14th,November, 2023
I would like to inform you that I and my client arrived to the paper recycling line order conclusions:
1- Specifications:
- Need 10-15 Ton
- Width 1000-2000mm
- two pulp making line
one produce Kraft paper jumbo and one produce white cultural paper:
- Thickness of 80-250gsm
- Boiler of Diesel
Questions :
(1) you want use one paper making machine to produce two different paper , sometimes produce
kraft paper , sometimes produce cultural paper ?
(2) two pulp making line , each pulp making line design 10-15ton per day ?
(3) for paper width 1000-2000mm, you want your paper machine output width max 2000mm ?
or we can design paper machine net width within this width scope ,For example , we design
machine output paper width 1600mm , is it okay ?
- Cost of sending experts for Implementating and experimenting and training per day or month
including all allowances like travel tickets, etc.
(1)Expert salary is 3000usd per month one engineer ,usually send 2 experts.
Implementating installation and experimenting machines will need about 4-6months .
The time can be longer or shorter ,it depends on your local installation team working efficiency .and
your local factory land conditions.our expert will also help with the installation sometimes.
(2)When machine test well and start normal working , experts will train your local employees ,
It can be 1 month or longer ,it depends on you .
(3)Customer also need pay for visa ,round tickets ,food ,room ,also China domestic transportation
cost to airport ,we don’t know the exact cost for this part because of the war in Yemen.
Two Experts guiding installation ,testing machine ,and training your local employees, only salary
during this period, it will be around 42,000 usd(for total 7months).
- Needed Space
It will need around 3500-5000square meter , bigger is better.
- Insurance from any land or sea risks and damages included or no,
if shipping company allow it ,we can buy insurance for you according to your needs.
- Warranty of Origin and Maintenance and Installation and Implementation and Spare parts
availability. Here i don’t understand
- Methods of payments as LC availability and Bank Performance Credit or Bank warranty or T/T or
etc
We usually use T/T payment ,and irrevocable confirmed LC at sight . for payment terms after we
confirm the machine design, before signing contract , can discuss with our Chairman finally.
- Delivery time starting from manufacturing to arriving the shipment to the arrival port.
It will take around100 working days , as dryers production needs longer time .