‫ﺍﻟﺠﻤﻬﻮﺭﻳــﺔ ﺍﻟﺠﺰﺍﺋﺮﻳــﺔ ﺍﻟﺪﻳﻤﻘﺮﺍﻃﻴــﺔ ﺍﻟﺸﻌﺒﻴــﺔ‬

‫‪...........................‬‬ ‫ﻭﻻﻳﺔ‬
‫‪...........................‬‬ ‫ﺩﺍﺋﺮﺓ‬
‫‪...........................‬‬ ‫ﺑﻠﺪﻳﺔ‬

‫ﺗﻘـﺮﻳـﺮ ﺗﻘـﺪﻳﻤـﻲ‬
‫ﺣــــﻮﻝ ﻣﻠﺤـــــﻖ‬

‫** ﺍﻟﺒﺮﻧﺎﻣﺞ ‪ :‬ﺇﻧﺠﺎﺯ ﺛﻼﺛﺔ ﺃﻗﺴﺎﻡ ﺗﻮﺳﻌﺔ ﺑﻤﺪﺭﺳﺔ ‪* ............................‬‬

‫ﻣﻮﺿﻮﻉ ﺍﻟﻤﻠﺤﻖ ‪ :‬ﻳﻬﺪﻑ ﻫﺬﺍ ﺍﻟﻤﻠﺤﻖ ﺇﻟﻰ ﺿﺒﻂ ﺍﻟﻜﻤﻴﺎﺕ ﺍﻟﻨﻬﺎﺋﻴﺔ ﺑﺎﻟﻨﻘﺼﺎﻥ ﻭﺍﻟﺰﻳﺎﺩﺓ ﻟﺒﻌﺾ ﺍﻷﺷﻐﺎﻝ‬
‫ﺍﻟﻤﻮﺟﻮﺩﺓ ﻓﻲ ﺍﻻﺗﻔﺎﻗﻴﺔ ﻭﻗﺪ ﺑﻠﻐﺖ ﻧﺴﺒﺔ ﺗﻌﺪﻳﻞ ﺍﻷﺷﻐﺎﻝ ‪) %02,95‬ﺑﺎﻟﻨﻘﺼﺎﻥ(ﺑﺎﻟﻨﺴﺒﺔ ﻟﻼﺗﻔﺎﻗﻴﺔ‬
‫ﺍﻟﺠﺪﻳﺪﺓ ﺑﻌﺪ ﺇﻋﺪﺍﺩ ﺍﻟﻤﻠﺤﻖ ﺭﻗﻢ ‪ 01‬ﻭﻫﻲ ﺍﻷﺷﻐﺎﻝ ﺍﻟﻤﻮﺟﻮﺩﺓ ﻓﻲ ﺍﻟﺘﻌﻴﻴﻦ ﺭﻗﻢ‪:‬‬
‫‪(B-04. C-02. C-04. C-05. C-07. C-09. C-14. D-01. D-02. D-03. D-04. D-05. D-06‬‬
‫‪ ( (D-08. E-02. F-04. F-06. F-07. F-08. F-09. F-17. G-02. G-03 .‬ﻭ ﺍﻟﺒﻨﻮﺩ ﺫﺍﺕ ﺍﻷﺭﻗﺎﻡ )‪(I-01. I-02. I-04‬‬
‫)‪(.C-01. C06. C-08. C-11. C-12. D-07. E-01. F-05. G-01. H-01. H-02. H-03. I-03‬‬
