RCC Bridge Construction Estimate Kanchanpur

This document appears to be a variation order for a road construction project in Nepal. It provides details of the original cost estimate, completion date, contractor, and revised cost estimate and completion date after incorporating proposed changes via the variation order. Key figures like the original and revised cost estimates and completion dates are left blank, suggesting this is a template order to be filled in with project-specific amounts.

Uploaded by

Saroj Mahato
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
166 views27 pages

RCC Bridge Construction Estimate Kanchanpur

This document appears to be a variation order for a road construction project in Nepal. It provides details of the original cost estimate, completion date, contractor, and revised cost estimate and completion date after incorporating proposed changes via the variation order. Key figures like the original and revised cost estimates and completion dates are left blank, suggesting this is a template order to be filled in with project-specific amounts.

Uploaded by

Saroj Mahato
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd

Government of Nepal

Ministry of Physical Infrastructure & Transportation


Department of Roads
Federal Road Supervision and Monitoring Office
Road Division Mahendranagar
Variation No : 1
Project Name: Contract Effective Date : 2074/02/07
Financed by : [Link] Nepal Completion Date : 2078/03/29 #DIV/0! ZERO
Contract No. : New completion date after this Variation : 2078/09/27
Contractor : Increase or decrease in Estimate w.r.t original cost in Nrs -
Percentage increase or decrease in Estimate #DIV/0! #DIV/0!
Original Cost Estimate in NRs: - (Excluding VAT) Increase or decrease in Contract Amount and Revised Contract in Nrs -
Original Contract Amount in NRs : - (Excluding VAT) Percentage increase or decrease w.r.t Original Contract Amount: #DIV/0! #DIV/0!
Revised Cost Estimate(till date) in NRs : - (Excluding VAT) Budgetary Provision for Increased works (GoN/Foreign):Yes/No Yes(GoN)
Revised Contract Amount after this Va - (Excluding VAT)

Revised Cost Estimate(till date) in Revised Contract amount after this %age change
Original Cost Estimate in NRS % change Original Contract Amount in NRs : w.r.t
Item NRs : Variation in NRS
Description of work Unit in Qty wrt Original
No
Org Qty Contract
Rate Amount Quantity Rate Amount Qty Rate Amount Qty Rate Amount Amount
Quantity
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
1 Excavation cum ###
2 Brick work cum ###
3 Cement concrete(1:1.5:3) cum ###
4 Formwork sqm ###
5 Aluminum works sqm ###
Total of (1-5) 0.00 0.0 0.0 0.0 0.00%
VAT 13% - 0.0 0.0 0.0
Grand Total - 0.0 0.0 0.0
Government of Nepal
Ministry of Physical Infrastructure & Transport
Department of Roads
Federal Highway Supervision and Monitoring Office
Road Division, Kanchanpur
Detail Estimate Sheet
Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
1 GENERAL
Insurance for the damage and loss of works, plants and
1.1 vehicles; personal injury, death of labour, Employee &
third party insurance
1.00 1.00
Total 1.00 Job
1.2 Provision for Pile Load Testing
2.00 2.00
Total 2.00 No
1.3 Photography of Bridge construction activities.
1.00
Total 1.00 LS
Provide & Maintain Traffic safety control measures & Temporary
1.4 Diversion during construction period, [Link] directed by
Engineer.
1.00 1.00
Total 1.00 LS
Suply of Total Station with Tripod and Two Prisms and Rods all
1.5 Complelte as per Specified In the Special Provision.
1.00
Total 1.00 Job
Supply, Provide and Install of Compression testing Machine
1.6 2000KN Capacity With all Accessories electric com Hand
Operated at DRO Lab Mahendranagar, Kanchanpur.
1.00 1.00
Total 1.00 Job
2 FOUNDATION WORKS.
Site Clearance works including cutting bushes and removing it
2.1 up to 25 m. (before and after Completion of works) (201)
Right Bank 1.00 15.00 12.00 180.00
Left Bank 1.00 15.00 12.00 180.00
Total 360.00 m2
E/W in Excavation for Foundation for abutments and piers
2.2 through all type of soil. (905)
Right Bank Abutment 1.00 11.50 10.60 4.25 518.07 H=(3.5+5)/2
Left Bank Abutment 1.00 11.50 10.60 4.38 533.31 H=(3.75+5)/2

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
Total 1051.38 m3
Supplying and placing of 150mm of Dry Stone Layer Foundation
2.3 of Pile cap
Right Bank Abutment 1.00 11.50 10.60 0.15 18.28
Left Bank Abutment 1.00 11.50 10.60 0.15 18.28
Wing Wall 4.00 5.00 3.75 0.15 11.25
Bed of Approach Road 2.00 10.20 3.00 0.15 9.18
Right side Approach Masonry wall 1.00 125.00 1.25 0.15 23.43
Catch Pit 1.00 3.00 2.00 0.15 0.90
Total 81.32 m3
Backfilling in layers in foundation pits, trenches etc
2.4 including compaction and watering complete, lead 10 m.
[sp 900] (908)
2.00 44.20 1.79 2.00 315.41
Total 315.41 m3
Boring, providing and installing bored Cast-In-Situ RCC
2.5 Pile of specified diameter including Bentonite as per
specification and drawing etc. all complete.(1612)
Right Bank 16.00 18.00 288.000
Left Bank 16.00 18.00 288.000
Total 576.00 Rm
Providing and placing machine mixed Cement Concrete
M15/40 for levelling course etc. including compaction,
2.6
curing, testing and lead 30m. etc. all complete as per
specification and drawing. (2000)
Right Bank Abutment 1.00 11.50 10.60 0.15 18.28
Left Bank Abutment 1.00 11.50 10.60 0.15 18.28
Wing Wall 4.00 5.00 3.75 0.15 11.25
Stone Masonry
Right side Approach 1.00 125.00 1.25 0.10 15.62 Wall
Catch Pit 1.00 3.00 2.00 0.10 0.60 Stone Masonry
Total 55.60 m3
Providing and placing machine mixed Cement Concrete M25/20
for pile cap, pile etc. including compaction, curing, testing and
2.7 lead 30m. etc. all complete as per specification and drawing.
(2000)
Right Abutment Pile 16.00 18.00 area= 0.78 224.64
Left Abutment Pile 16.00 18.00 area= 0.78 224.64
Right Bank Abutment Pile Cap 1.00 11.50 10.60 2.00 243.80
Left Bank Abutment Pile Cap 1.00 11.50 10.60 2.00 243.80
Approach slab 2.00 3.00 10.20 0.30 18.36
Total 955.24 m3
Providing and laying Reinforcement including cutting, bending,
2.8 binding, fixing in position and lead 30m. etc. all complete as per
specification and drawing. (2000)
As per attached calculation sheet 79674.64
Total 79674.64 Kg
Providing , Preparing and Installing Form Work including
2.9 necessary supports and removing after completion for
Substructure. (1804,1805)
Right Bank Abutment Pile Cap 1.00 44.20 2.15 95.03 Including PCC
Left Bank Abutment Pile Cap 1.00 44.20 2.15 95.03 Including PCC
Approach Road 2.00 10.20 0.30 6.12
Total 196.18 m2

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
3 SUB-STRUCTURAL WORKS
Providing and placing machine mixed Cement Concrete M30/20
3.1 for the abutment stem, etc. including compaction, curing, testing
and lead 30m. (2000)
Abutment Stem 2.00 11.00 2.00 3.00 132.00
Back wall 2.00 11.00 0.45 3.50 34.65
Haunch 2.00 11.00 0.15 0.40 1.32 Rectangular
2.00 11.00 area= 0.02 0.49 Triangle
Return wall
Rectangular 4.00 3.00 1.95 0.40 9.36
Triangular 4.00 0.40 area= 4.50 7.20
Total 185.02 m3
Levelling course over abutments for bearing with M30/20
3.2 Concrete, and curing including supply of materials and haulage
distance up to 30m (SS-1800) (2000)
Bearing Pedestal 4.00 1.40 1.40 0.14 1.09
Total 1.09 m3
Providing and placing machine mixed Cement Concrete M30/20
3.3 for the abutment Cap, etc. including compaction, curing, testing
and lead 30m. (2000)
Concrete Pedestal 2.00 11.00 2.00 1.00 44.00
Total 44.00 m3
Providing and laying Reinforcement including cutting, bending,
3.4 binding, fixing in position and lead 30m. etc. all complete as per
specification and drawing. (2000)
As per attached calculation sheet 19228.52
Total 19228.52 Kg
Providing , Preparing and Installing Form Work including
3.5 necessary supports and removing after completion for
Substructure. (1804,1805)
Abutment Stem 2.00 26.00 3.00 156.00
Abutment Cap 2.00 26.00 1.00 52.00
Back wall 2.00 22.90 3.50 160.30
Return wall
Rectangular 4.00 6.40 1.95 49.92
Triangular 4.00 area= 10.24 40.96
Total 459.18 m2
Supplying and placing of 300mm of Dry Gravel Layar at rear of
3.6 the abutment.(2404,3110)

Total 0.00 m3
Formation of Embankment to structure by common materials
3.7 with compaction.{903(2)}

Total 0.00 m3
Supply & Laying of geo Textile behind of retaining structures
3.8 abutment walls,head walls of casue ways & pipe culvert etc all
complete (3110)(2404)

Total 0.00 m2
Providing, jointing and laying 100m dia HDP pipes as weep hole
3.9 in place as per specification (700) (701)
10.00 2.10 21.00
Total 21.00 Rm

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
4 SUPER-STRUCTURAL WORKS
Providing and placing machine mixed Cement Concrete M45/20
for the super structure, deckslab, girder etc. including
4.1 compaction, curing, testing and lead 30m. etc. all complete as
per specification and drawing.
1 @267.73 m3 per slab 267.73
Total 267.73 m3
M35 in precast RC footpath slabs , parapet posts and their bases
4.2 and road kerbs (2000)
1 @34.3 m3 per slab 34.3
Total 34.30 m3
reinforcement bars, HYSD, TMT, minimum 0.2% proof stress
4.3 500Mpa (Fe 500).(2000)
1.00 @38.82 MT per slab 38.82

