed by cen
trifuging to remove the water. Ash solids can also be
removed by electrostatic precipitation of the oil.
1.6 Maintenance Requirements
1-6
Frequency and rate of starting the gas turbine of a com
bined cycle power plant also affect component life and
therefore maintenance costs. As indicated on Figure 1C,
middle curve, from one start every 100 operating hours
to one start every hour, the relative maintenance cost
can vary by a factor of six.
Load duty does not markedly affect maintenance for tur
bines operated in the operating range up to 100 percent
of machine base load. Figure 1C, bottom curve, shows
collective experience for General Electric gas turbines,
including the drastic increase in maintenance cost re
sulting from excessive loading beyond the base load.
1-7
TABLE 1-1
SITE DATA
PLANT NO. 1 2 3 4 5 6
REGION Great Lakes Southwes t Western West ern Northeast Southeast
STATE Wisconsin Texa s Oregon California Pennsylvania Georgia
NEAREST TOWN Keno sha Freeport H e rmis ton Los Angeles Bethlehem Albany
Foundation Type Timber Piles Timber Piles Spread Spread Spread Spread
& Spread Ftgs & Spread Ftgs Footings Footings Footings Footings
BLENDED
NO. 2 RESIDUALS HEAVY
KEROSENE DISTILLATE AND CRUDES RESIDUALS
ISO
PLANT NO. 1 2 3 4 5 6 Standard
ALTITUDE, ft 588 Sea Level 627 275 399 196 Sea Leve!
ATMOSPHERIC PRESSURE, psia 14.39 14.70 14.37 14.55 14.49 14.60 14.7
AIR TEMPERATURE, °F 83 90 92 83 85 92 59
(July Mean High)
AUXILIARY POWER, MW 2 9 9 9 9 9 9 9
FUEL FLOW, Ib/hr 116,833 117,389 114,192 118,148 117,098 116,037 126,388
(HHV = 19,430 Btu/lb)
GROSS HEAT RATE, Btu/KWh 3 8,079 8,038 8,098 8,083 8,097 8,081 8,078
NET HEAT RATE, Btu/KWh 3 8,346 8,355 8,373 8,348 8,365 8,350 8,324
NET PLANT EFFICIENCY, % 40.9 40.9 40.8 40.9 40.8 40.9 41.0
AUXILIARY POWER, MW 2 10 10 10 10 10 10 10
FUEL FLOW, Ib/hr 118,874 119,440 116,187 120,212 119,144 118,064 128,596
(HHV = 18,300 Btu/lb)
GROSS HEAT RATE, Btu/KWh 3 8,117 8,125 8,146 8,118 8,136 8,122 8,115
NET HEAT RATE, Btu/KWh 3 8,432 8,439 8,471 8,429 8,451 8,440 8,405
NET PLANT EFFICIENCY, % 40.5 40.4 40.3 40.5 40.4 40.4 40.6
Notes1 2 3
1 For purposes of this study the effect of differences in cooling tower performance
and condenser vacuum conditions have not been considered.
1-10
2.0 PLANT NO. 1 - GREAT LAKES LOCATION - CURRENT EPA
STANDARDS (BASE DESIGN)
A one mile long road and two mile railroad spur are
assumed to be required for access. The raw water makeup
for the plant is approximately 1,600 gpm, and wells are
assumed to be the primary supply source, supported by a
connection to the Kenosha Municipal Water System.
2-1
2.2 Plant Arrangements
Four plants are considered at this location for this
study—a single unit plant, nominal 250 MW burning distil
late fuels; a double unit, nominal 500 MW plant, (two-
250 MW units) burning distillate fuels; and the same two
plants burning blended residuals and crudes and heavy
residuals.
Plot plans and plant arrangements are described below and
shown in the Appendix on Figures 2A-1, 2A-2, 2A-3 and 2A-4.
2-2
These components are designed for intermediate load duty
broadly defined as cyclic operation with annual load
factors between 20% and 80%. Units are capable of sus
tained full power operation, and it is expected that in
practice, the units will be operated at approximately
80-90% capacity, fifty to sixty percent of the year for
an overall capacity factor of 50%.
