PEMBANGUNAN PLTA KERINCI MERANGIN H

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Senin, 02 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 9:00 2:00 Standby Dewatering
2 9:00 12:00 3:00 Excavation (Breaker & Scalling)
3 13:00 14:00 1:00 Mucking Out (3 DT Howo)
4 14:00 14:30 0:30 Survey & Marking
5 15:00 17:00 2:00 Install Steel Ribs 1 set STA 7278.234
6 17:00 18:00 1:00 Install Wiremesh 1 roll STA 7278.234
7 18:00 0:00 6:00 Safety Shotcrete 12 m³
8 0:00 7:00 7:00 Standby Dewatering
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1
2 Asst Formen 1 2 Genset 250 Kva 1
3 Operator 1 3 Compressor 750 CFM 2
4 Miner 9 4 Blower 110 1
5 Operator/ Driver 2 5 Shotcrete Aliva 2
6 SPV 1 6 Wheel Loader 1
7 Pelaksana /Surveyor 1 7 Sanchin 2
8 8 Jack Hammer 4
9 9 Breaker SH210 (07) 1
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-
Prepared by

Satria Ronaldo
UNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

AILY REPORT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
aan Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7276.75 7278.234 1.484 1.484

Material Type Jumlah Satuan

1 Sigunit L-72 AF pcs


2 Semen pcs
3 Pasir Liter
4 Crushing Brush Sak
5 Oxygen M3
6 Apart Pcs
7 Mata Gerinda Tbg
8 Ring Baut 32 Bh
9 Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Selasa, 03 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 8:30 1:30 Standby Dewatering
2 8:30 12:00 3:30 Excavation (Breaker & Scalling)
3 12:30 13:30 1:00 Mucking Out (3 DT Howo)
4 14:00 14:30 0:30 Survey & Marking
5 14:30 18:00 3:30 Standby Dewatering
6 18:00 20:00 2:00 Install Steel Ribs 1 set STA 7279.750
7 20:00 21:00 1:00 Install Wiremesh 1 roll STA 7279.750
8 22:00 5:00 7:00 Safety Shotcrete 12 m³
9 5:00 7:00 2:00 Standby Dewatering
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7278.234 7279.75 1.516 3

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Rabu, 04 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 11:00 4:00 Standby Dewatering
2 11:30 13:30 2:00 Drilling Face (45 Hole, 3m Depth)
3 13:30 14:00 0:30 Charging and Blasting
4 14:00 14:10 0:10 Ventillating
5 14:10 16:30 2:20 Mucking Out (4 DT Howo)
6 16:30 17:00 0:30 Scalling & Cleaning
7 17:00 2:00 9:00 Standby Dewatering
8 2:30 3:00 0:30 Survey & Marking
9 4:00 6:00 2:00 Install Steel Ribs 1 set STA 7282.314
10 6:00 7:00 1:00 Install Wiremesh 1 roll STA 7282.314
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7279.75 7282.314 2.564 5.564

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream Jam : 07:00 - 07:00 WIB


Hari/Tanggal : Kamis, 05 Agustus 2021 Shift : Day & Night

Jam Kerja Waktu STA


No Uraian Pekerjaan Ket.
Mulai Selesai (Menit) AWAL AKHIR +EXCAVASI (m) TOTAL (m)
1 7:00 9:30 2:30 Install Forepoling 14 pcs STA 7282.314
2 10:00 12:00 2:00 Prepare Safety Shotcrete
3 15:00 0:00 9:00 Safety Shotcrete 12 m³
4 5:00 7:00 2:00 Grouting 7 m³ STA 7282.314
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material Type Jumlah Satuan
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1 Sigunit L-72 AF pcs
2 Asst Formen 1 2 Genset 250 Kva 1 2 Semen pcs
3 Operator 1 3 Compressor 750 CFM 2 3 Pasir Liter
4 Miner 9 4 Blower 110 1 4 Crushing Brush Sak
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5 Oxygen M3
6 SPV 1 6 Wheel Loader 1 6 Apart Pcs
7 Pelaksana /Surveyor 1 7 Sanchin 2 7 Mata Gerinda Tbg
8 8 Jack Hammer 4 8 Ring Baut 32 Bh
9 9 Breaker SH210 (07) 1 9 Sekop Pcs
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by Approved by

Satria Ronaldo
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Jum'at, 06 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 11:30 4:30 Continues Grouting 14 m³ STA 7282.314
2 12:00 2:30 14:30 Standby Dewatering
3 3:00 5:00 2:00 Drilling Face (45 Hole, 3m Depth)
4 5:00 5:20 0:20 Charging and Blasting
5 5:20 5:30 0:10 Ventillating
6 5:30 7:00 1:30 Mucking Out (4 DT Howo)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7282.314 7283.55 1.236 6.8

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Sabtu, 07 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 9:00 2:00 Scalling & Cleaning
2 10:30 11:00 0:30 Survey & Marking
3 12:00 14:00 2:00 Install Steel Ribs 1 set STA7285.500
4 14:00 15:00 1:00 Install Wiremesh 1 roll STA 7285.500
5 16:00 23:00 7:00 Safety Shotcrete 8 m³
6 23:30 2:30 3:00 Standby Dewatering
7 3:00 5:30 2:30 Drilling Face (45 Hole, 3m Depth)
8 5:30 5:55 0:25 Charging and Blasting
9 5:55 6:10 0:15 Ventillating
10 6:10 7:00 0:50 Mucking Out (4 DT Howo)
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7283.55 7285.5 1.95 8.75

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs
Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Down Stream


Hari/Tanggal : Minggu, 08 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 8:30 1:30 Continues Mucking Out (4 DT Howo)
2 8:30 9:30 1:00 Scalling & Cleaning
3 9:40 10:10 0:30 Survey & Marking
4 10:20 12:40 2:20 Drilling Face (45 Hole, 3m Depth)
5 12:40 13:10 0:30 Charging and Blasting
6 13:10 13:20 0:10 Ventillating
7 13:20 16:00 2:40 Mucking Out (4 DT Howo)
8 16:00 16:40 0:40 Scalling & Cleaning
9 17:00 18:30 1:30 Prepare Safety Shocrete
10 18:30 22:00 3:30 Safety Shotcrete 7 m³
11 22:30 7:00 8:30 Standby Dewatering
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

7285.5 7287.95 2.45 11.2

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs