You are on page 1of 7

Project: Sabah Al‐Salem University City ‐Kuwait

University

Contract No: KU/KUCP/C0600/14‐15

Contract: Administration Facilities

TESTING COMMISSIOINING PROCEDURE/CHECKLIST

DUPLEX SUBMERSIBLE PUMP SET AT CULTURAL,

CONVOCATION AND LIBRARY BUILDING

Consultant: SOM‐PACE

MEP – Contractor: Al‐Ahlia Integrated


Index

1 ‐ Reference Standards & Specification

2 ‐ Technical Specification

3 ‐ Testing Commissioning Report

4 – Warranty Activation

4 – System Demonstration
1 – Reference Standards & Specification

The Following Contract Specification reference section 220000, 223200 & 01800
and relevant Standards shall be complied.

A) Section 220000, Clause 3.5: Adjusting & System demonstration.

B) Section 220000, Clause 1.5: Operation & Maintenance.

C) Section 22000, Clause 1.6: Warranty.

D) Section 223200, Clause 3.4: Field Quality Assurance.

E) Section 223200, Clause: 3.5 Demonstration.

F) Section 018100, Clause General Commissioning requirements.


2 – Technical Specification
3 – Testing & commissioning Report
4 – Warranty Activation
5 –System Demonstration
The Commissioning shall be supervised by our competent Engineer and training
for owners’ maintenance personnel shall be provided after successful
commissioning of the Electric Water Heater.

System demonstration shall be conducted only after substantial completion of


the project.