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
Total 38.82 Mt
Prestressing multistandered cables each compairing 19 mono
strands, eac mono strands of 12.7 mm dia 7-ply low relaxation
class II HTS (braking Load per mono strand = 183.71 \KN),Total
4.4 length of 19 multistranded cables (weighting @14.73
kg/m)=616.6m (total length of 12.7mm dia. monostrand weighting
@0.77526 Kg/m=11716m)

Prestressing multistandered cables each compairing 19 mono strands 1.00 @9.1 MT per slab 9.10
Total 9.10 Mt
Sheathing (ducting for housing 19 multi stranded cables ),
4.5 corrugated HDPE , 90mm internal dia. (wall thickness 2.3±0.3mm
as manufactured and 1.5 mm after loss of compression)

1.00 @ 675 m per slab 675.00


Total 675.00 Rm
4.6 Anchorages for 19 - stranded multi stranded cables

Total 32.00 No.


Providing expansion joint sealing as per drawing and
4.7 specification all complete. (1901)
Total quantity of expansion joint 2.00 11.00 22.00
Total 22.00 Rm
Providing and installing Pot Bearing including all necessary
4.8 axillary and incidental works etc. all complete(SS-1900) (1902)
4.00 4.00
Total 4.00 Rm
Providing and spraying bituminious 'tack coat MC80/MC100
4.9 including cleaning the surface using wire,brushes, broom etc.
(1301,1302) @1.0ltr/m2
@ 0.6 lit/m2 1.00 40.00 7.50 300.00 Sq.m.
@ 0.6 lit/m2 180.00 Lit
Providing, mixing, laying and compaction of 40mm thick
4.10 premixed carpet. (1307, 1308)
1.00 40.00 7.50 0.04 12.00
Total 12.00 m3
4.11 75 mm dia GI pipe (parpet railing)
75mm Dia GI pipe 1 253 253
Total 253.00 Rm
4.12 Drainage spouts each 450mm long , 100mm dia, GI pipe
16 16
Total 16.00 No
Providing, preparing and installing Steel Forms for girder and
4.13 removing after completion.(SS-1800) (1804,1805)
Main Girder
End Portion (Bottom-Rectangular Portion) 4 2.9 6.184 71.73
End Portion (Middle-Trapezoidal Portion) 4 2.9 0.429 4.97
End Portion (Top-Rectangular Portion) 4 2.9 0.36 4.17
Tappered Portion (Bottom-Rectangular Portion) 4 2.5 1.31 13.10
Tappered Portion (Bottom-Tappered Portion) 4 2.5 0.342 3.42
Tappered Portion (Middle-Tappered Portion) 4 2.523 4.857 49.02
Tappered Portion (Top-Tappered Portion) 4 2.5 0.712 7.12
Tappered Portion (Top-Rectangular Portion) 4 2.5 0.36 3.60
Middle Portion (Bottom-Rectangular Portion) 2 30 1.31 78.60
Middle Portion (Bottom-Trapezoidal Portion) 2 30 0.684 41.04
Middle Portion (Middle-Rectangular Portion) 2 30 4.36 261.60
Middle Portion (Top-Trapezoidal Portion) 2 30 0.995 59.70
Middle Portion (Top-Rectangular Portion) 2 30 0.36 21.60
Total 619.66 m2
Providing , Preparing and Installing Wooden Forms for slab and
4.14 x-beam structure and removing after completion. (1804,1805)

Deck Slab Bottom 1 42.950 11.00 472.45


Dedn. For Main girder bottom 2 -40.800 1.25 -102
Deck slab (four sides) 1 102.00 0.25 25.5
Foot path & Kerb 2 81.20 0.30 48.72
Cross Girder
Intermediate Cross Girder (Rectengular Vertical Portion) 3.00 9.20 2.488 68.66

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
Intermediate Cross Girder (Top-Trapezoidal Portion) 3.00 9.80 0.100 2.94
Intermediate Cross Girder (Top-Rectangular Portion) 3.00 10.10 0.180 5.45
End Cross Girder (Bottom-Rectangular Portion) 2.00 9.20 3.127 57.53
End Cross Girder (Middle-Trapezoidal Portion) 2.00 9.80 0.043 0.84
End Cross Girder (Top-Trapezoidal Portion) 2.00 10.10 0.180 3.63
Railing Post 52.00 0.80 1.000 41.6
Total 625.32 m2
5 APPROACH ROAD WORKS
Site Clearance for cutting thin vegetations,grubbing their roots
5.1 and disposal 25m far away from the construction site.(SS-200)
(201)
Left Side Approach 65 8.33 541.67
Right Side Approach 40 8.2 328.00 m2
Total 869.67 m2

