Professional Documents
Culture Documents
What are the factors that What are the five When is the capacity bill
What are performance
capital projects are components of supply procedure most
targets focused around?
evaluated on? chain? appropriate?
Qualitative factors of
Order entry flow includes What are the final assembly
Average ROI formula modification of existing
what functions? schedule process steps?
structures
Elements of relationships
What are some risks of Logistics order entry flow
between customer and Common parts planning bill
doing a project? responsibilities
supplier
Work breakdown structure Product and service Customer order flow: make
The S&OP process provides:
(WBS) provides what? development stages to stock environment
In a make to stock
environment there are two What are the six
What are the five stages 3 main methods of dates associated with a considerations that should
that a team goes through? allocating overhead customer-requested item, be addressed in the S&OP
date, and quantity, what are process?
they?
Uncommitted resources of
What are the assumptions What are the 4 Rs of supply Resource planning process
all types method of
of the EOQ model? chain agility? flow:
customer order dating
What are the four primary What are the four basics
What are the four steps of Positions on the volume-
approaches to demand methods of resource
the MRP planning process? variety matrix
fulfillment? planning?
Principle of postponement
Demand management Percent of complete orders
Surge capacity (aka order penetration
outputs shipped on time formula
point)
Standardized market entry What are the elements of What are the two types of
Finite loading
strategy the pre-transaction phase? master schedule hedges?
What are some commonly
What are the elements of Constraints oriented finite
Blunder market strategy used measures of
the transaction phase? loading
efficiency?
Interns supply chain What are the elements of PAB formula after the Network planning
components the post transaction phase? demand time fence techniques
Competence - are the suppliers representatives
capable of doing their jobs and are the
knowledgeable? Creditability - can the supplier
Step 1: determine if the deviation was
Project evaluation and selection Project and it's representatives be believed? Courtesy -
Parts of the supply chain that organization significant Step 2: determine of the deviation
planning Project implementation Project does the supplier treat the customer
doesn't have control over was real Step 3: determine if the forecast is still
closeout professionally and with consideration?
valid
Understanding - does the suppliers
representative understand the customers
needs, expectations, and interests?
Length of the project to complete Newness of Closeness Trust Sharing success Long term
Groups all of the common components for a
the technology How accurate the costs and Multiple Points of communication Joint Consolidate shipments Communicate with
product or family of products into one bill of
savings are Operating costs Exchange risk learning Coordination Information Problem carriers Shipping documentation
material
Additional investment required solving Assets
Also referred to as cycle stock, this inventory is Customer requested delivery dates Standard
1) develop management forecasts 2)
maintained because it was not procured in the Contribution Margin / Sales (Variable cost per lead times Uncommitted inventory and
management review and approval 3) create the
exact amount needed. Average is generally 1/2 unit/sales revenue per unit) planned production Uncommitted resources of
initial S&OP grids
what is procured at one time all types
All customer requested delivery dates are
1) develop the preliminary supply plan 2)
accepted regardless of the work to be done.
Inventory that is maintained to compensate for perform resource planning 3) develop
Total fixed costs/contribution margin per unit This is a very risky approach as a next day
fluctuations in supply and demand inventory or backlog plans 4) create updated
delivery for a two week lead time item would
S&OP grids
be accepted for example
Strategic Objectives set financial targets Measure the firms ability to satisfy customers
Bucketless systems use daily planning
Financial objectives set MPR revenue forecasts requirements from inventory or planned
increments, and bucketed use planning Beginning inventory + forecast - production
Key functional plans become inputs to the production Should be an element for the
increments greater than one day
master planning of resource process balanced scorecard
Information technology can be used Employees Also called fill rate Can be calculated based on
Demand management, sales and operations (Actual production - planned production) /
can be cross trained The service design can be monetary units, orders, line items, or physical
planning, and master scheduling planned production
improved units Typically stated as a percentage
Capacity that is normally not used in a system Jobs instead of customer orders Committed
The relationship between lead time required by
of linked resources. From theory of constraints date to determine what was scheduled to be Visual review Two-bin Min-max Periodic review
the customer and the cumulative lead time for
perspective, idle capacity consists of protective shipped Committed date to indicate when Order point Distribution requirements planning
the product
and excess capacity service was to be provided
Activity network diagram Affinity diagram provides a measure of forecast bias. RSFE Production plan rules on: inventory, customer
Interrelationship diagram Matrix diagram indicates the tendency of a forecast to be service, resource utilization Current MPS
Prioritization matrix Process decision program consistently higher or lower than actual Forecasts, customer orders, inventory levels,
chart Tree diagram demand. and resource constraints
Create the MPS Calculate information for
Simple Functions Divisional Conglomerate 1) pre-transaction 2) transaction 3) post-
order-promising Create the final assembly
Hybrid or Matrix transaction
schedule
An organization enters the market with a new Backlog level Level of quality Delivery Infinite is better when meeting due dates is
Deviations happened in the past Changes are
product or process and exits when the product performance Stockout percentage Customer more important than high utilization of the
requested for the future
starts to develop stable growth support production facility