TOP OF PILE CAP LEVEL PIER COORDINATES PILE - 1 PILE - 2 PILE - 3 PILE - 4
PIER NO.
# GROUND PILE CAP * PILE CUT BORE HOLE PILE LENGTH
LEVEL DEPTH OFF LEVEL NO. (L*) IN MM EASTING NORTHING EASTING NORTHING EASTING NORTHING EASTING NORTHING EASTING NORTHING
PILE CAP REINF.
300 300 (REFER FROM P1 (LHS) 16.697 1.800 14.447 P-1 24000 450248.876 2750886.518 450248.312 2750884.036 450246.394 2750887.082 450251.358 2750885.954 450249.440 2750889.000
SEPARATE DRAWING) P1 (RHS) 16.697 1.800 14.447 P-1 24000 450242.749 2750896.250 450242.185 2750893.768 450240.267 2750896.814 450245.231 2750895.686 450243.313 2750898.732
(TYP.)
300
END OF SPIRAL
SHEAR CURTAILMENT
CAST-IN-SITU PILE (TYP.) BAR NO. BAR 01 BAR 02 BAR 03 BAR 04 BAR 05 BAR 06 LENGTH LENGTH (L3**) IN MM
(L1*) IN MM (L2*) IN MM
SHAPE OF
+ DIM. DETAIL OF PILE BARS
--- --- ---
SCALE : 1/15 P1 (LHS) T25 - 17 NOS. T32 - 17 NOS. T20 - 17 NOS. T16 @125 T10 @150 T20 @2000 14000 14000 18000
1 1 P1 (RHS) T25 - 17 NOS. T32 - 17 NOS. T20 - 17 NOS. T16 @125 T10 @150 T20 @2000 14000 14000 18000
ANY REINFORCEMENT
TRAFFIC DIRECTION
SILCHAR AGARTALA
CL OF PIER ( LHS )
2 2
PILE-3 PILE-1
75 ** L3 IS VALID IF BAR 01 & 03 IS HAVING DIFFERENT DIA. OF REBAR.
NOTES:
1. CONCRETE SHALL BE DESIGN MIX AND HAVE MINIMUM 28 DAYS CHARACTERISTIC STRENGTH OF 35 MPa ON 150mm CUBES.
SECTION 2-2 2.
3.
H.Y.S.D. REINFORCEMENT BARS CONFORM TO IS: 1786 GRADE Fe-550D.
CLEAR COVER TO ANY REINFORCEMENT IN THE PILE & PILE CAP SHALL NOT BE LESS THAN 75mm.
CL OF ALIGNMENT
SCALE : 1/15
(REBAR 01 WITH 03)
4. LAP LENGTHS
PILE-4 PILE-2 LL= 60 x D WHERE D : DIAMETER OF SMALLEST BAR IN OVERLAP. FOR IS: 1786 GRADE Fe-550D
5750
WHEN BOTH BARS IN A BUNDLE ARE LAPPED AT ONE LOCATION, LAP LENGTH SHALL BE INCREASED BY 25%.
LAP
5. 100% LAPPING OF REINFORCEMENT IS PERMITTED HOWEVER LAPPING SHALL NOT BE DONE IN TOP 9.00m LENGTH OF PILE.
6. THE SPACING OF TRANSVERSE REINFORCEMENT SHALL NOT BE MORE THAN 150 mm AT THE LOCATIONS WHERE BARS ARE
LAPPED.
75mm CLEAR COVER TO 7. THE SOIL STRATA ENCOUNTERED DURING PILE BORING SHALL BE COMPARED WITH THE BORE LOG DETAILS GIVEN IN THE
ANY REINFORCEMENT DRAWING. ANY MAJOR VARIATION SHALL BE BROUGHT TO THE NOTICE OF THE ENGINEER.
CL OF PIER ( RHS )
5750
3 3
8. THE PILE LENGTH PROVIDED IS AS PER BORE-LOG DETAILS AVAILABLE BY GEO-TECH CONSULTANTS. IT MUST BE ENSURED ON
PILE-3 PILE-1
SITE THAT THE PILE IS TERMINATING IN SAME STRATA AS MENTIONED IN GEOTECH REPORT.
9. PILES SHOULD BE PLACED IN SUCH A WAY THAT AXIS OF PILE CAP ARE NORMAL & TANGENTIAL TO THE CENTER LINE OF
ALIGNMENT.