E/W in Excavation for Foundation for structures along


5.2
approach roads through all types of soil (905)
Upstream Left side approach
Bottom Layer 12.00 3.00 1.00 0.40 14.40
12.00 2.50 1.00 0.40 12.00
12.00 2.00 1.00 0.40 9.60
6.00 1.50 1.00 0.40 3.60
Upstream Right side approach
Bottom Layer 10.00 3.00 1.00 0.40 12.00
10.00 2.50 1.00 0.40 10.00
10.00 2.00 1.00 0.40 8.00
10.00 1.50 1.00 0.40 6.00
Downstream Left side approach
Bottom Layer 12.00 3.00 1.00 0.50 18.00
12.00 2.50 1.00 0.50 15.00
12.00 2.00 1.00 0.50 12.00
23.00 1.50 1.00 0.50 17.25
1.00 3.00 1.00 0.50 1.50
Downstream Right side approach
Bottom Layer 10.00 3.00 1.00 0.50 15.00
10.00 2.50 1.00 0.50 12.50
10.00 2.00 1.00 0.50 10.00
12.00 1.50 1.00 0.50 9.00 m3
Total 185.85 m3
Formation of Embankments including compaction in layers not
5.3 exceeding 150mm compacted depth,watering and haulage
10m etc all complete as per specification. (903(2))
Left Side Approach

Length Avg
Area (m2) Quantity (m3)
(m) Area(m2)

CH 0+000 0 43.46 0.00


CH 0+004 4 43.46 43.5 173.84
CH 0+017 13 59.89 51.7 671.77
CH 0+028 11 56.26 58.1 638.82
CH 0+039 11 38.65 47.5 522.00
CH 0+050 11 14.84 26.7 294.19
CH 0+070 20 0 7.4 148.40
Total 2449.02 m3

Backfilling in layers in foundation pits, trenches etc including


5.4
compaction and watering complete, lead 10 m.[sp 900] (908)

m3
Total 0.00 m3
Providing, laying, spreading, watering, levelling and
5.5 compaction of natural sand gravel subbase grading as per
table 12.1 of standard specification lead upto 10m.(1201)
Left Side Approach
CH 0+004 0.00 10.00 0.15 0.00
CH 0+017 13.00 10.00 0.15 19.50
CH 0+028 11.00 10.00 0.15 16.50

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
CH 0+039 11.00 7.50 0.15 12.37
CH 0+050 11.00 7.50 0.15 12.37
CH 0+070 20.00 7.50 0.10 15.00 m3
Right Side Approach
CH 0+004 0.00 10.00 0.15 0.00
CH 0+010 6.00 15.00 0.15 13.50
CH 0+016 6.00 15.00 0.15 13.50
CH 0+036 20.00 10.00 0.15 30.00
CH 0+065 29.00 7.50 0.15 32.62
CH 0+080 15.00 7.50 0.10 11.25
Approach Road towards Chinimill (Ch 0+000-0+070) 70.00 5.00 0.15 52.50
Approach Road towards Kalkatta (Postal highway)(Ch 0+000-0+050) 50.00 5.00
0.15 37.50
Total 266.61 m3

Supply and placing of heavy coated Gabion boxes/mattresses


with Selvege wire 7swg, Mesh Wire 10swg and selvadge wire
5.6 12swg Hexagonal Mesh size 100x120 mm, diaphragms
including rolling, cutting weaving & filling stones in the crate all
complete. (SS/SP-2400). 3*1*1M box (2401)

Upstream Left side approach


Bottom Layer 12.00 3.00 1.00 1.00 36.00
12.00 2.50 1.00 1.00 30.00
12.00 2.00 1.00 1.00 24.00
6.00 1.50 1.00 1.00 9.00
First Layer 12.00 2.50 1.00 1.00 30.00
12.00 2.00 1.00 1.00 24.00
12.00 1.50 1.00 1.00 18.00
2.00 3.00 1.00 1.00 6.00
Second Layer 14.00 2.00 1.00 1.00 28.00
15.00 1.50 1.00 1.00 22.50
2.00 3.00 1.00 1.00 6.00
Third Layer 15.00 1.50 1.00 1.00 22.50
5.00 3.00 1.00 1.00 15.00
Fourth Layer 7.00 3.00 1.00 1.00 21.00
Fifth Layer 4.00 3.00 1.00 1.00 12.00
1.00 1.50 1.00 1.00 1.50
Extra for packing 7.00 2.00 1.00 1.00 14.00
2.00 1.50 1.00 1.00 3.00

Upstream Right side approach


Bottom Layer 10.00 3.00 1.00 1.00 30.00
10.00 2.50 1.00 1.00 25.00
10.00 2.00 1.00 1.00 20.00
10.00 1.50 1.00 1.00 15.00
First Layer 10.00 2.50 1.00 1.00 25.00
10.00 2.00 1.00 1.00 20.00
10.00 1.50 1.00 1.00 15.00
3.00 3.00 1.00 1.00 9.00
Second Layer 10.00 2.00 1.00 1.00 20.00
10.00 1.50 1.00 1.00 15.00
5.00 3.00 1.00 1.00 15.00
Third Layer 10.00 1.50 1.00 1.00 15.00
3.00 3.00 1.00 1.00 9.00
3.00 2.00 1.00 1.00 6.00
Fourth Layer 5.00 3.00 1.00 1.00 15.00
Fifth Layer 4.00 3.00 1.00 1.00 12.00
Extra for packing 2.00 2.00 1.00 1.00 4.00
1.00 1.50 1.00 1.00 1.50

