Professional Documents
Culture Documents
and Maintenance
(33 kV and below)
SUB-STATION OVERVIEW
• The very earliest power stations used simple open knife switches, mounted on
insulating panels of marble or asbestos. Power levels and voltages rapidly
escalated, making opening manually operated switches too dangerous for anything
other than isolation of a de-energized circuit. Oil-filled equipment allowed arc
energy to be contained and safely controlled. By the early 20th century, a
switchgear line-up would be a metal-enclosed structure with electrically operated
switching elements, using oil circuit breakers. Today, oil-filled equipment has
largely been replaced by air-blast, vacuum, or SF6equipment, allowing large
currents and power levels to be safely controlled by automatic equipment
incorporating digital controls, protection, metering and communications.
Switchgears continued…
• Typically, the switchgear in substations is located on both the high voltage and the
low voltage side of large power transformers. The switchgear on the low voltage
side of the transformers may be located in a building, with medium-voltage circuit
breakers for distribution circuits, along with metering, control, and protection
equipment.
• Switch Gear include Equipments which are used to isolate / break the circuit in
normal operating condition , under Fault Condition .
• Under fault condition the switchgear breaks the circuit to isolate the faulty portion
of the network from healthy one thereby preventing whole system failure.
Switches are mainly of two types:
This is mainly of two types:
1. Circuit Breaker(ON-LOAD SWITCH)
2. Isolator(OFF-LOAD SWITCH)
Switchgear is mainly having these components:
• Bushings: When a high voltage conductor passes through a metal sheet or frame
which is at earth potential, the necessary insulation is provided in the form of
bushings.
• Bus-Bar and Conductors: The current carrying members in a circuit breaker consist
of fixed and moving contacts and conductors connecting these of the points
external to the breaker. If the outdoor switchyard is there, these connections are
connected directly to the overhead lines. In case of indoor switchgear, the
incoming conductors to the circuit breaker are connected to the bus bars.
11-kV Switchgear Panel
Panel Requirements:
• Sheet steel construction
• Dust & vermin proof
• Metal clad compartmentalized
design
• Compartments separated by
metallic partitions
• Pressure relief flaps for exit of
gas due to internal arc
• Accessible for maintenance &
inspection
• Doors & removable covers with
gaskets all round ( neoprene
cork gaskets)
• Thermostat controlled space
heater with on off switch
• X axis represents time in milli seconds and y axis represents distance in milli meter
• Closing Operation: At time T0 current starts flowing through the closing coil. After
time T1 the moving contact starts traveling towards fixed contact. At time T2
moving contact touches fixed contact. At time T3 the moving contact reaches at its
close position. T3 - T2 is overloading period of these two contacts (moving and
fixed contact). After time T3 the moving contact bounce back little bit and then
again comes to its fixed closed position, after time T4.
• Requirements: After hitting fixed contact, the moving contact may bounce back,
due to repulsive force which is not at all desirable. Hence sufficient mechanical
energy to be supplied to overcome repulsive force due to closing operation on
fault. In spring - spring mechanism, generally tripping or opening spring is charged
during closing operation. Hence sufficient mechanical energy also to be supplied
to charge the opening spring.
• Opening Operation: At time, T5 current starts flowing through trip coil of the
circuit breaker. At time T6 moving contact starts traveling backward for opening the
contacts. After time T7, the moving contact finally detaches the fixed contact. Time
(T7 - T6) is over lapping period. Now at time T8 the moving contact comes back to
its final open position but here it will not be at rest position since there will be
some mechanical oscillation of moving contact before coming to its final rest
position. At time T9 the moving contact finally comes to its rest position.
Types of Circuit Breaker
• The type of the Circuit breakers are classified based on the following:
Medium of arc quenching (Air, Air Blast, Vacuum,SF6)
Voltage level. (low voltage up to 1000V, Medium voltage, High voltage)
Mounting arrangement (Fixed, Draw out)
No. of Poles (Single, Two Pole, Three Pole & Four Pole)
Method of operation(manual/automatic)
• These negative ions obviously much heavier than a free electron and therefore over all
mobility of the charged particle in the SF6 gas is much less as compared other common gases.