10. BEFORE EXECUTION, CONTRACTOR SHALL VERIFY THE CO-ORDINATES OF PILE AT SITE. IN CASE OF ANY AMBIGUITY, THE CASE
1.5 TURN AT THE SHOULD BE REFERRED TO THE ENGINEER.
END OF SPIRAL 11.
TEMPORARY LINER OF SUITABLE THICKNESS HAS TO BE PROVIDED. FOR THE LENGTH OF TEMPORARY LINER, GEOTECH
FOUNDING LEVEL REPORTS NEED TO BE REFERRED OR AS PER SITE CONDITIONS.
PILE-4 PILE-2 12. THESE PILES ARE DESIGNED ACCORDING TO THE PROVIDED P&P & GEOTECHNICAL REPORTS. THE PILES ARE NOT EXPOSED
75
TO THE DRAIN WATER AS THE PILE CUT-OFF LEVEL IS KEPT APPROX. 3.0M BELOW O.G.L/N.B.L. AT SITE, IF IT IS ENCOUNTERED
1200
SECTION 3-3 THAT THERE WILL BE ANY STANGNANT WATER AROUND THE PILES THEN THE SAME MUST BE INFORMED TO THE DESIGNER
PILE REINFORCMENT SCALE : 1/15
PILE LAYOUT PLAN BEFORE EXECUTION OF THE WORK.
13. AT LOCATIONS WHERE PILES ARE RESTED BELOW DRAIN WATER THAN PERMANENT LINER OF 6MM THICKNESS (MINIMUM) MUST
(* REFER FROM TABLE ) BE PROVIDED AT LEAST 5M BELOW PILE CUTOFF LEVEL.
SCALE 1:25
CLIENT: EPC CONTRACTOR : DESIGN CONSULTANT : PROOF CONSULTANT : AUTHORITY ENGINEER : DRAWN PARVEEN CONSTRUCTION OF FOUR LANE BADARPUR BYPASS FROM DESIGN CHAINAGE
DESIGN PRABU KM: 27+300 AT CROSSING WITH NH-6 (OLD NH-44) NEAR SIDDESWAR PT.-I
BRIDGECON INFRACONSULTANTS VILLAGE TO DESIGN CHAINAGE KM: 38+400 ON NH-37 (OLD NH-44) AT
S.S. BUILDERS. CHECKED PRANJAL
PVT. LTD. KANDIGRAM CHAITA VILLAGE IN THE STATE OF ASSAM ON EPC MODE UNDER
APPROVED FARRUKH
249,NEW MODEL TOWN, 265, OKHLA INDUSTRIAL ESTATE BHARATMALA PARIYOJANA IN ECONOMIC CORRIDORS.
PHASE - III, NEW DELHI-110020 SAFETY CONSULTANT : PROOF
LUDHIANA (PUNJAB).
CONSULTANT
REINFORCEMENT DETAILS OF PILE FOR PIER P1
PH: +91-11-41832060
PH: +91-9254123666 AUTHORITY
+91-11-41832061 FLYOVER AT CH.@ 37655.000 (SHEET 1 OF 1)
ENGINEER
0 First Issue PRABU PRANJAL FARRUKH 07-11-2023 REV. SCALE
BUILDING INFRASTRUCTURE-BUILDING THE NATION DATE 07-11-2023 DRAWING NO. BIC-STR-FLY-BARAK-12201 0 AS SHOWN
REV. PARTICULARS DES. CHD. VER. DATE
CL OF PIER / PILE CAP CL OF PIER / PILE CAP
1200 4000
GROUND LEVEL
500
500
PILE CAP TOP
1800
1800
PILE CAP BOTTOM LEVEL
50
750 3600 50 750 100mm THK. (GRADE M-15) 750 3600 750
LEVELLING COURSE
5100 5100
CAST-IN-SITU PILE (TYP.)
SECTION A-A SECTION B-B
SCALE 1:35 SCALE 1:35
TRAFFIC DIRECTION
CL OF PIER CL OF PILE
CL OF PILE
100 5100 100
1200
750
CL OF PILE
CL OF PIER /
5100
3600
A A
PILE CAP P1 (LHS) 37655.000 16.697 16.197 14.397
CAST-IN-SITU PILE
(TYP.)
CL OF PILE NOTES:
REFERENCE DRAWINGS : 1. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS UNLESS OTHERWISE MENTIONED.