2-3
2.4 Fuel Oil System
2-4
2.4.3 Residual Fuel Treatment and Storage
2-5
2.5.2 Raw Water and Fire Protection System
2-6
The heat exchanger for this closed system is located
adjacent to the Power Block area. The unit is a
horizontal shell and straight tube type with two
divided water boxes of 50% capacity. It receives
in the shell side the hot water used to cool all
the internals of the power block and on the tube
side, it receives the service water from the cooling
tower sump. This exchanger is in continuous opera
tion when the plant is operating.
2.5.5 Circulating Water System
2-7
2.7 Switchyard
The switchyard serves the generating units, startup
transformers, transmission lines and an emergency
supply line of lower voltage (115 KV). The switch
yard would be equipped with circuit breakers, battery
operated disconnect switches, line traps, potential
devices and lightning arresters. Also included are
foundations, control building, supporting structures
and take-off towers.
2-8
3.0 PLANT NO. 2 SOUTHWEST LOCATION CURRENT EPA STANDARDS
A one mile long road and a two mile railroad are assumed
to be required for access to the plant.
Soil condition at the site are assumed to be similar to
those for Plant No. 1, and require the use of timber
piles to support the major equipment.
3-1
4.0 PLANT NO. 3 - WESTERN LOCATION - CURRENT EPA STANDARDS
4-1
4.3 Environmental Regulations (Cont'd)
4-2
5.0 PLANT NO. 4 - WESTERN LOCATION METROPOLITAN ZONE (L.A.)
STANDARDS
Combined cycle plants at this location would be considered
typical for plants in the Southern California, South Coast
Air Basin region of the United States. The plant fuels
would be delivered by rail to the site. As described be
low, the emissions standards of this air basin will permit
only distillates to be used as fuels in this area.
The access road and access railroad required for the plant
are each assumed to be one-half mile long.
5-1
South Coast Air Basin Air Quality Standards for sulfur
dioxides stated in Appendix, Figure 3A limits the SO2
emissions to 200 Ibs/hr per source. This is approximately
one-third of the allowable federal EPA rate. To meet this
standard without construction of a flue gas desulfuri
zation facility, which is excluded from the scope of this
study, a maximum sulfur content of the fuel can be only
0.25% by weight. (This is assuming three sources, i.e.
three gas turbines.) Most blended residuals and crudes
and heavy residuals have much higher sulfur content. See
Table 1-2, Typical Properties, Liquid Fuels. Therefore,
most of these fuels cannot be considered for use at this
site. In fact, as shown on Table 1-2, not all distillates
have such a low sulfur content. Only low sulfur blended
residuals and crudes and No. 2 distillates can meet this
0.25% limitation.
5-2
6.0 PLANT NO. 5 ^ NORTHEAST LOCATION - CURRENT EPA
STANDARDS
Combined cycle plants at this location would be considered
typical for plants in the Northeast region of the United
States. The plant fuels, either distillates or blended
residuals, would be delivered by rail to the site. For
purposes of this study, the plant location is near
Bethlehem, Pennsylvania. See Figure 1 in the Appendix.
A two mile long road and four mile railroad spur are
assumed to be required for access to the plant. Foundation
conditions are assumed to be good bearing soil or rock
which can support the plant on spread footing foundations
without piles.
6-1
7.0 PLANT NO. 6 - SOUTHEAST LOCATION - CURRENT EPA STANDARDS
Combined cycle plants at this location would be considered
typical for such plants in the Southeast region of the
United States. The plant fuels, either distillates or
blended residuals and crudes and heavy residuals, would
be delivered by rail to the site. For purposes of this
study, the plant location is near Albany, Georgia. See
Appendix, Figure 1.
7-1
8.0 CAPITAL COST ESTIMATES
8-1
8.3.1 Land and Land Rights; Licenses and Permits
8-2
8.4.2 Transmission and Distribution
8-3
facilities, food subsidies, free transporation, and
the like, are assumed to add 15% to the cost of labor
at this site.
8.8 Escalation
8-4
of expenditures is four months later than for the first
unit. Therefore, the costs of the second unit are subject
to an additional four months of escalation.