‫ﺣﻴﺚ ﺍﻧﻪ ﺳﺠﻠﺖ ﻫﺬﻩ ﺍﻟﻌﻤﻠﻴﺔ ﻓﻲ ﺇﻃﺎﺭ ﺍﻟﺼﻨﺪﻭﻕ ﺍﻟﻤﺸﺘﺮﻙ ﻟﻠﺠﻤﺎﻋﺎﺕ ﺍﻟﻤﺤﻠﻴﺔ ﻟﺴﻨﺔ ‪ 2019‬ﺑﻌﻨﻮﺍﻥ‪:‬‬
‫** ﺍﻟﺒﺮﻧﺎﻣﺞ‪ :‬ﺇﻧﺠﺎﺯ ﺛﻼﺛﺔ ﺃﻗﺴﺎﻡ ﺗﻮﺳﻌﺔ ﺑﻤﺪﺭﺳﺔ ‪** ............................‬‬
‫ﺣﻴﺚ ﺗﻢ ﺍﻹﻋﻼﻥ ﻋﻦ ﺍﻃﻠﺐ ﺍﻟﻌﺮﻭﺽ ﺍﻟﻤﻔﺘﻮﺡ ﻣﻊ ﺍﺷﺘﺮﺍﻁ ﻗﺪﺭﺍﺕ ﺩﻧﻴﺎ ;ﻭﻓﻘﺎ ﻟﻺﺟﺮﺍﺀﺍﺕ ﺍﻟﺸﻜﻠﻴﺔ ﻃﺒﻘﺎ ﻟﻠﻤﺎﺩﺓ ‪44‬‬
‫ﻣﻦ ﺍﻟﻤﺮﺳﻮﻡ ﺍﻟﺮﺋﺎﺳﻲ ‪ 247/15‬ﺍﻟﺼﺎﺩﺭ ﺑﺘﺎﺭﻳﺦ ‪ 2015/09/16‬ﻭﻗﺪ ﺗﻢ ﺍﻻﺷﻬﺎﺭﻓﻲ ﺍﻟﺠﺮﺍﺋﺪ ﺍﻟﻮﻃﻨﻴﺔ ﻳﻮﻡ‬
‫‪ 06/10/2020‬ﺑﻤﺪﺓ ﺗﺤﻀﻴﺮ ﺍﻟﻌﺮﻭﺽ ﺗﻘﺪﺭ ﺏ ‪ 12‬ﻳﻮﻡ ‪ ،‬ﻭﺫﻟﻚ ﻋﻦ ﻃﺮﻳﻖ ﺍﻹﺷﻬﺎﺭ ﻓﻲ ﺟﺮﻳﺪﺗﻴﻦ ﻳﻮﻣﻴﺘﻴﻦ‬
‫ﻭﻃﻨﻴﺘﻴﻦ ‪) ،‬ﺑﺎﻟﻠﻐﺔ ﺍﻟﻌﺮﺑﻴﺔ ﺍﻟﻔﺮﻧﺴﻴﺔ ( ﺣﻴﺚ ﺗﻢ ﺍﺳﺘﻼﻡ ﺇﺣﺪﻯ ﻋﺸﺮ ﻋﺮﺿﺎ ﺗﻢ ﻓﺘﺤﻬﺎ ﻳﻮﻡ ‪ 2020/10/18‬ﻋﻠﻰ‬
‫ﺍﻟﺴﺎﻋﺔ ﺍﻟﺜﺎﻧﻴﺔ ﺯﻭﺍﻻ ﻣﻦ ﻗﺒﻞ ﻟﺠﻨﺔ ﻓﺘﺢ ﺍﻻﻇﺮﻓﺔ ﻭ ﺗﻘﻴﻴﻢ ﺍﻟﻌﺮﻭﺽ ‪ ،‬ﻛﻤﺎ ﺗﻢ ﺗﻘﻴﻴﻤﻬﺎ ﻳﻮﻡ ‪.2020/10/20‬‬
‫ﻓﻲ ﺍﻷﺧﻴﺮ ﺗﻢ ﺇﺳﻨﺎﺩ ﺍﻟﻌﻤﻠﻴﺔ ﺇﻟﻰ ﻣﻘﺎﻭﻟﺔ …………………… ﺑﺎﻋﺘﺒﺎﺭﻩ ﻗﺪﻡ ﺍﻗﻞ ﻋﺮﺽ ﺑﻤﺒﻠﻎ ﻳﻘﺪﺭﺏ‪9.707.068,00 :‬‬
‫ﺩﺝ )ﺑﺎﺣﺘﺴﺎﺏ ﻛﻞ ﺍﻟﺮﺳﻮﻡ( ﻭﺑﻤـﺪﺓ ﺇﻧﺠـﺎﺯ ﺗﻘـﺪﺭ ﺏ ‪ 03‬ﺃﺷﻬﺮ ﻭﺟﺮﻯ ﺗﺤﺴﻴﻦ ﺍﻟﻌﺮﺽ ﺑﺘﺎﺭﻳﺦ ‪ 2020/11/15‬ﺑﻌﺪ‬