Downstream Left side approach


Bottom Layer 12.00 3.00 1.00 1.00 36.00
12.00 2.50 1.00 1.00 30.00
12.00 2.00 1.00 1.00 24.00
23.00 1.50 1.00 1.00 34.50
1.00 3.00 1.00 1.00 3.00
First Layer 12.00 2.50 1.00 1.00 30.00

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
12.00 2.00 1.00 1.00 24.00
23.00 1.50 1.00 1.00 34.50
5.00 3.00 1.00 1.00 15.00
Second Layer 12.00 2.00 1.00 1.00 24.00
11.00 1.50 1.00 1.00 16.50
2.00 1.50 1.00 1.00 3.00
1.00 2.00 1.00 1.00 2.00
8.00 3.00 1.00 1.00 24.00
Third Layer 12.00 1.50 1.00 1.00 18.00
9.00 3.00 1.00 1.00 27.00
Fourth Layer 9.00 3.00 1.00 1.00 27.00
Fifth Layer 3.00 3.00 1.00 1.00 9.00
1.00 2.50 1.00 1.00 2.50
1.00 2.00 1.00 1.00 2.00
Extra for packing 7.00 2.00 1.00 1.00 14.00
2.00 1.50 1.00 1.00 3.00

Downstream Right side approach


Bottom Layer 10.00 3.00 1.00 1.00 30.00
10.00 2.50 1.00 1.00 25.00
10.00 2.00 1.00 1.00 20.00
12.00 1.50 1.00 1.00 18.00
First Layer 10.00 2.50 1.00 1.00 25.00
10.00 2.00 1.00 1.00 20.00
11.00 1.50 1.00 1.00 16.50
3.00 3.00 1.00 1.00 9.00
Second Layer 10.00 2.00 1.00 1.00 20.00
11.00 1.50 1.00 1.00 16.50
3.00 3.00 1.00 1.00 9.00
Third Layer 10.00 1.50 1.00 1.00 15.00
4.00 3.00 1.00 1.00 12.00
Fourth Layer 6.00 3.00 1.00 1.00 18.00
Fifth Layer 4.00 3.00 1.00 1.00 12.00
1.00 1.50 1.00 1.00 1.50
2.00 3.00 1.00 0.50 3.00
Extra for packing 1.00 2.00 1.00 1.00 2.00
9.00 1.50 1.00 1.00 13.50
Total 1218.85 m3
Supply &Laying of geo Geo Textile behind of retaining
5.7 structures abutment walls,head walls of casue ways & pipe
culvert etc all complete (3110) (2404)
Upstream Left side
Bottom Layer 1.00 42.00 1.00 42.00
First Layer 1.00 42.00 1.00 42.00
Second Layer 1.00 35.00 1.00 35.00
Third Layer 1.00 30.00 1.00 30.00
Fourth Layer 1.00 21.00 1.00 21.00
Fifth Layer 1.00 13.50 1.00 13.50
Extra for packing 1.00 8.50 1.00 8.50

Upstream Right side approach


Bottom Layer 1.00 40.00 1.00 40.00
First Layer 1.00 39.00 1.00 39.00
Second Layer 1.00 35.00 1.00 35.00
Third Layer 1.00 25.00 1.00 25.00
Fourth Layer 1.00 15.00 1.00 15.00
Fifth Layer 1.00 12.00 1.00 12.00
Extra for packing 1.00 5.50 1.00 5.50

Downstream Left side approach


Bottom Layer 1.00 62.00 1.00 62.00
First Layer 1.00 62.00 1.00 62.00
Second Layer 1.00 52.00 1.00 52.00
Third Layer 1.00 39.00 1.00 39.00
Fourth Layer 1.00 27.00 1.00 27.00
Fifth Layer 1.00 13.50 1.00 13.50

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
Extra for packing 1.00 10.00 1.00 10.00

Downstream Right side approach


Bottom Layer 1.00 42.00 1.00 42.00
First Layer 1.00 40.00 1.00 40.00
Second Layer 1.00 35.00 1.00 35.00
Third Layer 1.00 22.00 1.00 22.00
Fourth Layer 1.00 18.00 1.00 18.00
Fifth Layer 1.00 13.50 1.00 13.50
Top Layer 2.00 6.00 0.50 6.00
Extra for packing 1.00 3.00 4.00 12.00
Total 817.50 m2

6 RIVER TRAINING AND PREOTECTION WORKS


6.1 E/W Excavation for foundation through all types of soil (905)
B=(4.8+2.8)/2
Wing Wall 4.00 5.00 3.80 4.31 327.75 H=(4.25+4.375)/2
Upstream Right Bank Protection 1.00 33.00 2.00 1.00 66.00 Gabion Foundation
Upstream Right Bank Protection 1.00 12.00 3.00 1.00 36.00 Gabion Foundation
Upstream Left Bank Protection 1.00 14.00 3.00 1.00 42.00 Gabion Foundation
Stone Masonry
Right side Approach 1.00 150.00 2.35 0.60 211.50 Wall
Catch Pit 1.00 3.00 2.00 1.00 6.00 Stone Masonry
Total 689.25 m3
Backfilling in layers in foundation pits, trenches etc including
6.2 compaction and watering complete, lead 10 m.[sp 900] (908)
Right Bank Protection 1 30 1.3 3 117.00
Right Bank Protection 1 12 1.7 3 61.20
Left Bank 1 10 1.75 3 52.50
Right side Approach 1 150.00 0.25 0.5 18.75 Stone Masonry
Total 249.45 m3
Formation of Embankments including compaction in layers not
6.3 exceeding 150mm compacted depth,watering and haulage 10m
etc all complete as per specification. (903(2))

Length Avg
Right side Approach
(m)
Area (m2)
Area(m2)
Quantity (m3)

CH 0+000 1 43.46
CH 0+004 1 4 43.46 43.5 173.84
CH 0+010 1 6 12.7 28.1 168.48
CH 0+016 1 6 22.35 17.5 105.15
CH 0+036 1 20 40.5 31.4 628.50
CH 0+065 1 29 34 37.3 1080.25
CH 0+080 15 35 34.5 517.50
CH 0+000 1 15.25
Approach Road
CH 0+020 1 4 15.25 15.3 61.00 towards Chinimil
CH 0+070 1 7 0 7.6 53.37
CH 0+000 1 18.58 Approach Road
CH 0+020 1 20 16.33 17.5 349.10 towards Kalkatta
(Hulaki Rajmarg)
CH 0+050 1 30 0 8.2 244.95
Total 3382.14 m3
Supply and placing of heavy coated Gabion boxes/mattresses
with Selvege wire 7swg, Mesh Wire 10swg and selvadge wire
6.4 12swg Hexagonal Mesh size 100x120 mm, diaphragms including
rolling, cutting weaving & filling stones in the crate all complete.
(SS/SP-2400). 3*1*1M box (2401)
Upstream right Bank Protection
Bottom Layer 33.00 2.00 1.00 1.00 66.00
First Layer 32.00 2.00 1.00 1.00 64.00
Second Layer 31.00 1.50 1.00 1.00 46.50
Top Layer 10.00 3.00 1.00 1.00 30.00
Upstream Left Bank Protection
Bottom Layer 37.00 2.00 1.00 1.00 74.00
First Layer 37.00 2.00 1.00 1.00 74.00
Second Layer 36.00 1.50 1.00 1.00 54.00
Top Layer 36.00 1.00 1.00 1.00 36.00 m3
Sub Total 386.71
Upstream right Bank Protection

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
Bottom Layer 12.00 3.00 1.00 1.00 36.00
First Layer 12.00 2.00 1.00 1.00 24.00
Second Layer 13.00 1.50 1.00 1.00 19.50
Top Layer 4.00 3.00 1.00 1.00 12.00
Upstream Left Bank Protection
Bottom Layer 14.00 3.00 1.00 1.00 42.00
First Layer 14.00 2.00 1.00 1.00 28.00
Second Layer 14.00 1.50 1.00 1.00 21.00
Top Layer 7.00 1.50 1.00 1.00 10.50
Down stream Left Bank Protection
Bottom Layer 13.00 2.00 1.00 1.00 26.00
First Layer 13.00 2.00 1.00 1.00 26.00
Second Layer 13.00 1.50 1.00 1.00 19.50
Top Layer 12.00 1.00 1.00 1.00 12.00
Down stream Right Bank Protection
Bottom Layer 8.00 2.00 1.00 1.00 16.00
First Layer 8.00 2.00 1.00 1.00 16.00
Second Layer 7.00 1.50 1.00 1.00 10.50
Top Layer 6.00 1.00 1.00 1.00 6.00
Right side Approach d/s 10.00 2.00 1.00 1.00 20.00
10.00 1.50 1.00 1.00 15.00
3.00 3.00 1.00 1.00 9.00
Lest side Approach d/s 40.00 2.00 1.00 1.00 80.00
40.00 2.00 1.00 1.00 80.00
40.00 1.50 1.00 1.00 60.00
13.00 3.00 1.00 1.00 39.00
Sub Total 618.35 m3
Total 1005.06 m3
Supply and placing of heavy coated Gabion boxes/mattresses
with Selvege wire 7swg, Mesh Wire 10swg and selvadge wire
6.5 12swg Hexagonal Mesh size 100x120 mm, diaphragms including
rolling, cutting weaving & filling stones in the crate all complete.
(SS/SP-2400).(2401)
Upstream Right Bank
Launching 12.00 3.00 1.00 0.50 18.00
Upstream Left Bank
Launching 14.00 3.00 1.00 0.50 21.00
Upstream Right Bank
Launching 33.00 3.00 1.00 0.50 49.50
Upstream Left Bank
Launching 37.00 3.00 1.00 0.50 55.50
Down stream Left Bank Protection
Launching 13.00 3.00 1.00 0.50 19.50
Down stream Right Bank Protection
Launching 8.00 3.00 1.00 0.50 12.00
Total 140.59 m3
Supply &Laying of geo Geo Textile behind of retaining structures
6.6 abutment walls,head walls of casue ways & pipe culvert etc all
complete (3110) (2404)
Upstream Left Bank Protection 1.00 43.00 3.00 129.00
Upstream Right Bank Protection 1.00 13.00 3.00 39.00
Down stream Left Bank Protection 1.00 13.00 2.50 32.50 m2
Total 200.50 m2
Providing and laying Random rubble masonry in cement mortatr
including scaffolding, curing, preparation of mortar etc.
6.7 complete, masoned height 0-5m, lead 30m (manual mixing)
mortar 35%(cement sand) 1:4. (2607) for wing wall B=(4.7+2.8)/2
B=((4.5+3.6)/
Wing Wall Base 4.00 2+(2.5+1.6)/2)/2
5.00 3.75 2.00 150.00
Wing Wall Left Bank Upstream 4.00 5.00 3.05 2.20 134.20 RCC PORTION

US Left side 1.00 5.25 2.58 0.50 6.75 SLOPE PORTION

1.00 5.50 1.20 0.60 3.96


DS Left 1.00 5.03 2.25 1.20 13.56
DS Right 1.00 5.25 1.03 1.75 9.41
Stone Masonry
Right side Approach 1.00 125.00 0.88 2.50 275.00 Wall

Prepared By: Checked By: Recommended By: Approaved By:


Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur

Length Breadth Height


S.N. Description of Works No. Quantity Unit Remarks
(m) (m) (m)
Catch Pit 1.00 8.00 0.60 1.00 4.80 Stone Masonry
Total 597.68 0.00
Grass sodding works including sod cutting , transporting ,
6.8 placing in position and water sprinkling.(1201)
Total 0.00 m2
7 MISCELLANEOUS WORKS
Providing & Installation of reflectorized Bridge Sign Board of
7.1 size 1.5mX0.75m with steel stands including all reinforcement
works & formwork complete.(SS-1500)(1501)
2.00 2.00 No
Total 2.00 No
supplying and applying paint application in two coats in addition
7.2 two one prime coat etc all complete.(1502)
Parapet Posts 64.00 Area= 0.80 51.20 m2
Footpath Kerb 2.00 Area= 8.18 16.36
Total 67.56 m2
Supplying and fixing in place R.C.C. delineator and guard post
7.3 including excavation, back filling, painting and erection etc. all
complete as per drawing.(1504)
30.00 30.00 No
Total 30.00 No

8 New Item
Providing and Laying Reinforced cement concrete NP3 Flush
jointed pipe for culverts including fixing with cement mortar 1:2
8.1 as per Drawing and Techinical Specifications. 900mm internal
dia
37.50 37.50 Rm
Total 37.50 Rm

Prepared By: Checked By: Recommended By: Approaved By:


13/27
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur
Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura

Item No. Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per
2.8 specification and drawing. (2000)
BAR BENDING SCHEDULE OF PILES AT ABUTMENT (PER WALL)
Unit wt.
S.N Sketch Bar mark Dia. (mm) Nos Length (m) Weight Unit Remarks
Kg/m

0.94

1 19.925 PL1 25 20 20.86 3.80 1585.36

2 0.85 0.15 PL2 10 120 2.81 0.62 209.06

For 1 no of Pile 1794.424 Kg


FOR 16 NO. OF PILE PER ABUTMENT 28710.780 Kg
BAR BENDING SCHEDULE OF PILES CAP AT ABUTMENT (PER WALL)
0.50 10.45
0.50
1 APC1 20.00 78.00 11.45 2.46 2197.02

0.5 10.45
2 0.5 APC2 25.00 78.00 11.45 3.80 3393.78

0.5 11.35 0.5


3 APC3 20.00 72.00 12.35 2.46 2187.43

4 0.5 11.35 0.5 APC4 20.00 72.00 12.35 2.46 2187.43

0.075

1.85 APC5 12.00 506.00 2.00 0.88 890.56


0.075
10.45

5 11.35 APC6 16.00 4.00 43.60 1.55 270.32

For 1 Pile Cap 11126.54 Kg


TOTAL REINFORCEMENT IN PILE AND PILE CAP PER ABUTMENT 39837.32
TOTAL REINFORCEMENT IN PILE FOR 2 ABUTMENT TILL DATE 79674.64 Kg
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur
Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Item No. Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per
3.4 specification and drawing. (2000)
Unit wt.
S.N SHAPE LABEL Dia. (mm) Nos Length (m) Weight Unit Remarks
Kg/m
BAR BENDING SCHEDULE OF ABUTMENT WALL (PER WALL)
0.3