Distillate Residual
2x250 MW 2x250 MW
Units 1st 2nd 1st 2nd
PLANT NO. 1 2 3 4 5 6
SITE NEAR KENOSHA FREEPORT HERMISTON LOS ANGELES BETHLEHEM ALBANY
STATE WI TX OR CA PA GA
FUEL OIL TYPE DISTILLATE DISTILLATE DISTILLATE DISTILLATE DISTILLATE DISTILLATE
EMISSIONS STANDARDS EPA EPA EPA/OR CA (LA) 67 EPA EPA
PLANT MWe NET - 1 UNIT 1 x 272 1 x 273 1 x 265 ) X 275 1 x 272 1 x 270
ITEM S MILLIONS
20 Civil/Structural/Architectural
21,22 Structural & Misc. Iron & Steel 0.11 0.10 0.12 0.12 0.12 0.10
25 Architectural & Finish 0.25 0.23 0.28 0.25 0.28 0.23
26 Earthwork 1.29 1.12 2.61 0.90 2.15 2.02
27 Piles & Caissons 0.13 0.12 - - -
28 Site Improvements 1.65 1.52 3.02 1.23 2.57 2.63
30 Heat Recovery Steam Generators 11.45 10.56 12.66 11.2.7 12.73 10.85
Engineering & Home Office Services, 4.77 4.67 4.97 4.72 4.95 4.75
Including Fees
Allowance For Funds During Con- 6.52 6.21 7.22 6.41 7.15 6.44
struction (8%)
(3.90)(1)
Total Estimated Project Cost S88.00 $83.60 $97.10 $93.20 $86.00 $96.40 $87.40
at July 1, 1976 Price Level for
Plant Comoletion - August 1, 1977
Distillate Fuel Use
Additional Cost For Residual 6.50 5.80 7.50 6.90 6.40 2) 7.50 6.00
Fuel Use
Total Estimated Project Cost $94.50 $89.40 $104.60 $100.10 $92.40 $103.90 $93.40
At July 1, 1976 Price Level
Residual Fuel Use
$/kW - Distillate Fuel Use $324/kW $306/kW $366/kW $352/kW $313/kW $354/kW $324/kW
PLANT MWe NET - 1 UNIT 1 x 258 1 x 259 1 x 251 lx 261 1 x 258 1 x 256
RESIDUAL FUEL USE
$/kW - Residual Fuel Use $366/kW $345/kW $417/kW $399/kW $354/kW $403/kW $365/kW
(1) Adjustment for a Western Site 2) This plant is not permitted under the present
Not In A Remote Location regulations. See Pgs 1-3 and 5-2.
8-6
TABLE 8-2
PLANT 1 2 3 4 5 6
SITE NEAR KENOSHA FREEPORT HERMISTON LOS ANGELES BETHLEHEM ALBANY
STATE WI TX OR CA PA GA
FUEL OIL TYPE DISTILLATE DIS TILLATE DIS TILLATE DISTILLATE DISTILLATE DISTILLATE
EMISSIONS STANDARDS EPA EPA EPA/OR CA(LA) 67 EPA EPA
PLANT MWe NET - 2 EQUAL SIZE UNITS 2x272 2x273 2x265 2x275 2x272 2x270
ITEM $ MILLIONS
20 Civil/Structural/Architectural
21,22 Structural & Misc. Iron & Steel 0.19 0.17 0.23 0.21 0.22 0.18
25 Architectural & Finish 0.46 0.42 0.51 0.45 0.51 0.43
26 Earthwork 1.95 1.70 3.37 1.54 2.85 2.63
27 Piles & Caissons 0.25 - 0.23 - - _ -
28 Site Improvements 2.31 2.12 3.77 1.87 3.31 3.25
30 Heat Recovery Steam Generators 22.90 21.12 25.32 22.54 25.46 21.69
Engineering & Home Office Services, 7.01 6.87 7.26 6.96 7.25 6.95
Including Fees
Total Estimated Plant Cost $148.10 $140.80 $160.80 $145.50 $160.40 $145.10
Other Owners Costs (5%) 7.41 7.04 8.04 7.28 8.02 7.26
Allowance for Funds During Cons- 12.49 11.86 13.46 12.22 13.48 12.14
truction (8%)
( 7.10:I1)
Total Estimated Project Coot at $168.00 $159.70 $182.30 $175.20 $165.00 $181.90 $164.50
July 1, 1976 Price Level for
Plant Completion - October 1, 1977