‫ﺍﻟﻤﻨﺢ ﺍﻟﻤﺆﻗﺖ ﺍﻟﻤﺆﺭﺥ ﺏ ‪ 2020 /10/27‬ﻟﻴﺼﺒﺢ ﺍﻟﻤﺒﻠﻎ ﺍﻟﺠﺪﻳﺪ ﻟﻼﺗﻔﺎﻗﻴﺔ ‪ 464 391.30 9‬ﺩﺝ‬
‫ﺗﻤﺖ ﺟﻠﺴﺔ ﻓﺘﺢ ﺍﻟﻌﺮﻭﺽ ﻳﻮﻡ ‪ ،2020/10/18‬ﻣﻦ ﻗﺒﻞ ﻟﺠﻨﺔ ﻓﺘﺢ ﺍﻻﻇﺮﻓﺔ ﻭﻫﻲ ﻛﺎﻟﺘﺎﻟﻲ ‪:‬‬
‫ﻣﺪﺓ ﺍﻻﻧﺠﺎﺯ‬ ‫ﺍﻟﻤﺒﻠﻎ ﺍﻟﻤﻘﺘﺮﺡ‬ ‫ﺍﺳﻢ ﺍﻟﻤﺆﺳﺴﺔ‬ ‫ﺍﻟﺮﻗﻢ‬
‫‪ 08‬ﺃﺷﻬﺮ‬ ‫‪10.680.559,40‬‬ ‫‪01‬‬
‫‪03‬ﺃﺷﻬﺮ‬ ‫‪8.946.717,50‬‬ ‫‪02‬‬
‫‪06‬ﺃﺷﻬﺮ‬ ‫‪11.219.855,50‬‬ ‫‪03‬‬
‫‪06‬ﺃﺷﻬﺮ‬ ‫‪9.198.700,00‬‬ ‫‪04‬‬
‫‪06‬ﺃﺷﻬﺮ‬ ‫‪9.576.108,50‬‬ ‫‪05‬‬
‫‪05‬ﺃﺷﻬﺮ‬ ‫‪10.572.198,00‬‬ ‫‪06‬‬
‫‪03‬ﺃﺷﻬﺮ‬ ‫‪9.707.068,00‬‬ ‫‪07‬‬
‫‪05‬ﺃﺷﻬﺮ‬ ‫‪12 610 370,50‬‬ ‫‪08‬‬
‫‪06‬ﺃﺷﻬﺮﺍﻭ‪ 20‬ﻳﻮﻡ‬ ‫‪11.433.186,80‬‬ ‫‪09‬‬
‫‪03‬ﺃﺷﻬﺮ‬ ‫‪10.165.039,50‬‬ ‫‪10‬‬
‫‪05‬ﺃﺷﻬﺮ‬ ‫‪10.232.036,50‬‬ ‫‪11‬‬
‫‪04‬ﺃﺷﻬﺮ‬ ‫‪11.220.914,60‬‬ ‫‪12‬‬
‫‪09‬ﺃﺷﻬﺮ‬ ‫‪11.172.077,00‬‬ ‫‪13‬‬
‫‪05‬ﺃﺷﻬﺮ‬ ‫‪10.066.626,50‬‬ ‫‪14‬‬
‫‪04‬ﺃﺷﻬﺮ‬ ‫‪8.739.824,10‬‬ ‫‪15‬‬

‫ﺗﻘﻴﻴﻢ ﺍﻟﻌﺮﻭﺽ‪:‬‬
‫ﺗﻘﻴﻴﻢ ﺍﻟﻌﺮﻭﺽ ﺍﻟﺘﻘﻨﻴﺔ‬
‫‪ -‬ﺗﺎﺭﻳﺦ ﺍﻻﺟﺘﻤﺎﻉ‪.2020/10/20:‬‬
