PEMBANGUNAN PLTA KERINCI MERANGIN H

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Senin, 16 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 14:30 7:30 Safety Shotcrete 10 m³
2 14:45 17:00 2:15 Drilling Face (60 Hole, 3m Depth)
3 17:00 17:40 0:40 Charging and Blasting
4 17:40 17:50 0:10 Ventillating
5 17:50 20:20 2:30 Mucking Out (4 DT Howo)
6 20:20 20:50 0:30 Scalling & Cleaning
7 20:50 21:20 0:30 Survey & Marking
8 21:30 23:00 1:30 Install Steel Ribs 1 set STA 7297.363
9 23:00 1:30 2:30 Install Wiremesh 1 roll STA 7297.363
10 2:00 7:00 5:00 Safety Shotcrete 10 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1
2 Asst Formen 1 2 Genset 250 Kva 1
3 Operator 1 3 Compressor 750 CFM 2
4 Miner 9 4 Blower 110 1
5 Operator/ Driver 2 5 Shotcrete Aliva 2
6 SPV 1 6 Wheel Loader 1
7 Pelaksana /Surveyor 1 7 Sanchin 2
8 8 Jack Hammer 4
9 9 Breaker SH210 (07) 1
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
UNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

AILY REPORT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
aan Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7295.919 7297.363 1.444 1.444

Material Type Jumlah Satuan

1 Sigunit L-72 AF pcs


2 Semen pcs
3 Pasir Liter
4 Crushing Brush Sak
5 Oxygen M3
6 Apart Pcs
7 Mata Gerinda Tbg
8 Ring Baut 32 Bh
9 Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Selasa, 17 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 10:30 3:30 Continues Safety Shotcrete
2 11:00 14:00 3:00 Standby Dewatering
3 14:30 17:10 2:40 Drilling Face (60 Hole, 3m Depth)
4 17:10 17:40 0:30 Charging and Blasting
5 17:40 18:00 0:20 Ventillating
6 18:00 20:30 2:30 Mucking Out (4 DT Howo)
7 20:30 21:00 0:30 Scalling & Cleaning
8 21:00 21:30 0:30 Survey & Marking
9 22:00 23:30 1:30 Install Steel Ribs 1 set STA 7300.387
10 23:30 1:00 1:30 Install Wiremesh 1 roll STA 7300.387
11 1:00 7:00 6:00 Safety Shotcrete 5 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7297.363 7300.387 3.024 4.468

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Rabu, 18 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 11:00 4:00 Continues Safety Shotcrete 4 m³
2 11:00 7:00 20:00 Standby Dewatering
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-
-

Prepared by
Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream Jam : 07:00 - 07:00 WIB


Hari/Tanggal : Kamis, 19 Agustus 2021 Shift : Day & Night

Jam Kerja Waktu STA


No Uraian Pekerjaan Ket.
Mulai Selesai (Menit) AWAL AKHIR +EXCAVASI (m) TOTAL (m)
1 7:00 10:00 3:00 Standby Dewatering
2 10:00 11:30 1:30 Drilling Face (60 Hole, 3m Depth)
3 11:30 12:05 0:35 Charging and Blasting 7300.387 7300.896 0.509 4.977
4 12:05 12:20 0:15 Ventillating
5 12:20 14:30 2:10 Mucking Out (4 DT Howo)
6 14:30 15:00 0:30 Scalling & Cleaning
7 17:30 18:00 0:30 Survey & Marking
8 19:00 21:00 2:00 Install Steel Ribs 1 set STA 7300.896
9 21:00 23:45 2:45 Install Wiremesh 1 roll STA 7300.896
10 0:00 6:00 6:00 Safety Shotcrete 9 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material Type Jumlah Satuan
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1 Sigunit L-72 AF pcs
2 Asst Formen 1 2 Genset 250 Kva 1 2 Semen pcs
3 Operator 1 3 Compressor 750 CFM 2 3 Pasir Liter
4 Miner 9 4 Blower 110 1 4 Crushing Brush Sak
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5 Oxygen M3
6 SPV 1 6 Wheel Loader 1 6 Apart Pcs
7 Pelaksana /Surveyor 1 7 Sanchin 2 7 Mata Gerinda Tbg
8 8 Jack Hammer 4 8 Ring Baut 32 Bh
9 9 Breaker SH210 (07) 1 9 Sekop Pcs
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by Approved by

Satria Ronaldo
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Jum'at, 20 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 8:30 1:30 Drilling Face (60 Hole, 3m Depth)
2 8:30 9:05 0:35 Charging and Blasting
3 9:05 9:20 0:15 Ventillating
4 9:20 11:30 2:10 Mucking Out (4 DT Howo)
5 11:30 14:00 2:30 Break Pray Jum'at
6 14:00 16:00 2:00 Scalling & Cleaning
7 16:00 16:30 0:30 Survey & Marking
8 16:30 18:00 1:30 Install Steel Ribs 1 set STA 7303.121
9 18:00 20:30 2:30 Install Wiremesh 1 roll STA 7303.121
10 21:00 5:00 8:00 Safety Shotcrete 12 m³
11 6:30 7:00 0:30 Drilling Face (60 Hole, 3m Depth)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7300.896 7303.121 2.225 7.202

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Sabtu, 21 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 8:30 1:30 Continues Drilling Face (60 Hole, 3m Depth)
2 8:30 9:00 0:30 Charging and Blasting
3 9:00 9:15 0:15 Ventillating
4 9:15 11:45 2:30 Mucking Out (4 DT Howo)
5 11:45 12:20 0:35 Scalling & Cleaning
6 12:20 12:50 0:30 Survey & Marking
7 13:30 15:30 2:00 Install Steel Ribs 1 set STA 7305.433
8 15:30 18:00 2:30 Install Wiremesh 1 roll STA 7305.433
9 18:30 23:30 5:00 Safety Shotcrete 7 m³
10 0:00 2:15 2:15 Drilling Face (60 Hole, 3m Depth)
11 2:15 2:45 0:30 Charging and Blasting
12 2:45 3:00 0:15 Ventillating
13 3:00 5:00 2:00 Mucking Out (4 DT Howo)
14 5:00 5:30 0:30 Scalling & Cleaning
15 5:30 6:00 0:30 Survey & Marking
16 6:00 7:00 1:00 Standby Dewatering
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7303.121 7305.433 2.312 9.514

7305.433 7307.275 1.842 11.356

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Minggu, 22 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 11:30 4:30 Standby Dewatering
2 12:00 13:30 1:30 Safety Shotcrete 7 m³
3 15:30 17:00 1:30 Install Steel Ribs 1 set STA 7307.275
4 17:00 18:30 1:30 Install Forepoling 16 pcs STA 7307.275
5 18:30 20:30 2:00 Install Wiremesh 1 roll STA 7307.275
6 20:30 4:00 7:30 Safety Shotcrete 10 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by