We know that mobility of charged particle is majorly responsible for conducting current
through a gas.
• Hence, for heavier and less mobile charged particles in SF6 gas, it acquires very high
dielectric strength. Not only the gas has a good dielectric strength but also it has the
unique property of fast recombination after the source energizing the spark is removed.
The gas has also very good heat transfer property. Due to its low gaseous viscosity
(because of less molecular mobility) SF6 gas can efficiently transfer heat by convection.
So due to its high dielectric strength and high cooling effect SF6 gas is approximately 100
times more effective arc quenching media than air. Due to these unique properties of
this gas SF6 circuit breaker is used in complete range of medium voltage and high
voltage electrical power system. These circuit breakers are available for the voltage
ranges from 33KV to 800KV and even more.
Difference between SF6 and Vacuum technologies
• SF6 Circuit Breaker: SF6 Gas pressure monitoring possible. Vacuum
Circuit Breaker: Vacuum cannot be monitored.
• Fall in pressure can be annunciated in SF6 CB. Loss of vacuum will
be known with CB failure in VCB
• SF6 breaker can interrupt rated current even after gas pressure falls
down to atmospheric pressure. Vacuum CB has to be taken out for
replacement of poles.
• Good Electrical endurance for both
• Interrupting chambers can be maintained in SF6 breakers.
Interrupters to be replaced( Cost of replacement 40% of cost of CB)
in Vacuum CB
• SF6 CBs are rugged. Sensitive to rough handling well suited to
motor duty operations. Vacuum CBs are relatively inferior to motor
switching. Surge protection essential
• Vacuum CB is relatively less smooth in switching compared to SF6
CB
Selection criterion(Ratings) of Circuit Breaker
Rated Short Circuit Breaking Current:
Short circuit breaking current of circuit breaker is defined as maximum electric current that
can flow through the breaker from time of occurring short circuit to the time of clearing the
short circuit without any permanent damage in the CB.
• The value of short circuit breaking current is expressed in RMS. During short circuit, the
CB is not only subjected to thermal stress, it also suffers seriously from mechanical
stresses. So during determining short circuit capacity, the mechanical strength of the CB
is also considered. So for choosing suitable circuit breaker it is obvious to determine the
fault level (The prospective maximum current or power, which will flow in a circuit that
is subject to a fault) at that point of the system where CB to be installed.
• Once the fault level of any part of electrical transmission is determined it is easy to
choose the correct rated circuit breaker for this part of network.
Other parameters:
• Rated Normal Current
• Climatic Conditions(Ambient Temperature)
• Selection of Transient Recovery Voltage
• Duration of Circuit Breaker
• Selection of Capacitive Current switching
• Selection of type of Circuit Breaker
Name Plate Details of CB
• Architecture: Metal-clad air insulated
(IEC 298)
• Internal Arc Protection: As per IEC
• Degree of protection: IP 4X
• Normal service condition: Indoor
(IEC 294)
• Temperature category: Min. –5 Deg
C, Max. 50 Deg C, Ave. +38 Deg. C
• Rated Capacity : 500 MVA
• Rated Voltage: 12 kV
• Service Voltage: 11 kV
• Rated Frequency: 50 Hz
• Short circuit Current with stand
capacity: 26.3 Amp for 3 seconds.
• Peak with stand current rating: 66 kA
• Bus bar continuous rated
current:1600 A
• Bus bar material: Copper
Electrical Fuse
• A fuse is a part of the circuit which consists of conductor which melts easily and
breaks the connection when electric current exceeds the predetermined value.
This increase in current can be either because of overload or short circuit.
• The materials used for fuse wires are mainly tin, lead, zinc, silver, antimony,
copper, aluminum etc.
Depending upon the position in power system, the isolators can be categorized as
1) Bus side isolator – the isolator is directly connected with main bus
2) Line side isolator – the isolator is situated at line side of any feeder
3) Transfer bus side isolator – the isolator is directly connected with transfer bus.
Constructional Features:
• Isolators are 3-pole stacks of insulators mechanically coupled with each other.
• Conducting parts are supported on post insulators.