‫ﺍﻟﻤﺠﻤﻮﻉ‬ ‫ﻣﺨﻄﻂ ﺍﻷﺷﻐﺎﻝ‬ ‫ﺍﺟﺎﻝ ﺍﻟﺘﻨﻔﻴﺬ‬ ‫ﺍﻻﻣﻜﺎﻧﻴﺎﺕ‬ ‫ﺍﻟﻌﺘﺎﺩ‬ ‫ﺍﺳﻢ ﺍﻟﻤﺆﺳﺴﺔ‬ ‫ﺍﻟﺮﻕ‬
‫‪ 100‬ﻥ‬ ‫‪ 05‬ﻥ‬ ‫‪15‬ﻥ‬ ‫ﺍﻟﺒﺸﺮﻳﺔ‬ ‫‪ 50‬ﻥ‬ ‫ﻡ‬
‫‪ 30‬ﻥ‬
‫‪52.62‬‬ ‫‪05.00‬‬ ‫‪05.62‬‬ ‫‪20‬‬ ‫‪22.00‬‬ ‫‪01‬‬
‫‪64.00‬‬ ‫‪00.00‬‬ ‫‪09.00‬‬ ‫‪15.00‬‬ ‫‪40.00‬‬ ‫‪02‬‬
‫‪59.75‬‬ ‫‪05.00‬‬ ‫‪7.50‬‬ ‫‪12.00‬‬ ‫‪32.25‬‬ ‫‪03‬‬
‫‪42.25‬‬ ‫‪05.00‬‬ ‫‪07.50‬‬ ‫‪09.00‬‬ ‫‪20.75‬‬ ‫‪04‬‬
‫‪55.50‬‬ ‫‪05.00‬‬ ‫‪07.50‬‬ ‫‪07.00‬‬ ‫‪36.00‬‬ ‫‪05‬‬
‫‪65.00‬‬ ‫‪05.00‬‬ ‫‪09.00‬‬ ‫‪16.00‬‬ ‫‪35.00‬‬ ‫‪06‬‬
‫‪84.12‬‬ ‫‪00.00‬‬ ‫‪13.12‬‬ ‫‪38.00‬‬ ‫‪33.00‬‬ ‫‪07‬‬
‫‪29.75‬‬ ‫‪02.50‬‬ ‫‪09.00‬‬ ‫‪00.00‬‬ ‫‪18.25‬‬ ‫‪08‬‬
‫‪55.75‬‬ ‫‪05.00‬‬ ‫‪06.75‬‬ ‫‪04.00‬‬ ‫‪40.00‬‬ ‫‪09‬‬
‫‪61.25‬‬ ‫‪05.00‬‬ ‫‪15.00‬‬ ‫‪03.00‬‬ ‫‪38.25‬‬ ‫‪10‬‬
‫‪74.50‬‬ ‫‪05.00‬‬ ‫‪09.00‬‬ ‫‪22.00‬‬ ‫‪38.50‬‬ ‫‪11‬‬
‫ﻧﺘﻴﺠﺔ ﺍﻟﺘﻘﻴﻴﻢ ‪:‬‬
‫‪/2‬ﺍﻟﻤﺮﺣﻠﺔ ﺍﻟﻤﺎﻟﻴﺔ ‪:‬‬