750
1. GENERAL ARRANGEMENT DRAWING - BIC-STR-FLY-BARAK-12001 & 12002 2. DIMENSIONS ARE NOT TO BE SCALED, ONLY WRITTEN DIMENSIONS SHALL BE FOLLOWED.
100
CLIENT: EPC CONTRACTOR : DESIGN CONSULTANT : PROOF CONSULTANT : AUTHORITY ENGINEER : DRAWN PARVEEN CONSTRUCTION OF FOUR LANE BADARPUR BYPASS FROM DESIGN CHAINAGE
DESIGN PRABU KM: 27+300 AT CROSSING WITH NH-6 (OLD NH-44) NEAR SIDDESWAR PT.-I
BRIDGECON INFRACONSULTANTS VILLAGE TO DESIGN CHAINAGE KM: 38+400 ON NH-37 (OLD NH-44) AT
S.S. BUILDERS. CHECKED PRANJAL
PVT. LTD. KANDIGRAM CHAITA VILLAGE IN THE STATE OF ASSAM ON EPC MODE UNDER
APPROVED FARRUKH
249,NEW MODEL TOWN, 265, OKHLA INDUSTRIAL ESTATE BHARATMALA PARIYOJANA IN ECONOMIC CORRIDORS.
PHASE - III, NEW DELHI-110020 SAFETY CONSULTANT : PROOF
LUDHIANA (PUNJAB).
CONSULTANT
DIMESNIONS DETAILS OF PILE CAP FOR PIER P1
PH: +91-11-41832060
PH: +91-9254123666 AUTHORITY
+91-11-41832061 FLYOVER AT CH.@ 37655.000 (SHEET 1 OF 2)
ENGINEER
0 First Issue PRABU PRANJAL FARRUKH 07-11-2023 REV. SCALE
BUILDING INFRASTRUCTURE-BUILDING THE NATION DATE 07-11-2023 DRAWING NO. BIC-STR-FLY-BARAK-12202 0 AS SHOWN
REV. PARTICULARS DES. CHD. VER. DATE
10
PIER SHAFT PIER SHAFT
xD
REINFORCEMENT REINFORCEMENT
IA
10xDIA
SECTION A-A
SCALE 1:25
SECTION B-B
SCALE 1:25
TRAFFIC DIRECTION
BAR MARK 01 BAR MARK 02 BAR MARK 03 BAR MARK 04 BAR MARK 4a BAR MARK 05 BAR MARK 06
PIER NO.
TRANSVERSE LONGITUDINAL
P1 (LHS) T12 - 110mm T20 - 105mm T20- 110mm T20 - 105mm T16 - 105mm
T12 @ 150mm C/C
C/C C/C C/C C/C C/C T12 - 210mm C/C T12 - 220mm C/C
P1 (RHS) T12 - 110mm T20 - 105mm T20- 110mm T20 - 105mm T16 - 105mm
T12 @ 150mm C/C T12 - 210mm C/C T12 - 220mm C/C
C/C C/C C/C C/C C/C
A A LEGENDS
BAR ON TOP FACE
BAR ON BOTTOM FACE
NOTES:
1. CONCRETE SHALL BE DESIGN MIX AND HAVE MINIMUM 28 DAYS CHARACTERISTIC STRENGTH
OF 35 MPa ON 150mm CUBES.
2. ALL REINFORCING STEEL SHALL BE HYSD GRADE Fe 500D.
3. CLEAR COVER TO ANY REINFORCEMENT IN THE PILE CAP SHALL NOT BE LESS THAN 75mm.
4. LAP LENGTHS
LL = 78*D WHERE D : DIAMETER OF SMALLEST BAR IN OVERLAP.
DETAIL -1 5. LAPS SHOULD BE SUITABLY STAGGERED & MINIMUM DISTANCE BETWEEN ADJACENT LAPS
B SCALE : 1/25
SHALL BE 1.3 TIMES THE LAP LENGTH. NOT MORE THAN 50% OF THE BARS SHALL BE LAPPED
PLAN VIEW OF PILE CAP
LONGITUDINAL DIRECTION STAGGERED TIED TO ALTERNATE BARS. AT ANY SECTION.
(SHEAR LINKS NOT SHOWN FOR CLEARTY) SCALE 1:25
6. BEFORE CASTING OF PILE CAP, INITIAL AND ROUTINE LOAD TEST SHALL BE CARRIED OUT TO
VERIFY PILE LOAD CAPACITY.