• Conducting parts consists of AL or Cu rod , Fixed and moving contacts.
Double-Break Isolators:
These have three stacks of post insulators as
shown in the figure. The central post insulator
carries a tubular or flat male contact which can
be rotated horizontally with rotation of central
post insulator. This rod type contact is also
called moving contact.
This type of arrester is also called ‘protector tube’ and is commonly used on
system operating at voltages up to 33kV. It essentially consists of a rod gap
AA’ in series with a second gap enclosed within the fiber tube. The gap in the
fiber tube is formed by two electrodes. The upper electrode is connected to
rod gap and the lower electrode to the earth. One expulsion arrester is placed
under each line conductor. On the occurrence of an over voltage on the line,
the series gap AA’ spanned and an arc is stuck between the electrodes in the
tube. The heat of the arc vaporizes some of the fiber of tube walls resulting in
the production of neutral gas. In an extremely short time, the gas builds up
high pressure and is expelled through the lower electrode, which is hollow. As
the gas leaves the tube violently it carries away ionized air around the arc.
This deionizing effect is generally so strong that the arc goes out at a current
zero and will not be re-established.
Metal Oxide Arrestor:
• The metal oxide arresters are without gaps, unlike the SIC arrester. This
“gap-less” design eliminates the high heat associated with the arcing
discharges. A metal-oxide surge arrester utilizing zinc-oxide blocks
provides the best performance, as surge voltage conduction starts and
stops promptly at a precise voltage level, thereby improving system
protection. Failure is reduced, as there is no air gap contamination
possibility; but there is always a small value of leakage current present at
operating frequency.
• It is important for the test personnel to be aware that when a metal oxide
arrester is disconnected from an energized line a small amount of static
charge can be retained by the arrester. As a safety precaution, the tester
should install a temporary ground to discharge any stored energy.
Rating of MOA:
• Duty cycle rating: The silicon carbide and MOV arrester have a
duty cycle rating in KV, which is determined by duty cycle
testing. Duty cycle testing of an arrester is performed by
subjecting an arrester to an AC rms voltage equal to its rating
for 24 minutes. During which the arrester must be able to
withstand lightning surges at 1-minute intervals.
Construction Features:
• This type of arrester comprises of numbers of solid zinc oxide disc. This
discs are arranged one by one to form a cylindrical stack.
• The number of zinc oxide discs used per lightning arrester depends upon
the voltage rating of the system.
• This stack is kept inside a cylindrical housing of polymer or porcelain. Then
the stack is placed inside the housing and highly pressed by heavy spring
load attached to end cap at top.
• The equipment connection terminal for line is projected from top cap and
connection terminal for earth is projected from the bottom cap.
• The ZnO disc consists of mainly zinc oxide (90 to 95%) with relatively small
amounts of several additives of other metal oxide (5 to 10%) like alumina,
antimony tri-oxide, bismuth oxide, cobalt oxide, zirconium etc.
ZnO Lightening
Arrestor
The zinc oxide has highly non-uniform current voltage (I – V) characteristics.
This makes it very suitable for the LA operation. This can be represented as:
Where Vr and Ir are the reference voltage and current beyond which it starts
operating.
Working:
• When the normal conditions are there, there is no
current in the LA as it offers high resistance to it.
Current in milli A flows through it.
• When the voltage in the line exceeds the reference
voltage , LA starts operating and current in the KA
flows through it.
• Due to increase in current, temperature rises and
due to non linear characteristic of ZnO, resistance of
material decreases and it offers low impedance path
to fault current(in KA).
• This is the basic working of ZnO LA.
Instrument Transformers
• Instrument transformers are high accuracy class electric devices used to
isolate from high voltage lines for metering and protection purposes.
• These are of two types:
Current Transformer
Voltage Transformer
Current Transformer:
Current Transformers, as defined in IS:2705, is
“an instrument transformer in which the secondary current under normal
circumstances of use, is substantially proportional to the primary current and
differs in phase from it by an angle approximately equal to zero”.
The purpose of CT, as used in power system, is of two kinds:
a) Protection and relaying;
b) Metering and indication.