Distillate Fuel Use
Total Estimated Project Cost $180.70 $171.00 $197.00 $188.70 $177.40 $196.70 $176.30
At July 1, 1976 Price Level
Residual Fuel Use
$/kW - Distillate Fuel Use $309/kW $292/kW $344/kW $331/kW $300/kW $334/kW $305/kW
PLANT MWe NET - 2 EQUAL SIZE 2 x 258 2 x 259 2 x 251 2 x 261 2 x 258 2 x 256
UNITS - RESIDUAL FUEL USE
$/kW - Residual Fuel Use $350/kW $330/kW $392/kW $376/kW $340/kW $381/kW $344/kW
8-7
TABLE 8-3
ORDER OF MAGNITUDE
CAPITAL COST ESTIMATE SUMMARIES
ESCALATED TO 1985, 1990 & 1995
IN $/KW
(Distillate Fuel)
(Residual Fuel)
2 x 250 MW Unit
IN $/KW
(Distillate Fuel)
8-8
9. FUTURE DEVELOPMENTS
9-1
.45 -| TURBINE INLET
CONDITIONS:
TEMPERATURE °F
COMPRESSOR EFFICIENCY = 0.85
COMBUSTION EFFICIENCY = 0.98 f3000
- 8 < 2600
\2400
2000
.40 -
1750
- 9
cc
<
CD
=3
V)
D I—
m .35 - CD
I- -10 b
o
< o
> 1500
o
z
UJ UJ
o -11
H
<
CC
it .30 H
LU <
I— UJ
hi - 12 X
z
h- 13
.25 -
- 14
I I
10 15
COMPRESSOR PRESSURE RATIO
9-2
CONDITIONS:
COMPRESSOR EFFICIENCY = 0.85
COMBUSTION EFFICIENCY = 0.98
TURBINE EFFICIENCY = 0.90
GENERATOR EFFICIENCY = 0.975 TURBINE INLET
MECHANICAL EFFICIENCY = 0.975 TEMPERATURE °F
AMBIENT TEMPERATURE = 60° F
AMBIENT PRESSURE = 14.69 PSIA
^ 200 -
9-3
It is anticipated that the next generation of industrial/
utility turbines, using present aircraft engine technology
will operate at a 16 to 1 pressure ratio and a 2,400°F
turbine inlet temperature. Specific power will be about
202 kWe per pound of air, and a net bus bar efficiency of
about 38 percent (8,988 Btu/kwh) may be achieved.
9-4
14
I
5y -30
tDCQ—
u) >o
z
UJ
i-<
cc cc
1500° F - APPROXIMATE TURBINE INLET TEMPERATURES
I-< 10" <
m
LU 03
I
D
-35
mD
O< _i
<
LU
cc
UJ
03<
03
9 o>
< -40
CC
UJ
o>
8- 15 \19 14 1970° F
-45
-50
3000° F
-55
'80 '90
9-5
TABLE 9-1
POINT IDENTIFICATION
2. Parr Steam Station; South Carolina Electric and Gas Co.; Parr,
South Carolina
5. Sterlington S.E. Station Unit #7; Louisiana Power & Light Co.;
Sterlington, Louisiana
16. Curtiss Wright Corp. Models TEC 300, TEC 400, TEC 550, and TEC 600
18. Western Farmers Co-op; and Arko, Okla. General Electric Co. Model
STAG 100
19. General Electric Co. Model STAG 600
20. Turbodyne Model CC-200, CC 400
21. Beaver Plant; Portland General Electric Co.; Portland, Oregon
9-6
These processes are fairly well developed and are expected
to be commercially available in the intermediate term
(after 1985).
Processes for converting coal to oil are being developed,
and are also expected to be commercially available in the
intermediate term.
9-7
Raproduced from the 1976 edition of the Uniform Building Code, copyright 1976,
with permission of the publisher. International Conference of Building Officials.
APPENDIX
>
I
HEAT RATE
RELATIVE PERFORMANCE FACTOR
AMBIENT TEMPERATURE °F
AMBIENT TEMPERATURE EFFECT ON NET PLANT PERFORMANCE
HEAT RATE
RELATIVE PERFORMANCE FACTOR.
