Professional Documents
Culture Documents
Journal of NUCLEAR SCIENCE and TECHNOLOGY, 25[11], pp. 891~894 (November 1988).
55
892 SHORT NOTE (S. Yanagihara et al.) J, Nucl. Sci. Technol.,
56
Vol. 25, No. 11 (Nov. 1988) SHORT NOTE (S. Yanagihara et al.) 893
57
894 SHORT NOTE (S. Yanagihara et al.) J. Nucl. Sci. Technol.,
to evaluate efficiency of the dismantling tasks. 400~800 mR/h (2.9 x 10-8~5.6 x10-8 C/kg,s) for
A total of 882 man-days was found to be the core grid support bolts. The dismantled
needed for the dismantling activity in the components will be put into containers of
followings : various types according to the radiation level.
After the reactor internals were dismantled,
Preparation :124 man-days
the working area was cleaned up. All tools
Assembling of devices : 220 man-days
and devices were taken out from the radiation
Dismantling :368 man-days
controlled area after it was confirmed that
Disassembling of devices : 89 man-days
there was no radioactive contamination on
Cleaning up :81 man-days
their surfaces. The strippable paint coated
Since the total weight of the dismantled over the surface of the slave arm was proved
reactor internals was approximately 170 kg, to be quite useful to remove the contamination
the work efficiency, that is, the ratio of man- easily. Almost all contamination could be
powers needed for the dismantling activity to removed together with the paint stripped from
the weight of the dismantled components was the surface of the slave arm, though the
calculated to be approximately 2,200 man-days contamination caused by strong contact with
per ton. This was extremely large compared the wall of the reactor pressure vessel, which
with the other works such as dismantling of was 10-10Ci/cm2 (3.7x104 Bq/m2) in maximum,
the reactor pressure vessel head and piping, was not removed. Except these contaminated
because the work efficiency of these activities components, waste of about 540 kg in total
was in the range of 10~50 man-days per ton. weight was secondly produced. This included
In spite of this low work efficiency, cumu- vinyl sheets and groves which were mainly
lative radiation exposure to workers was used by visitors for study and observation.
measured to be less than 0.05 man-rems (5x 3. Concluding Remarks
10-4 man,Sv) though the environmental dose The underwater plasma arc cutting system
rate was high around the location of these operated by the JARM-25 was proved to be
reactor internals in the core. The maximum quite useful to dismantle reactor components
dose rate was calculated to be approximately and to minimize radiation exposure to workers
30 R/h (2.2 x 10-6 C/kg,s) in air environment, as well. During 1988, the dismantled pieces
which is mainly caused by g-ray emitting from and some instruments stored in the spent fuel
the wall of the core shroud. The radiation pool will be removed to provide spaces for
exposure to workers was measured during the follow-on dismantling activities. The disman-
work of lifting up and packaging of the dis- tling of the remaining reactor internals will
mantled pieces. In addition, it was confirmed begin in April 1989, using a mast-type under-
by a dust monitoring system that the air in water plasma arc cutting system. Finally, all
the working environment was kept clean reactor components and buildings will be
during the dismantling activity. The remotely completely removed and then the site will be
controlled dismantling system including the landscaped by 1992.
local ventilation was, therefore, proved to be REFERENCES
effective to minimize worker exposure, though (1) ISHIKAWA, M., et al.: Proc. Int. Conf. on Nu-
it required a large amount of man-power clear Power Performance and Safety, IAEA-
expenditure. CN-48/152, (1987), Vienna.
(3) Waste Management (2) ISHIKAWA, M., et al.: Proc. 1987 Int. Decom-
missioning Symp., Oct. 4~8, 1987, Pittsburgh,
Surface dose rate of each dismantled re-
Penn., USA, III-118.
actor internal was measured to be in the (3) YANAGIHARA, S., et al.: J. At. Energy Soc.
range of 13~17 mR/h (9.3 x10-10~1.2 x 10-9 C/ Jpn., (in Japanese), 30[3], 235~246 (1988).
kg,s) for the feedwater sparger and also (4) ASHIDA, S., et al.: Ref. (2), VI-48.
58