SCHEDULE Q

QUALITY REQUIREMENTS

Attachment I CONTRACTOR Quality Personnel Qualification Requirements

Attachment II SAUDI ARAMCO Standards and Procedures Containing Quality


Requirements

Attachment III Quality Requirements for CONTRACTOR Supplied Materials

Attachment IV Quality Requirements for Construction Phase

Attachment V Summary of Quality System Deliverables

Attachment VI Project Specific Quality Requirements

EXHIBIT I OF ATTACHMENT VI TO SCHEDULE Q

PROJECT SPECIFIC QUALITY REQUIREMENTS

Position Primary CONTRACTOR Subcontractor(s)

Coating QC Inspector One (1) full time* One (1) full time per
Subcontractor**

* If this discipline is involved in procurement


** If the Subcontractor is involved in procurement
*** If this discipline is involved in design

Construction Primary Inspectors CONTRACTOR Pre-


Discipline (CONTRACTOR or Supervising Commissioning
Subcontractor) Inspectors Inspectors

Coatings / One (1) full time One (1) full time One (1) full time
Insulations Inspector per three (3) Inspector for every Inspector
Testing crews per site (1) five (5) Subcontractor
Inspectors (1)