Daily Activities

December 04, 2023

Sunny Day

Monday

Activities

 Cutting, bending and Installation of 10mm Rebars for 2 nd floor beam


 Installation of formworks and supports at 2nd floor girder beam
 Bending, Cutting and Installation of 16mm Rebars for 2 nd floor beam
 Checking and Re - Mocking up the layout for stairs
 Backfilling of soil and Bagging of excess soil at basement area
 Pumping of Water at Basement Area
 CHB laying at perimeter of 2nd floor

December 05, 2023

Sunny Day

Tuesday

Activities:

 Cutting, bending and Installation of 10mm Rebars for 2 nd floor beam


 Inspection and Meeting with Arch. Raissa and Engr. Yuan for 2nd Floor Partition
 Installation of formworks and supports at 2nd floor girder beam
 Bending, Cutting and Installation of 16mm Rebars for 2nd floor beam
 Backfilling of soil and Bagging of excess soil at basement area
 Pumping of Water at Basement Area
 CHB laying at perimeter of 2nd floor
December 06, 2023

Sunny Day

Wednesday

Activities:

 Cutting, bending and Installation of 10mm Rebars for 2 nd floor beam


 Inspection and Meeting with Arch. Raissa and Engr. Yuan for 2nd Floor Partition
 Installation of formworks and supports at 2nd floor girder beam
 Bending, Cutting and Installation of 16mm Rebars for 2nd floor beam
 Backfilling of soil and Bagging of excess soil at basement area
 Pumping of Water at Basement Area
 CHB laying at perimeter of 2nd floor

December 07, 2023

Sunny Day

Thursday

Activities:

 Cutting, bending and Installation of 10mm Rebars for 2nd floor beam
 Installation of formworks and supports at 2nd floor girder beam
 rBending, Cutting and Installation of 16mm Rebars for 2nd floor beam and overhang
 Checking and Re - Mocking up the layout for stairs
 Electrical piping at 2nd floor slab and GI wire pulling
 Backfilling of soil and Bagging of excess soil at basement area
 Installation of GI pipes for 2nd floor slab support
 Laying out 2nd floor partitions and Windows for checking
 Coordinate with Structural Engineer regarding the Structural Details
 Pumping of Water at Basement Area
 CHB laying at perimeter of 2nd floor
 Delivery of Materials

December 1, 2023

Sunny Day
Friday

Activities:

 Cutting, bending and Installation of 10mm Rebars for 2 nd floor beam


 Installation of formworks and supports at 2nd floor girder beam
 Bending, Cutting and Installation of 16mm Rebars for 2 nd floor beam and overhang
 Checking and Re - Mocking up the layout for stairs
 Backfilling of soil and Bagging of excess soil at basement area
 Installation of GI pipes for 2nd floor slab support
 Laying out 2nd floor partitions and Windows for checking
 Pumping of Water at Basement Area
 CHB laying at perimeter of 2nd floor

December 02, 2023

Sunny Day

Saturday

Activities:

 Cutting, bending and Installation of 10mm Rebars for 2nd floor beam
 Installation of formworks and supports at 2nd floor girder beam
 Bending, Cutting and Installation of 16mm Rebars for 2 nd floor beam and overhang
 Checking and Re - Mocking up the layout for stairs
 Backfilling of soil and Bagging of excess soil at basement area
 Installation of GI pipes for 2nd floor slab support
 Laying out 2nd floor partitions and Windows for checking
 Pumping of Water at Basement Area
 CHB laying at perimeter of 2nd floor

Target Activities for 2 Weeks from Dec. 9 to Dec. 16

 Backfilling of Soil
 Concrete Pouring of column at 2nd floor and 2nd floor column
 Installation of Perforated Pipe at Basement Area
 Installation of Form Works for 2nd floor Column
 Installation of Form Works for 2nd floor Girder Beam
 Installation of Deformed bars for 2nd floor girder beam
 Installation of Deformed bars for 2nd floor Column
 Plastering of walls at ground floor area
 Installation of Drainage Lines and Water line
 Installation of Electrical Pipes