Professional Documents
Culture Documents
PERMIT No.
APPLICABLE ONLY TO TESTING & COMMISSIONING PROJECT/ SITE
ALL WORK UNDER THIS PERMIT IS VALID FOR A SINGLE ACTIVITY AND PER SHIFT
REQUESTED BY (Supervisor) DATE & TIME DURATION
CONTRACTOR
SPECIFIC WORK LOCATION
Electrician competency is assessed by Supervision consultant & proof Minimum of 2 Locks & Tags in languages understood by workers placed
of qualification is readily available. and held by the operator/ maintenance/ supervisor.
LOTO/ ISOLATION REQUIREMENT Energy sources have been identified & recorded. Reasons for lock out is mentioned on Tags and legible.
(Must be completed by Competent
Electrical Supervisor and verified on
site by Permit Authoriser) All affected/ relevant parties have been notified. Isolation has been verified & recorded by a competent electrician.
Task specific PPE such as electrical insulated boots & face protection
Test equipment to verify that all energy has been released or controlled.
is provided as stated in LOTO procedure.
LOTO Procedure, activity briefing & Permit requirement is briefed to all HSE officer has conducted inspection to ensure LOTO procedure is
operative & records available. adhered to as per Expo & Dubai Municipality requirement.
ISSUE
I ….Supervisor …………………………(Permit requestor) confirm that this LOTO requirement have been checked and recorded at work location.
_______________________
I will ensure all operatives are briefed on Permit to Work requirements and the activity.
Signature, Date & Time
I ……..Site/ Construction/ Project Manager …. (PTW Authoriser) confirm to authorise the testing & commissioning activity (Specify if other activity) as detailed in this Permit.
_______________________
I confirm that I have physically checked work location and all isolation conditions is satisfactory.
Signature, Date & Time
HAND-BACK/ CLOSE OUT (Must be completed by Supervisor/ Permit requestor and returned to Permit Coordinator)
Work is completed at (Time & Date): ………………….
_______________________
I ….Supervisor …………………………(Permit requestor) confirm that the work is completed and have checked operation of energy restoration.
Signature, Date & Time
SUSPENSION/ CANCELLATION
Where monitoring of any type identifies contractor works which are not adequately covered by a Health and Safety MS/RA, all or specific parts of those works will be immediately suspended by the Supervision Consultant and/or the Employer until
satisfactory action is taken by the contractor to rectify the situation.