‫ﺍﻟﻤﻼﺣﻈﺔ‬ ‫ﻣﺒﻠﻎ ﺍﻟﻌﻤﻠﻴﺔ ﺑﻌﺪ ﺍﻟﺘﺼﺤﻴﺢ‬ ‫ﺍﺳﻢ ﺍﻟﻤﺆﺳﺴﺔ‬ ‫ﺍﻟﺮﻕ‬
‫ﻣﺒﻠﻎ ﺍﻟﻌﻤﻠﻴﺔ‬
‫ﻡ‬
‫‪10.680.559,40‬‬ ‫‪10.680.559,40‬‬ ‫‪01‬‬
‫‪10.066.626,50‬‬ ‫‪10.066.626,50‬‬ ‫‪02‬‬
‫‪11.219.855,50‬‬ ‫‪11.219.855,50‬‬ ‫‪03‬‬
‫ﻓﺎﺯ ﺑﺎﻟﺤﺼﺔ ﺍﻷﻭﻟﻰ‪.…………:‬ﻭ‬ ‫‪04‬‬
‫ﺗﻢ ﺍﻗﺼﺎﺅﻩ ﻣﻦ ﺍﻟﺤﺼﺔ ﺍﻟﺜﺎﻧﻴﺔ‬ ‫‪9.576.108,50‬‬ ‫‪9.576.108,50‬‬
‫ﺣﺴﺐ ﺩﻓﺘﺮ ﺍﻟﺸﺮﻭﻁ‬
‫‪10.572.198,00‬‬ ‫‪10.572.198,00‬‬ ‫‪05‬‬
‫ﺍﻗﻞ ﻋﺮﺽ ‪:‬ﺍﻟﺤﺼﺔ ﺍﻟﺜﺎﻧﻴﺔ‬ ‫‪9.707.068,00‬‬ ‫‪9.707.068,00‬‬ ‫‪06‬‬
‫‪11.433.186,80‬‬ ‫‪11.433.186,80‬‬ ‫‪07‬‬
‫‪10.165.039,50‬‬ ‫‪10.165.039,50‬‬ ‫‪08‬‬
‫‪10.232.036,50‬‬ ‫‪10.232.036,50‬‬ ‫‪09‬‬
‫ﻓﻲ ﺍﻷﺧﻴﺮ ﺍﻗﺘﺮﺣﺖ ﺍﻟﻠﺠﻨﺔ ﺍﻟﺘﻌﺎﻣﻞ ﻣﻊ ﻣﻘﺎﻭﻟﺔ ……………………… ﺑﺎﻋﺘﺒﺎﺭﻩ ﻗﺪﻡ ﺍﻗﻞ ﻋﺮﺽ ﺑﻤﺒﻠﻎ ﻋﺮﺽ ﻳﻘﺪﺭ‬

‫ﺏ ‪ 9.707.068,00‬ﺩﺝ ﻭﺑﻤﺪﺓ ﺍﻧﺠﺎﺯ ﻳﻘﺪﺭ ﺏ ‪ 03‬ﺍﺷﻬﺮ‪ .‬ﻭ ﺑﻌﺪ ﺗﺤﺴﻴﻦ ﺍﻟﻌﺮﺽ ﺃﺻﺒﺢ ﻣﺒﻠﻎ ﺍﻻﺗﻔﺎﻗﻴﺔ ‪464 391.30 9‬ﺩﺝ‬
‫ﺃﺳﺒﺎﺏ ﺍﻟﻠﺠﻮﺀ ﺇﻟﻰ ﺍﻟﻤﻠﺤﻖ ﺿﺒﻂ ﺍﻟﻜﻤﻴﺎﺕ ﺍﻟﻨﻬﺎﺋﻴﺔ‪:‬‬

