ash pool

Remark
1. The customer needs to connect the cable to the equipment within a range of 1 meter, with a power requirement
of 380V 50HZ and a three-phase AC power supply
2. Negotiate and resolve any outstanding matters; The customer needs to provide equipment installation wiring
cables:
Cooler,ball mill and screening machine: 3 * 10mm ² Cable (national standard) water pump: 3 * 4mm ² Cable
(National Standard)
130 dross separator: 4 * 6mm ² Cable (national standard) peripheral: 3 * 25mm ² Cable+6mm ² (Zero Line) (National
Standard)