The CTs of both these types are different in construction and purpose, though
their characteristics are one and the same.
Vector Diagram of CT
Some Terms:
Phase Error: The current transformer works on the principle of variable flux. In the ideal
current transformer, secondary current would be exactly equal (when multiplied by the
turns ratio) and opposite to the primary current.
But, as in the voltage transformer, some of the primary current or the primary ampere-
turns are utilized for magnetizing the core, thus leaving less than the actual primary ampere
turns to be transformed into the secondary ampere-turns. This naturally introduces an error
in the transformation. The error is classified into current ratio error and the phase error.
Composite Error:
The RMS value of the difference between the instantaneous primary current and the
instantaneous secondary current multiplied by the turns ratio, under steady state
conditions.
Rated primary current:
Rated primary current of current transformer is an optimum value of primary current at
which, error of the CT are minimum and losses in the CT are also less.
Rated secondary current:
The current in the secondary circuit on which the performance of the CT is based. Typical
values of secondary current are 1 A or 5 A.
Rated burden:
The apparent power of the secondary circuit in Volt-amperes expressed at the rated
secondary current and at a specific power factor. Typical burden ratings for IEC CTs are 1.5
VA, 3 VA, 5 VA, 10 VA, 15 VA, 20 VA, 30 VA, 45 VA and 60 VA.
Accuracy Class of CT:
There is always some difference in expected value and actual value of output of an
instrument transformer current error and phase angle error count in CT, as because
primary current of current transformer has to contribute the excitation component of
CT core. Accuracy class of current transformer is the highest permissible percentage
composite error at rated current. The standard accuracy classes of current transformer
as per IS-2705 are 0.1, 0.2, 0.5, 1, 3 & 5 for metering CT.
• The accuracy class or simply class of measuring current transformer is 0.1, means
the maximum permissible limit of error is 0.1%, more clearly, if we try to measure
100 A with a 0.1 class CT, the measured value may be either 100.1 or 99.9 A or
anything in between these range.
The standard accuracy class for the protection current transformer, as per IS-2705 are
5 P, 10 P, 15 P.
• Here in the protection current transformer, 5 P means 5%, 10 P means 10%, and
15 P means 15% error and ′P′ stands for protection.
The accuracy class for the protection CT is always more, because during short
circuit , high current flows and CT should be capable of step down this much
amount of current easily. So, its accuracy class is kept high.
Instrument Security Factor
ISF or instrument security factor of current transformer is defined as the ratio of instrument
limit primary current to the rated primary current. The instrument limit primary current of
metering CT is the value primary current beyond which CT core becomes saturated.
Accuracy Limit Factor
For protection current transformer, the ratio of accuracy limit primary current to the rated
primary current is called accuracy limit factor of current transformer.
Knee Point Voltage of Current Transformer
Knee point voltage of current transformer is significance of saturation level of a current
transformer core mainly used for protection purposes. The sinusoidal voltage of rated
frequency is applied to the secondary terminals of CT, with other winding being open
circuited which increased by10%, cause the exiting current to increase by 50%.
Circuit Diagram of PT
• Phasor Diagram:
Some Terms:
Voltage Error or Ratio Error:
The difference between the ideal value Vp/KT and actual value Vs is the voltage error or ratio error in a
potential transformer, it can be expressed as,
Rated secondary voltage: This is the voltage at which the meters and protective devices connected to
the secondary circuit of the voltage transformer operate.
Rated burden: This is the load in terms of volt-amperes (VA) posed by the devices in the secondary
circuit on the VT. This includes the burden imposed by the connecting leads. The VT is required to be
accurate at both the rated burden and 25% of the rated burden.
Accuracy class required: The transformation errors that are permissible, including voltage (ratio) error
and phase angle error. Phase error is specified in minutes. Typical accuracy classes are Class 0.5, Class 1
and Class 3. Both metering and protection classes of accuracy are specified. In a metering VT, the VT is
required to be within the specified errors from 80% to 120% of the rated voltage. In a protection VT, the
VT is required to be accurate from 5% up to the rated voltage factor times the rated voltage.