‫ﺣﻴﺚ ﺍﻧﻪ ﺑﻌﺪ ﺍﻟﺘﺄﺷﻴﺮ ﻋﻠﻰ ﺍﻻﺗﻔﺎﻗﻴﺔ ﻣﻦ ﻃﺮﻑ ﺍﻟﻤﺮﺍﻗﺐ ﺍﻟﻤﺎﻟﻲ ﺑﺘﺎﺭﻳﺦ ‪ ، 2020/12/07‬ﺗﻢ ﺗﺴﻠﻴﻢ ﺃﻣﺮ ﺑﺪﺍﻳﺔ ﺍﻷﺷﻐﺎﻝ‬
‫ﻳﻮﻡ ‪ ، 2021/01/31‬ﺇﻻ ﺍﻧﻪ ﺃﺛﻨﺎﺀ ﺍﻧﺠﺎﺯ ﺍﻷﺷﻐﺎﻝ ‪ ،‬ﺗﺒﻴﻦ ﻣﺎﻳﻠﻲ‪:‬‬
‫ﺍﻥ ﺍﻟﺒﻨﻮﺩ ﺫﺍﺕ ﺍﻻﺭﻗﺎﻡ ‪:‬‬
‫‪(C-02. C-04. C-05. C-07. C-09.. D-01. D-02. D-03. D-04. D-05. D-06 .‬‬
‫‪ ( (D-08. E-02. F-04. F-06. F-07. F-08. F-09. F-17. G-03 .‬ﻭ ﺍﻟﺒﻨﻮﺩ ﺫﺍﺕ ﺍﻷﺭﻗﺎﻡ )‪ (I-01. I-02. I-04‬ﺍﻟﺨﺎﺻﺔ‬
‫ﺑﺎﻟﻤﻠﺤﻖ ﺭﻗﻢ ‪ 01‬ﺣﺼﻞ ﻓﻴﻬﺎ ﻧﻘﺼﺎﻥ ﺑﺴﺒﺐ ﺧﻄﺎ ﻓﻲ ﺍﻟﺘﻤﺘﻴﺮ ﻭ ﺍﻟﺘﻘﺪﻳﺮ ﻣﻦ ﻃﺮﻑ ﻣﻜﺘﺐ ﺍﻟﺪﺭﺍﺳﺎﺕ ﺍﻟﺬﻱ ﺍﻋﺪ‬
‫ﺍﻟﺒﻄﺎﻗﺔ ﺍﻟﺘﻘﻨﻴﺔ ﺑﻤﺴﺎﺣﺔ ﺃﺭﺿﻴﺔ ﺍﻛﺒﺮ ﻣﻦ ﺍﻷﺭﺿﻴﺔ ﺍﻟﺤﻘﻴﻘﻴﺔ ﻟﻠﻤﺸﺮﻭﻉ ﺑﺴﺒﺐ ﺍﻟﺘﺮﺍﺟﻊ ﻋﻦ ﻭﺿﻊ ﺳﻼﻟﻢ ﻟﻠﺼﻌﻮﺩ ﻭ‬
‫ﺇﻟﺼﺎﻕ ﺍﻷﻗﺴﺎﻡ ﺍﻟﺠﺪﻳﺪﺓ ﺑﺎﻷﻗﺴﺎﻡ ﺍﻟﻘﺪﻳﻤﺔ ﻟﺘﻔﺎﺩﻱ ﺍﻧﺠﺎﺯ ﺍﻟﺴﻼﻟﻢ ﺇﻟﻰ ﺟﺎﻧﺐ ﺗﺪﺧﻞ ﺍﻟﻬﻴﺌﺔ ﺍﻟﻮﻃﻨﻴﺔ ﻟﻤﺮﺍﻗﺒﺔ‬
‫ﺍﻟﺒﻨﺎﻳﺎﺕ ‪ CTC‬ﻭﺍﺳﺘﺒﺪﺍﻝ ﺑﻌﺾ ﺃﺟﺰﺍﺀ ﺍﻟﺴﻘﻒ ﻣﻦ ﺳﻘﻒ ﻋﺎﺩﻱ ﺇﻟﻰ ﺳﻘﻒ ﺑﺨﺮﺳﺎﻧﺔ ﻣﺴﻠﺤﺔ ﻣﻤﻠﻮﺀﺓ ﺑﺎﻹﺿﺎﻓﺔ ﺍﻟﻰ‬
‫ﺑﻌﺾ ﺍﻟﺘﻌﺪﻳﻼﺕ ﺍﻟﺘﻲ ﺃﻗﺮﺗﻬﺎ ﺍﻟﻤﺼﻠﺤﺔ ﺍﻟﻤﺘﻌﺎﻗﺪﺓ ﻣﻊ ﻣﻜﺘﺐ ﺍﻟﺪﺭﺍﺳﺎﺕ ﻓﻲ ﺍﻟﻤﺸﺮﻭﻉ ﺗﺒﻌﺎ ﻟﺘﻌﻠﻴﻤﺎﺕ ﺭﺋﻴﺲ‬
