ABSTRACT FOR ''IMPROVEMENT & RESTORATION TO SASON MAIN CANAL FROM RD 00 TO 14.

75
KM''
Achieved Target for this Season
Bed PCC (m) Bed Lining (m) Wall (m) Slope Lining (m) Bed PCC (m) Bed Lining (m) Wall (m)
Reach 1 (0-3482m) 700 700 522 2782 2782
Reach 2 (3482-7160m) 2300 2300 637 1378 1378
Reach 3A (7160-9730m) 1074 1074 678 1496 1496 1496
Reach 3B (9730-11207m) 443 443 290 1034 1034 1034
Reach 4 (11207-14750m) 1725 1725 317 697 1818 1818 400
Total 6242 6242 1285 1856 8508 8508 2930