Professional Documents
Culture Documents
Page 2 of 2
CONSTRUCTION PTE LTD
Doc No: V3-OHS-810-1-F08
Start End
Date Time
Approval (stage 4) PermitNo V3/Myra/G
This permit is valid for one day only. The conditions of issue must be complied with throughout the duration of work. The permit may be
withdrawn at any time. Applicant is responsible for the copy of this permit and must be produced upon request and returned to the Safety
Dept upon completion ofwork.
Location ofWork Myra
Description of Process &Work Activity
Equipment/ Machinery Used
The following measures must be observedl complied with before the start of any work.
(Tickwhere necessary andindicate N.A when notrequired.)
Workers have been briefed on Risk Assessment, Safe Work All floor opening and open sides have been adequately
Procedures barricaded
All works are within a working height of 2metres All electricaltools have been inspected by LEW
Daily Toolbox Meeting have been conducted Warning signs and barricade have been placed at work
area
Workers are provided with required PPE
Note: a. I hereby seek approval to perfom the above work
b.I have taken measures to render the place safe and I shall ensure compliance with the instruction as stated.
C.Any changein condition willinvalidatethis Permit and anew Permitwillbe applied wheneverthe existing Permitis invalidated
Stage 1:Application of General Permit-To-Work To becompleted by Applicant
I have read he conditions relating to the work to be performed and I fully understand the nature of work required and will ensure that the above measures are fully complied
with.
Name of Applicant Signature
Designation Appointed PTW applicant Company
Date Time
Stage 2:Inspection &Endorsement (Tobe completed by V3 AreaIn Charge
I have inspected and assessedtogether withthe applicant on the worklarea to be performed andcertifiedthatall measures arecomplied with
Name Signature
Designation Appointed Area Incharge Company V3 Construction Pte Ltd
Date Time
Stage 3: Check &Confirmation (To be completed by Contractor PTW Assessor)
I have checked and confirmthattheworkissafeto proceed.
Name Signature
Designation Appointed PTW Assessor Company (Contractor)
Date Time
Stage 3: Check &Confirmation (Tobecompletedby V3Construction P/L PTW Assessor
Name Mr.Anand/Sakthivel Signature
Designation Appointed PTW Assessor Company
Date Time
Stage 4:ApprovalofPermit(Tobe completedbyV3ConstructionP/LHOP Or his Designates)
Name Mr. Cui Yongjie_ Signature
Designation Project Manager/Authorized Manager|Company V3 Construction Pte Ltd
Date Time
Stage 5: Completion of GENERAL Work To be completed by Applicant (Site supervisor)
Theabove work has been completed on at hrs andI hereby return this permitfor yourretention.
Name of Applicant Signature
Designation Appointed PTW Assessor Company
|Date Time
V3
Page I of 2
CONSTRUCTION PTE LTD Doc No: V3-OHS-810-1-F08
Rev. 0
Operational Control 03 Jan 2020
(7) Subcontractor or relevant personnel where PTW is applicable, shall verify the hazards are
VOperational Control
CONSTRUCTION PTE LTD Doc No:V3-OHS-810-1-F-21
Name Contractor *
NRIC/FIN no Designation
Location
Date (Circle/ indicate where applicable)
Inspectioon
General PTW
Housekeeping maintained at work areas? YININ.A
1 YININ.A
2 Proper and safe access egress provided at work areas7 YININA
3 All works less than 2 meter in hejght? YININ.A
4 Electrical tools safe and inspected by LEW YININ.A
5 Workers involved briefed on RA /SW related to activity?. YININ.A
6Hacking Locations cleaned of debris?(indicate locations)
WAH PTW YININ.A
sides and
Guardrails are in place to prevent person from falling thru
opening? YININ.A
2 No incompatible works below? YIN/IN.A
3 Valid certs,checklist for use of MEWP? YININ.A
4 Valid inspection tags and checklistfor scaffold ? YIN/NA
5Provision of anchorage points whereby guardrailsis not provided? YININA
6 Workers involved Trained &briefed on RA/SWP related to activity? YININ.A
Removal of safety provision to facilitate works
assessment)
eg guardrails, toeboard ? (indicate locations and risk
Hotwork PTW YININ.A wa*
YIN/N.A_
YININ.A
Suitable Fire-fighting equipment provided? YININ.A
5 Workers involved briefed on RA/SWP related to activity?.
Others YININ.A
Competent assessor appointed for WAH and or other activity? YININ.A
RA adeguate and relevant to the work process?_ **
YININ.A
Immediate supervision compliannce for relevant activity?
V3 rectified? YININ.A
4 Are all safety inspections on the previous day by
reference number sent for
indicate number of inspection finding and (No:
closure)?2 YININ.A
previous day?
Any pending safety inspection finding fromremarks
and state reason under for consideration)
indicate number (No:
* * * * * * * * * * * * * *
Remarks5
Special instructions by V3 Safety department:
Name &Sign
with the instruction as stated.
Thave taken measures to render the place safe and I shal ensure complianca whenever the existing Permit is irivalidated
and a new Pemmit will be applied
change in condition will invalidate this Permit
Any
PTM is applicable, shall verify the hazards are unchanged during the validity period.
Subcontractor cw relevant personnel where **