29-04-2022 360

Civil Electrical Total Deviation


Total Agreement Value 8,89,71,958.00 4,74,38,042.00 13,64,10,000.00 1,26,13,220.00 14,90,23,220.00
Total Work Done 4,43,91,052.00 53,96,486.00 4,97,87,538.00 4,97,87,538.00
40% 36.50% 9,92,35,682.00
Final Date 28-08-2023 28-08-2023 66.59%
Total Revised duration 486.06 days 486.06 days
Duration deducted due to less
work done 131.39 days 239.73 days days
Final Date 18-04-2023 31-12-2022 days
Delay due to contractor final date -
date of determination -90.33 days -198.67 days

Compensation diff bw final dates 131.39 days 239.73 days days