ALTITUDE FEET
ALTITUDE EFFECT ON NET PLANT PERFORMANCE
A- 2
APPENDIX
FIGURE 1C
RELATIVE
MAINTENANCE COST FACTORS
_ REFINERY
RESIDUAL
OIL
CRUDE
_
OIL DISTILLATE
FUEL TYPE
EFFECT OF FUEL ON GAS TURBINE MAINTENANCE COST
MAINTENANCE COST FACTOR
FAST START/LOAD
NORMAL START/LOAO
1/1000 1/100
STARTS/FIRED HOUR
A- 3
APPENDIX
SWITCHYARD
STEAM TURBINE GENERATOR
RAW RESIDUAL
FUEL STORAGE TANK
60 DAY SUPPLY
PUMPSTATION
CONTROL ROOM
^ WATER
HEAT EXCHANGERS TREATMENT AREA
& CLOSED COOLING
WATER SYSTEM
Cf 89 109129 180
FIGURE 2A-3 PLOT PLAN SINGLE UNIT RESIDUAL FUEL
SCALE
APPENDIX
] FUEL UNLOADING
FUEL
TREATMENT I RAW RESIDUAL FUEL STORAGE TANKS
COOLING
TOWERS
xr ioo'izs laor
FIGURE 2A-4 PLOT PLAN DOUBLE UNIT RESIDUAL FUEL
SCALE
BYPASS
FUELOIL STACK
STACK
360° F
900PSIG
FUEL 82 MWe
850° F
STORAGE THREE HEAT
RECOVERY
DEAERATOR
I TREATED
1___ ?Uf^STORAGE. _J
I FEEDWATER (Q
1950°F
FIGURE 2B-1
GAS TURBINES
EMERGENCY FIRE
PROTECTION PUMP
UNLOADING
TANK
A—9
AUXILIARY BOILER
TANK CAR DUPLEX UNLOADING PUMPS STORAGE TANK DUPLEX PUMPS
FILTER (11 3-50% CAPACITY 60 DAY SUPPLY FILTER (1) 2-100% CAPACITY
UNLOADING
TANK WITH
STEAM COILS
AUXILIARY BOILER
FUEL HEATERS
TANK CAR DUPLEX UNLOADING PUMPS RAW RESIDUAL 1-300% CAPACITY TREATMENT FUEL 2-100% CAPACITY
FILTER 2-100% CAPACITY STORAGE TANK STEAM HEATED PLANT FORWARDING STEAM HEATED
60 DAY SUPPLY PUMPS
3-60% CAPACITY
MEAT RECOVERY STEAM
GENERATORS IF FIRED
TANK CAR
UNLOADING
PUMP
FEDERAL EPA
Primary
- Annual arithmetic mean 0.03
- Maximum 24-hour concentration 0.14
- Maximum 3-hour concentration
- Maximum 1-hour concentration
Secondary
- Annual arithmetic mean
- Maximum 24-hour concentration
- Maximum 3-hour concentration 0.50
- Maximum 1-hour concentration
State of California
South Coast Air Basin
Southern California Metropolitan Zone (LA) Rule 67
___________________________________________________
A-l 1
FIGURE 3B
FEDERAL EPA
State of California
South Coast Air Basin
Southern California Metropolitan Zone (LA) Rule 67
A-l 2
FIGURE 3C
NITROGEN OXIDES EMISSIONS AND AMBIENT AIR QUALITY STANDARDS
FEDERAL EPA
Primary
- Annual Average 0.05
- 1 hour —
Secondary
- Annual Average 0.05
- 1 hour
fa)
v applicable for liquid fuels to new stationary
fossil-fired installations only.
^k^Federal Standards are promulgated in micrograms
per cubic meter of air. Values shown in ppm are
approximate equivalents.