CLIENT: EPC CONTRACTOR : DESIGN CONSULTANT : PROOF CONSULTANT : AUTHORITY ENGINEER : DRAWN PARVEEN CONSTRUCTION OF FOUR LANE BADARPUR BYPASS FROM DESIGN CHAINAGE
DESIGN PRABU KM: 27+300 AT CROSSING WITH NH-6 (OLD NH-44) NEAR SIDDESWAR PT.-I
BRIDGECON INFRACONSULTANTS VILLAGE TO DESIGN CHAINAGE KM: 38+400 ON NH-37 (OLD NH-44) AT
S.S. BUILDERS. CHECKED PRANJAL
PVT. LTD. KANDIGRAM CHAITA VILLAGE IN THE STATE OF ASSAM ON EPC MODE UNDER
APPROVED FARRUKH
249,NEW MODEL TOWN, 265, OKHLA INDUSTRIAL ESTATE BHARATMALA PARIYOJANA IN ECONOMIC CORRIDORS.
PHASE - III, NEW DELHI-110020 SAFETY CONSULTANT : PROOF
LUDHIANA (PUNJAB).
CONSULTANT
REINFORCEMENT DETAILS OF PILE CAP FOR PIER P1
PH: +91-11-41832060
PH: +91-9254123666 AUTHORITY
+91-11-41832061 FLYOVER AT CH.@ 37655.000 (SHEET 2 OF 2)
ENGINEER
0 First Issue PRABU PRANJAL FARRUKH 07-11-2023 REV. SCALE
BUILDING INFRASTRUCTURE-BUILDING THE NATION DATE 07-11-2023 DRAWING NO. BIC-STR-FLY-BARAK-12203 0 AS SHOWN
REV. PARTICULARS DES. CHD. VER. DATE
11000 500 11000
MEDIAN
P1
500 10000 500 GAP 500 10000 500 CL OF PIER /
CB CARRIAGE WAY (LHS) CB CB CARRIAGE WAY (RHS) CB PIER CAP
CL OF BRG. 750 750 CL OF BRG.
CL OF DECK / PIER CL OF DECK / PIER
FRL B FRL POCKET FOR
2.5% SLOPE 2.5% SLOPE EXP. JOINT 40mm EXP. JOINT
55mm 55mm
SHEAR SHEAR SHEAR SHEAR GAP GAP
KEY KEY KEY KEY
700 600 700 700 600 700 590
750
750
750
750
750
750
456
456
387
387
319
319
A A
250
250
650 L 650 L L L L 650 L 650 1300 1300
750
750
750
ELASTOMERIC
1375 2750 2750 2750 1375 1375 2750 2750 2750 1375 PAD
PIER TOP LEVEL
750
750
750
100 4000 100 100 4000 100
PIER CAP
700 1200 700
PIER PIER
G.L.
500
500
500
PIER BOTTOM LEVEL
1800
1800
750 3600 750 750 3600 750 750 3600 750
B
PCC 100mm THK. PCC 100mm THK. PCC 100mm THK.
CAST-IN-SITU
1200 TYPICAL CROSS SECTION PILE (TYP.)
1200
TYP. SCALE : 1/50 FL. TYP. VIEW B-B
SCALE : 1/50
700
700
GAP
1300
GL - GROUND LEVEL
FL - FOUNDING LEVEL
700 700 700
800 650 650 800 800 CB - CRASH BARRIER
2600
590
590
590
(TYP.) (TYP.) 700 700
550 750
1300
700
FRL 27.000
PIER CAP TOP LEVEL * 24.371
1375 2750 2750 2750 1375 1375 2750 2750 2750 1375 PIER TOP LEVEL 22.871
11000 500 11000 PIER BOTTOM LEVEL 16.197
SCHEDULE :-
NOTES:
PILE CAP 1. ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS
GROUND PILE CAP
FRL BOTTOM
PIER NO. CHAINAGE LEVEL TOP LEVEL UNLESS OTHERWISE MENTIONED.
(m) LEVEL 2. DIMENSIONS ARE NOT BE SCALED, ONLY WRITTEN DIMENSION SHALL BE
(m) (m)
(m) FOLLOWED.