Rated voltage factor:
Depending on the system in
which the VT is to be used, the
rated voltage factors to be
specified are different.
• Simplicity of system
• Easy maintenance of different equipments
• Minimizing the outage during maintenance
• Future provision of extension with growth of demand
• Optimizing the selection of bus bar arrangement scheme so
that it gives maximum return from the system
Bus Bar Arrangement
Single Bus System:
• Single Bus System is simplest and
cheapest one. In this scheme all the
feeders and transformer bay are
connected to only one single bus as
show.
• This System is very simple in design
, cost effective and easy to operate.
• One but major difficulty of these
type of arrangement is that,
maintenance of equipment of any
bay cannot be possible without
interrupting the feeder or
transformer connected to that bay.
Single Bus Bar System with
Sectionalizer:
NC
ABB
SF6
ABB BHEL
BHEL
SF6 MOCB
MOCB
33/11 KV 33 /11 KV
25 MVA 20 MVA 33/11 KV
CROMPTON BHARAT BIJEE 16 MVA TR -1
TR -III TR -II BHARAT BIJLEE
GULABI BAGH PUMPING
SUBHADRA COLONY
GULABI BAGH PUMPING
7.2 MVAR CAP BANK-1
DSIDC JJ COLONY
TRANSFORMER
100 KVA LOCAL
RAILWAY STATION
CAP BANK-2
KANHIYA NAGAR
5.04 MVAR
PUMPING STN 1
NAAG MANDIR
KALA PAHAR
GULABI BAGH
CSA COLONY
DAYA BASTI
DAYA BASTI
11 KV I/C - 1
11/ KV I/C- 3
11 KV I/C 2
STN -6
STN -2
SZB NO -6
SZB NO 7
NORTH DELHI POWER LIMITED DRG NO DATE DRAWN BY CHECKED BY 33 /11 KV SHAHZADA BAGH GRID STATION
POWER SYSTEM CONTROL RANI BAGH PSC - 37(R) 04/12/06 TB.,SJ RN APPROVED BY
SC.,DS
CAN
750-500/5-5-5A
33KV SF6
1250A ,1500MVA
33KV SF6
1250A ,1500MVA
33 / 11 KV
33 / 11 KV 25 MVA
25 MVA TRF -2
TRF -1
12KV SF6
600A ,26.3KA
11 KV ,1600A 500MVA
FOR 3 SEC,3W,50HZ CU BUS BAR
7.2 MVAR CAP BANK -1
KHURANA S/ST
I/C TRF NO 1
I/C TRF NO 2
MARUTI O/H
FEEDER -8
MEHTA S/S
HVDS O/H
FEEDER -5
FEEDER -6
FEEDER -7
NORTH DELHI POWER LIMITED DRG NO DATE DRAWN BY CHECKED BY 33 /11 KV PAYAL GRID STATION
P S & T – PITAMPURA PSC - 01(R) 04/08/07 TRUSHA APPROVED BY JAYANTA CHATTERJEE
33/11 KV 33/11 KV
16 MVA TR -2 16 MVA TR -1
33/11 KV (CG) VOLTAMP
16 MVA TR -3 SPARE I /C REWARI LINE -1
I /C REWARI LINE -2
SHUNT CAPACITOR BANK-2
CAPACITOR BANK -1
C -BLK KIRTI NAGAR
E -BLK KIRTI NAGAR
F -BLK MS GARDEN
5.04 MVAR
RAJDHANI S/STN
I/C TRF NO 2
SHARDA PURI
SARASWATI
DSIDC NO-1
I/C TRF NO 1
5.04MVAR
GARDEN
DLF NO -3
NORTH DELHI POWER LIMITED DRG NO DATE DRAWN BY CHECKED BY 33 /11 KV SARASWATI GARDEN GRID STATION
POWER SYSTEM CONTROL RANI BAGH PSC - 35(R) 04/12/06 TB.,SJ PC APPROVED BY CAN
SC.,DS
BUS
PT
REAR
BUS COUPLER
NC NC
NC NC
NC
FRONT
CGL
CGL
VCB
BUS
PT
33/11 KV
20 MVA 33 / 11 KV
VOLTAMP 16 MVA
TRF-2 APEX
TRF -1
11 KV BUS - 2
11 KV BUS - 1
CAPACITOR BANK
TRANSFORMER
400 KVA LOCAL
PRAGYA MALL
10 -B SMB FEEDER
13 -B S/S SMB
8 -B S/S SMB
5 B S/S SMB
6 B S/S SMB
I /C TRF -2
I /C TRF -1
SPARE-2
SPARE-3
SPARE-5
7-B S/S
NORTH DELHI POWER LTD DRG NO DATE DRAWN BY CHECKED BY 33 /11 KV SHALIMAR BAGH GRID STATION
P S & T – PITAMPURA PSC - 39(R) 16/08/07 TRUSHA APPROVED BY JAYANTA CHATTERJEE
Conditional Monitoring:
Generally we have a maintenance schedule for the maintenance of switch gear
depending on the operating conditions, previous test results and age of equipment .