‫ﺍﻟﺠﻤﻬﻮﺭﻳﺔ ﺑﻀﺮﻭﺭﺓ ﺍﺳﺘﺒﺪﺍﻝ ﻧﺠﺎﺭﺓ ﺍﻟﺨﺸﺐ ﺑﻨﺠﺎﺭﺓ ‪ PVC‬ﺑﻐﺮﺽ ﺍﻟﺤﻔﺎﻅ ﻋﻠﻰ ﺍﻟﻤﻮﺍﺭﺩ ﺍﻟﺒﻴﺌﻴﺔ ﻭ ﺗﺨﻔﻴﺾ‬
‫ﻓﺎﺗﻮﺭﺓ ﺍﺳﺘﺮﺍﺩ ﺍﻟﺨﺸﺐ‪.‬‬
‫ﻭ ﻓﻴﻤﺎ ﻳﺨﺺ ﺍﻟﺒﻨﻮﺩ ﺍﻟﺘﻲ ﻟﻢ ﺗﻨﺠﺰ ﻛﻠﻴﺎ ‪.B-04.F09.G02. C-14. F-06. F-07‬‬

‫‪ B-04‬ﻟﻢ ﺑﺘﻢ ﺍﻧﺠﺎﺯﻩ ﺑﺴﺒﺐ ﺗﻮﺍﻓﻖ ﻣﺴﺘﻮﻯ ﺍﻻﻗﺴﺎﻡ ﺍﻟﻘﺪﻳﻤﺔ ﻣﻊ ﺍﻟﺠﺪﻳﺪﺓ ﻭ ﻛﺎﻥ ﺗﻢ ﺍﺩﺭﺍﺟﻪ ﻓﻲ ﺍﻟﺘﻘﺪﺩﻳﺮ ﺍﻻﺩﺍﺭﻱ ﻣﻦ‬
‫ﺍﺟﻞ ﺗﺪﺍﺭﻙ ﺍﺧﺘﻼﻑ ﺍﻟﻤﺴﺘﻮﻯ‪.‬‬
‫‪ C-14‬ﻗﺮﺭﺕ ﺍﻟﻤﺼﻠﺤﺔ ﺍﻟﻤﺘﻌﺎﻗﺪﺓ ﺭﻓﻘﺔ ﻣﻜﺘﺐ ﺍﻟﺪﺭﺍﺳﺎﺕ ﺍﺳﺘﺒﺪﺍﻝ ﺍﻟﻮﺍﻗﻲ ﺍﻟﺤﺪﻳﺪﻱ ﺑﺠﺪﺍﺭ ﺍﺳﻤﻨﺘﻲ ﺣﻔﺎﻇﺎ ﻋﻠﻰ ﺻﺤﺔ‬
‫ﺍﻟﺘﻼﻣﻴﺬ ﺑﻤﺎ ﺍﻥ ﺍﺍﻻﻗﺴﺎﻡ ﻭﺟﻬﺖ ﻟﻠﺴﻨﺔ ﺍﻻﻭﻟﻰ ﺍﺑﺘﺪﺍﺋﻲ ﺍﻟﺜﺎﻧﻴﺔ‪.‬‬
‫‪ F-06‬ﻭ ‪F-07‬ﺗﻢ ﺍﻟﺘﺨﻠﻲ ﻋﻨﻬﻤﺎ ﺑﺴﺒﺐ ﻣﻮﻗﻌﻬﻤﺎ ﺍﻟﺴﺎﺑﻖ ﻓﻲ ﺍﻟﺴﻼﻟﻢ‪.‬‬
‫‪ F09‬ﺑﻌﺪ ﺗﻌﻄﻞ ﺟﺮﺱ ﺍﻟﻤﺪﺭﺳﺔ ﺍﻟﻤﺪﺭﺳﺔ ﻗﺮﺭﺕ ﺍﻟﺒﻠﺪﻳﺔ ﺍﺩﺭﺍﺟﻪ ﻓﻲ ﺍﻻﺗﻔﺎﻗﻴﺔ ﺍﻻ ﺍﻥ ﻛﻬﺮﺑﺎﺋﻲ ﺍﻟﻤﻘﺎﻭﻟﺔ ﺍﺻﻠﺤﻪ ﻓﺘﻢ‬
‫ﺍﻻﺳﺘﻐﻨﺎﺀ ﻋﻦ ﻋﻦ ﻫﺬﺍ ﺍﻟﺒﻨﺪ‪.‬‬
‫‪ G02‬ﺗﺒﻌﺎ ﻟﺘﻌﻠﻴﻤﺎﺕ ﺭﺋﻴﺲ ﺍﻟﺠﻤﻬﻮﺭﻳﺔ ﺑﻀﺮﻭﺭﺓ ﺍﺳﺘﺒﺪﺍﻝ ﻧﺠﺎﺭﺓ ﺍﻟﺨﺸﺐ ﺑﻨﺠﺎﺭﺓ ‪ PVC‬ﺑﻐﺮﺽ ﺍﻟﺤﻔﺎﻅ ﻋﻠﻰ‬
‫ﺍﻟﻤﻮﺍﺭﺩ ﺍﻟﺒﻴﺌﻴﺔ ﻭ ﺗﺨﻔﻴﺾ ﻓﺎﺗﻮﺭﺓ ﺍﺳﺘﺮﺍﺩ ﺍﻟﺨﺸﺐ‪.‬‬
‫ﺍﻣﺎ ﺍﻟﺒﻨﻮﺩ ﺫﺍﺕ ﺍﻷﺭﻗﺎﻡ ‪:‬‬