3. GRADE OF CONCRETE SHALL BE AS FOLLOWS:
P1 (LHS) 37655.000 27.000 16.697 16.197 14.397 PILE AND PILE CAP : M-35
PIER & PIER CAP : M-40
P1 (RHS) 37655.000 27.000 16.697 16.197 14.397 LEVELING COURSE : M-15
CLIENT: EPC CONTRACTOR : DESIGN CONSULTANT : PROOF CONSULTANT : AUTHORITY ENGINEER : DRAWN PARVEEN CONSTRUCTION OF FOUR LANE BADARPUR BYPASS FROM DESIGN CHAINAGE
DESIGN PRABU KM: 27+300 AT CROSSING WITH NH-6 (OLD NH-44) NEAR SIDDESWAR PT.-I
BRIDGECON INFRACONSULTANTS VILLAGE TO DESIGN CHAINAGE KM: 38+400 ON NH-37 (OLD NH-44) AT
S.S. BUILDERS. CHECKED PRANJAL
PVT. LTD. KANDIGRAM CHAITA VILLAGE IN THE STATE OF ASSAM ON EPC MODE UNDER
APPROVED FARRUKH
249,NEW MODEL TOWN, 265, OKHLA INDUSTRIAL ESTATE BHARATMALA PARIYOJANA IN ECONOMIC CORRIDORS.
PHASE - III, NEW DELHI-110020 SAFETY CONSULTANT : PROOF
LUDHIANA (PUNJAB).
CONSULTANT
DIMENSIONAL DETAILS OF SUBSTRUCTURE FOR PIER P1
PH: +91-11-41832060
PH: +91-9254123666 AUTHORITY
+91-11-41832061 FLYOVER AT CH.@ 37655.000 (SHEET 1 OF 1)
ENGINEER
0 First Issue PRABU PRANJAL FARRUKH 07-11-2023 REV. SCALE
BUILDING INFRASTRUCTURE-BUILDING THE NATION DATE 07-11-2023 DRAWING NO. BIC-STR-FLY-BARAK-12204 0 AS SHOWN
REV. PARTICULARS DES. CHD. VER. DATE
10
FRL
xD
IA
LINK
TYPICAL DETAIL BAR
1200
1200
MARK 3a, 3b, 4a & 4b
300
300
PIER TOP LEVEL
SECTION 1-1 #
SCALE 1:20
TRANSITION ZONE
10
xD
IA
2 2 2 2
(PIER HEIGHT)
(PIER HEIGHT)
STIRRUP
L
L
TYPICAL DETAIL BAR
1 1 1 1
MARK 5a & 5b
CONFINING ZONE
4000 (MIN.)
SECTION 2-2 #
SCALE 1:20
GROUND LEVEL
150
300
GRADE OF
TRAFFIC DIRECTION
LAP LENGTH
CL PIER
CONCRETE
1200
M40 68 x D
900
HERE D IS DIAMETER OF SMALLEST
BAR IN OVERLAP.
150
TRANSVERSE SECTIONAL VIEW LONGITUDINAL SECTIONAL VIEW 150 3700 150
4000
CLIENT: EPC CONTRACTOR : DESIGN CONSULTANT : PROOF CONSULTANT : AUTHORITY ENGINEER : DRAWN PARVEEN CONSTRUCTION OF FOUR LANE BADARPUR BYPASS FROM DESIGN CHAINAGE
DESIGN PRABU KM: 27+300 AT CROSSING WITH NH-6 (OLD NH-44) NEAR SIDDESWAR PT.-I
BRIDGECON INFRACONSULTANTS VILLAGE TO DESIGN CHAINAGE KM: 38+400 ON NH-37 (OLD NH-44) AT
S.S. BUILDERS. CHECKED PRANJAL
PVT. LTD. KANDIGRAM CHAITA VILLAGE IN THE STATE OF ASSAM ON EPC MODE UNDER
APPROVED FARRUKH
249,NEW MODEL TOWN, 265, OKHLA INDUSTRIAL ESTATE BHARATMALA PARIYOJANA IN ECONOMIC CORRIDORS.
PHASE - III, NEW DELHI-110020 SAFETY CONSULTANT : PROOF
LUDHIANA (PUNJAB).
CONSULTANT
REINFORCEMENT DETAILS OF PIER P1
PH: +91-11-41832060
PH: +91-9254123666 AUTHORITY
+91-11-41832061 FLYOVER AT CH.@ 37655.000 (SHEET 1 OF 1)
ENGINEER
0 First Issue PRABU PRANJAL FARRUKH 07-11-2023 REV. SCALE
BUILDING INFRASTRUCTURE-BUILDING THE NATION DATE 07-11-2023 DRAWING NO. BIC-STR-FLY-BARAK-12205 0 AS SHOWN
REV. PARTICULARS DES. CHD. VER. DATE