State of California
South Coast Air Basin
Southern California Metropolitan Zone (LA) Rule 67
A-13
FIGURE 3D
SUMMARY EFFLUENT LIMITATIONS GUIDELINES AND STANDARDS FOR LIQUID WASTE DISCHARGES (A)
EFFLUENT LIMITATIONS*
SOURCE EFFLUENT CHARACTERISTIC BPCTCA (1977) BATEA (1983) New Sources
Once Through Cooling Water Chlorine - Free Available 0.2 (0.5 max)** 0.2 (0.5 max)** 0.2 (0.5 max)**
Cooling Tower Blowdown Chemical Additives (Corrosion No Limitation Established on Case No Detectable Amount
Inhibitors) by Case Basis
Chlorine - Free Available 0.2 (0.5 max)** 0.2 (0.5 max)** 0.2 (0.5 max)**
Chromium No Limitation 0.2 (0.2 max) No Detectable Amount
Zinc No Limitation 1.0 (1.0 max) No Detectable Amount
Phosphorous No Limitation 5.0 (5.0 max) No Detectable Amount
pH 6.0 to 9.0 6.0 to 9.0 6.0 to 9.0
Bottom Ash Transport TSS 30 (100 max) 1977 limit in 1977 limit in
Oil & Grease 45 (20 max) pounds divided by pounds divided by
PH 6.0 to 9.0 6.0 to 9.0 6.0 to 9.0
Metal Cleaning Waste^ TSS 30 (100 max) 30 (100 max) 30 (100 max)
Oil & Grease 15 (20 max) 15 (20 max) 15 (20 max)
Copper, Total 1.0 (1.0 max) 1.0 (1.0 max) 1.0 (1.0 max)
Iron, Total 1.0 (1.0 max) 1.0 (1.0 max) 1.0 (1.0 max)
pH 6.0 to 9.0 6.0 to 9.0 6.0 to 9.0
*Note: Numbers are concentrations, mg/1, except for pH values. Effluent limitations, except where otherwise
indicated, are monthly averages of daily amounts, mg. to be determined by the concentrations shown and
the flow of waste water from the source in question. In some cases there are limitations shown on the
maximum amount for any day. Where waste waters from one source with effluent limitations for a parti
cular pollutant are combined with other waste waters, the effluent limitation, mg (or mg/1), for the
particular pollutant, excluding pH, for the combined stream shall be the sum of the effluent limitations
(for concentration limits apply appropriate dilution factors) for each of the streams which contribute
to the combined stream except that the actual amount, mg (or mg/1), of the pollutant in a contributing
stream will be used in place of the effluent limitation for those contributing streams where the actual
amount, mg (or mg/1), of the pollutant is less than the effluent limitation, mg (or mg/1), for the
contributing steam. The pH value should be in the range given at all times.
**Note: Effluent limitations are average concentrations during a maximum of one 2-hour period a day and maximum
concentrations at any time. No more than one unit at a plant may be chlorinated at any time. Limita
tions are subject to case-by-case variances if higher levels or more lengthy period are needed for
condenser tube cleanliness.
1) Low Volume Waste Sources include but are not limited to: waste waters from wet scrubber air pollu
tion control systems, ion exchange water treatment evaporator blowdown, laboratory and sampling
streams, floor drainage, cooling tower basin cleaning wastes, and blowdown from recirculating house
service water systems.
2) Metal Cleaning wastes include any cleaning compounds, rinse waters, or any other waterborne residues
derived from cleaning any metal process equipment including, but not limited to, boiler tube clean
ing boiler fireside cleaning and air preheater cleaning.
3) Rainfall Runoff from construction areas and material storage areas for all rainfall events less than
or equal to the once in 10 year 24 hour event is to be treated.
(A) Note: Several of the provisions of the regulations establishing these limitations were set aside and remanded
to the EPA for further consideration on July 18, 1976 (9ERC1055).
A-14
FIGURE 3E
SUMMARY OF EFFLUENT LIMITATIONS GUIDELINES AND STANDARDS FOR HEAT TO THE WATERS OF THE U.S. ^
EFFLUENT LIMITATIONS
TYPE OF UNIT BPCTCA (1977) BATEA (1983)1 NEW SOURCE3
LARGE UNIT
1) EXEMPTIONS ARE PROVIDED FOR: a) coldside blowdown, b) hot side blowdown for systems under construction,
c) discharges into existing cooling ponds or cooling lakes, d) where sufficient land is not available, e) sites
where salt drift would cause a problem, f) sites where cooling tower fog would cause a substantial hazard to
commercial aviation.
2) A delay of up to two years may be granted for some plants on the basis of system reliability.
3) EXEMPTIONS ARE PROVIDED: a) coldside blowdown from recirculating cooling water systems, b) coldside blow
down from cooling ponds.
NOTE: 40CFR122 provides means whereby Thermal Discharge Limitations can be modified if the owner or operator
of a facility can demonstrate that less stringent limitations will protect fish and wildlife.
(a) Note: Provisions of the regulations establishing these limitations were set aside and remanded to the EPA
for further consideration on July 18, 1976 (9ERC1055).