Other methods are used in addition to maintain the healthiness of the equipment as
below:
• Thermal Imaging(often used)
• Partial Discharge Testing
• Acoustic Emission Testing(by using surface mounted transducers or
ultrasonic detectors)
• SF6 equipment(invariably fitted with alarms and interlocks to warn of loss
of pressure)
These techniques are the preventative maintenance techniques.
Thermal Imaging
• In this technique, a thermal imaging
camera is used.
• Thermal cameras detect the changes in
heat in the area at which they are pointed.
The device can use these variations in heat
to build a picture on a screen.
• These devices are fast becoming an
essential tool for preventative maintenance
work because they show where heat is
leaking from pipes or where electrical
equipment is giving off more heat than it
should. For example, in the case of using a
thermal imaging camera for circuit
breakers, the technician would point the
device at all the circuit breakers. If the
resulting image on the screen suggests that
a high amount of heat is being generated
from a specific breaker then it may indicate
that there is some damage. The cost for
replacing the breaker at this point is small;
however, if the issue will be left for an
extended period of time, it will lead to
damage of equipment, there by cost will
increase.
Installation of Circuit Breaker
General:
• All adjustments are made in factory, all moving parts are already
positioned correctly and fastened.
• It is advisable to keep the transport packings of the pole columns, thereby
facilitating eventual transport on subsequent overhaul work.
• To prevent the absorption of any moisture, in case of SF6 breaker , the
pole columns are filled with insulating gap abs(1.5 bar).
Erection Requirements:
• An erection crane with a carrying capacity of about 850 kg and a crane
hook height of at least 4mabove the floor.
• A lifting Sling
• Dimension Drawings, Circuit Drawing and Circuit Diagrams
• Torque wrench for a range of 6-200 Nm and socket tool 24 mm
• Open end wrenches for bolts M6-M16 and 0.5” UNC and open end wrench
for 36mm
• A Thermometer for ambient temperature.
• Gas filling equipment in case of SF6 Circuit Breaker
Erection Procedure:
1. Lift the complete assembled circuit breaker with crane
2. In case of SF6 breaker: Check SF6 pressure by pressing the disc of the
check valve inwards with pin of approx. 5 mm. diameters, when a hissing
sound is heard. The circuit breaker is supplied with a gas pressure of 1.5
bar absolute to prevent the ingress of moisture in then interrupting
chamber. When this hissing sound is not heard, then there is a leak which
must be attended to.
3. Place supports on the prepared foundation. The upper bearing surface
for the pole support must be horizontal and must lie in one level. Screw
supports tight to the foundation.
4. The exact location can be obtained from the installation layout plan.
During erection, make sure that the fixation holes for the earthing
connection are positioned correctly.
5. Mount frame with the assembled poles on supports with fasteners
6. Place cubicle in the correct mounting position between the supports on
wooden under layments.
7. To mount mechanism on the frame lift the operating mechanism upward
by lifting bolts, insert stay bolts in the holes provided for them and
fasten with the accompanying fasteners .Be careful, the pole in the
middle must not be damaged by lifting ropes. Ensure that there is no
washer between frames and stay bolts. During mounting of mechanism
ensure that the upper joint head of the connecting rod is inserted in to
the fork of the actuating lever.