‫)‪ (.C-01. C06. C-08. C-11. C-12. D-07. E-01. F-05. G-01. H-01. H-02. H-03. I-03‬ﺣﺼﻞ ﻓﻴﻬﺎ‬
‫ﺯﻳﺎﺩﺓ ﺑﺴﺒﺐ ﻋﺪﻡ ﺩﻗﺔ ﺍﻟﺘﻘﺪﻳﺮ ﺍﻹﺩﺍﺭﻱ ﻭ ﺍﻟﺘﻌﺪﻳﻼﺕ ﺍﻟﺘﻘﻨﻴﺔ ﺍﻟﺘﻲ ﻃﺮﺃﺕ ﻋﻠﻰ ﺍﻟﻤﺸﺮﻭﻉ‪.‬‬

‫ﻣﻦ ﺍﺟﻞ ﺗﺴﻮﻳﺔ ﺍﻟﻜﻤﻴﺎﺕ ﺍﻟﻨﻬﺎﺋﻴﺔ ﻟﻠﻤﺸﺮﻭﻉ ﺗﻢ ﺍﺗﻔﺎﻕ ﺍﻷﻃﺮﺍﻑ ﺍﻟﻤﺘﻌﺎﻗﺪﺓ ﻋﻠﻰ ﺇﺑﺮﺍﻡ ﻣﻠﺤﻖ ﻟﻀﺒﻂ ﺍﻟﻜﻤﻴﺎﺕ ﺍﻟﻨﻬﺎﺋﻴﺔ ﻟﻴﺼﺒﺢ‬
‫ﺍﻟﻤﺒﻠﻎ ﻛﺎﻟﺘﺎﻟﻲ‪:‬‬
‫ﺍﻟﻤﺒﻠﻎ ﺍﻷﻭﻟﻲ ﻟﻼﺗﻔﺎﻗﻴﺔ ‪ 464 391.30 9 :‬ﺩﺝ‬
‫ﻣﺒﻠﻎ ﺍﻷﺷﻐـﺎﻝ ﺑﺎﻟﻨﻘﺼﺎﻥ)ﻓﻲ ﺇﻃﺎﺭ ﺍﻻﺗﻔﺎﻗﻴﺔ( ‪ 676 459,40 :‬ﺩﺝ‪.‬‬
‫ﻣﺒﻠﻎ ﺍﻷﺷﻐـﺎﻝ ﺑﺎﻟﻨﻘﺼﺎﻥ)ﺧﺎﺭﺝ ﺍﻃﺎﺭ ﺍﻻﺗﻔﺎﻗﻴﺔ( ‪ : 418 050,57‬ﺩﺝ‪.‬‬
‫ﻣﺒﻠﻎ ﺍﻷﺷﻐـﺎﻝ ﺑﺎﻟﺰﻳﺎﺩﺓ )ﺧﺎﺭﺝ ﺇﻃﺎﺭ ﺍﻻﺗﻔﺎﻗﻴﺔ(‪93 127,02 :‬ﺩﺝ‪.‬‬
‫ﻣﺒﻠﻎ ﺍﻷﺷﻐـﺎﻝ ﺑﺎﻟﺰﻳﺎﺩﺓ)ﻓﻲ ﺇﻃﺎﺭ ﺍﻻﺗﻔﺎﻗﻴﺔ( ‪ :760 539,23‬ﺩﺝ‪.‬‬
‫ﻣﺒﻠﻎ ﻣﻠﺤﻖ ﺿﺒﻂ ﺍﻟﻜﻤﻴﺎﺕ ﺍﻟﻨﻬﺎﺋﻴﺔ )ﺑﺎﻟﻨﻘﺼﺎﻥ (‪ 240 843,72 :‬ﺩﺝ‪.‬‬
‫ﻣﺒﻠﻎ ﺍﻟﻤﻠﺤﻖ ﺭﻗﻢ ‪ 8 158 552,33 : 01‬ﺩﺝ‪.‬‬
‫ﺍﻟﻤﺒﻠﻎ ﺍﻟﺠﺪﻳﺪ ﻟﻼﺗﻔﺎﻗﻴﺔ ‪ 7 917 708,61 :‬ﺩﺝ ‪.‬‬

‫‪................‬‬ ‫ﺣﺮﺭ ﺏ……ﻓﻲ ‪:‬‬


‫ﺭﺋﻴﺲ ﺍﻟﻤﺠﻠﺲ ﺍﻟﺸﻌﺒﻲ‬
‫ﺍﻟﺒﻠﺪﻱ‬