Professional Documents
Culture Documents
Sunny Day
Monday
Activities
Sunny Day
Tuesday
Activities:
Sunny Day
Wednesday
Activities:
Sunny Day
Thursday
Activities:
Cutting, bending and Installation of 10mm Rebars for 2nd floor beam
Installation of formworks and supports at 2nd floor girder beam
rBending, Cutting and Installation of 16mm Rebars for 2nd floor beam and overhang
Checking and Re - Mocking up the layout for stairs
Electrical piping at 2nd floor slab and GI wire pulling
Backfilling of soil and Bagging of excess soil at basement area
Installation of GI pipes for 2nd floor slab support
Laying out 2nd floor partitions and Windows for checking
Coordinate with Structural Engineer regarding the Structural Details
Pumping of Water at Basement Area
CHB laying at perimeter of 2nd floor
Delivery of Materials
December 1, 2023
Sunny Day
Friday
Activities:
Sunny Day
Saturday
Activities:
Cutting, bending and Installation of 10mm Rebars for 2nd floor beam
Installation of formworks and supports at 2nd floor girder beam
Bending, Cutting and Installation of 16mm Rebars for 2 nd floor beam and overhang
Checking and Re - Mocking up the layout for stairs
Backfilling of soil and Bagging of excess soil at basement area
Installation of GI pipes for 2nd floor slab support
Laying out 2nd floor partitions and Windows for checking
Pumping of Water at Basement Area
CHB laying at perimeter of 2nd floor
Backfilling of Soil
Concrete Pouring of column at 2nd floor and 2nd floor column
Installation of Perforated Pipe at Basement Area
Installation of Form Works for 2nd floor Column
Installation of Form Works for 2nd floor Girder Beam
Installation of Deformed bars for 2nd floor girder beam
Installation of Deformed bars for 2nd floor Column
Plastering of walls at ground floor area
Installation of Drainage Lines and Water line
Installation of Electrical Pipes