8. Fitting of connecting rod, the operating mechanism and the CB are to be
coupled together in the open position. The connecting rod is already
adjusted in the factory. Adjust connecting rod so it can move freely in the
joint heads.
9. Fitting of the density monitor for SF6 breaker : Connect density monitor,
cables and possible pressure gauge
10. Complete the Hi-voltage connections.
Commissioning:
• All data which are checked or measured are to be entered in a
commissioning record and preserved for future compare. The
SF6 breaker, SF6 gas pressure can be seen from CB name
plate.
• For SF6 breaker: Filling of SF6 gas to the nominal filling pressure. As the
circuit breaker is supplied vacuum processed and filled with SF6 gas at
transport pressure of 0.15 MPa abs, during commissioning only one filling
of SF6 gas is required, to top up pressure up to the filling pressure given
on the rating plate. In the filling process the dependence of the nominal
pressure on temperature must definitely be taken in to account. After
temperature equalization period of approx. 1 hour, check the pressure and
correct if necessary by adding or releasing the gas. Check all the sealing
joints on the breaker poles and the gas supply system for leaks with leak
detector / soap solution. Repair any leak, if found.
• Connect proper earthing to the terminals provided.
• Test charging to be done after complete testing and clearance from
protection and maintenance / projects group.
Testing of Circuit Breaker
Following major tests are conducted on CB:
• Operational Checks (checking min/max pick up and drop out coil voltages, proper operation
for safety interlocks)
• Insulation resistance Test
• Contact Resistance measurement
• Spring Charging motor resistance, current and time
• Operation Time (Close, open, close-open time)
• Notch Point of VCB ( on moving Contact Rod of Vacuum Interrupter)
Insulation Resistance Test: In insulation resistance test, a high DC voltage is applied across,
conductor and ground more specifically. The voltage is applied across the insulator. Due to this
applied high DC voltage there will be a current through the electrical insulator. By dividing the
applied voltage by this current, we get the actual resistive value of the insulator.
• This test is generally done by means of megger.
• Megger gives required direct (dc) voltage across the insulator an it also shows the resistive
value of insulator directly in Mohm range. The megger are generally of 500 V, 2.5 KV an 5 KV.
• This test includes:
Phase to phase measurement
Phase to Ground measurement
Across pole(in open conditions)
Contact Resistance Measurement: This involves injecting a fixed current, usually around
300 A through the contacts and measuring the voltage drop across it. This test is done with
a special contact resistance measuring instrument.
Then, using Ohm's law, the resistance value is calculated. The resistance value needs to be
compared with the value given by the manufacturer. The value should also be compared
with previous records.
Operational Checks : It includes min/max pick up and drop out coil voltages of relay, safety
operation for interlocks(closing and tripping interlock) and operation for rack in/out.
Pick up voltage: As the voltage of a de-energized relay is increased, the value at or below
which all contacts must function.
Drop out Voltage: As the voltage on an energized relay is decreased, the value at or above
which all contacts must return to their de-energized position.
• Pick up voltage and drop out voltage values are simple to measure. A power supply and
a digital multi-meter are the only two components needed.
Spring Charged motor Test: In this, a voltage source of particular voltage is applied to
motor to charge up the spring. Then charging time is calculated using stop watches
and charging current is calculated using ohm’s law. Lastly, it is compared with previous
measurements.
Operation Time: Circuit Breaker is made to go through various operations. The basic
operations are “Close” when joining and “trip” when parting the contacts. These are
not the only operations that the breaker is meant to do. In most of the cases it has to
execute on demand a combination of the basic operations, called cycles. The most
popular are the following:
• Trip-Free(C-O) : It indicates a trip on short circuit after a close. The breaker must
open instantly.
• Reclose-open(O-C): It indicates a fast close after short circuit trip to re-establish
the current.
Operating time is calculated using digital pulse counter technique. The instrument is
connected across main contacts and the time gets measured when circuit breaker
operates. This time is compared with the reference operating time.
Maintenance Checklist for CB
Continued…
Maintenance Checklist for Isolator
Thermo Scanning Checklist