1 5.6 A1 32.00 37.00 6.50 6.31 1517.56


0.6

2 4.27 A' 32.00 37.00 4.87 6.31 1137.00

0.6

0.3

3 5.60 A2 25.00 74.00 6.50 3.80 1827.80

0.6

1.87

4 0.87 A3 16.00 74.00 5.48 1.55 628.56

10.87
5 0.4 A4 16.00 27.00 11.67 1.55 488.39

0.4 10.87
6 A5 16.00 27.00 11.67 1.55 488.39

10.87
7 0.4 A6 20.00 27.00 11.67 2.46 775.12

0.06

8 4.42 A7 16.00 74.00 4.54 1.55 520.74

0.06

0.06

9 4.42 A8 16.00 74.00 5.28 1.55 605.62

0.8

0.1 10.92
10 A9 12.00 30.00 11.12 0.88 293.57

14 of 27
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur
Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Item No. Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per
3.4 specification and drawing. (2000)
Unit wt.
S.N SHAPE LABEL Dia. (mm) Nos Length (m) Weight Unit Remarks
Kg/m

0.22
0.4
11 A10 10.00 20.00 1.02 0.62 12.65 For 2 wall

1.42

12 4.53 A11 12.00 6.00 5.95 0.88 31.42 For 2 wall

1.87

13 0.06 A12 16.00 220.00 1.99 1.55 678.59

14 4.42 A13 12.00 2.00 4.42 0.88 7.78


2.92

A13 12.00 24.00 2.92 0.88 61.67

3.72

15 1.99 A14 12.00 20.00 3.72 0.88 65.47 for 2 wall

A14 12.00 40.00 1.99 0.88 70.05

0.32
0.75
0.5
16 A15 12.00 24.00 1.57 0.88

3.5
17 A16 12.00 24.00 3.50 0.88 73.92

15 of 27
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur
Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Item No. Providing and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per
3.4 specification and drawing. (2000)
Unit wt.
S.N SHAPE LABEL Dia. (mm) Nos Length (m) Weight Unit Remarks
Kg/m

0.2 1.67
0.6
18 A17 16.00 24.00 2.47 1.55 91.88

0.2 1.22
19 A18 16.00 24.00 2.22 1.55 82.58
0.8

For 1 abutment stem 9458.76 Kg


Sub-Total for 2 abutment stem 18917.52 Kg
BAR BENDING SCHEDULE OF ABUTMENT STOPPER (PER STOPPER)

0.5
1 ST1 16.00 8.00 2.10 1.55 26.04
1.3
0.3

0.5

2 1.685 ST2 16.00 8.00 2.485 1.55 30.81

0.3

0.06
3 1.4 ST3 8.00 11.00 3.800 0.38 15.88
0.5
0.3

0.06
4 1.4 ST4 8.00 1.00 3.712 0.38 1.41
0.456

0.06
5 1.4 ST5 8.00 1.00 3.370 0.38 1.28
0.285

0.06
6 1.4 ST6 8.00 1.00 3.154 0.38 1.20
0.177

0.06
7 1.4 A6 8.00 1.00 2.970 0.38 1.13
0.085

For 1 Stopper 77.75 Kg


Sub-Total for 4 Stopper 311.00 Kg
Total 19228.52 kg

16 of 27
Project Name: Construction of RCC Bridge over Sutiya Nadi near Chinimill on Belauri Na Pa 13, Kanchanpur
Contract No. : DROMNR/3371574/073/74-092
Contractor : M/S Rajendra Nirman Sewa, Dadeldhura
Item [Link] and laying Reinforcement including cutting, bending, binding, fixing in position and lead 30m. etc. all complete as per specification and
3.4 drawing. (2000)
S.N SHAPE LABEL Dia. (mm) Nos Length (m) Unit wt. Kg/m Weight Unit Remarks

BAR BENDING SCHEDULE OF BEAM AND SLAB


10.90
0.1
1 1601 16.00 153.00 11.100 1.55 2632.37

4.25

2 0.1 2002 20.00 306.00 4.350 2.46 3274.51

7.08
3 1603 16.00 152.00 7.080 1.55 1668.05

40.32
4 1004 10.00 74.00 40.320 0.61 1820.04

11.71
5 1005 10.00 38.00 11.710 0.61 271.44

40.32
6 1006 10.00 69.00 40.320 0.61 1697.07

7 4.10
.8
0.6

7 -0
7-

0 .6
0.8

7 1607 16.00 159.00 6.179 1.55 1522.81


7

0.30

87 4.10
0.
0.6

7-
7-

0 .6
0.8

8 2008 20.00 158.00 6.180 2.46 2402.04


7

0.30

0.10 2.52
0.6
7-
0.8

9 1209 12.00 320.00 3.650 0.87 1016.16


7

0.30

2.70

0.30
10 2010 20.00 70.00 3.000 2.46 516.60
0.30
1.54
11 1611 16.00 70.00 2.140 1.55 232.19
0.30

10.92

12 1212 12.00 17.00 10.920 0.87 161.51

40.67

13 1016 10.00 12.00 40.670 0.61 297.70

0.175

14 .475 0.125 1017 10.00 554.00 1.420 0.61 479.87


.325

0.05 0.125 0.135


0.175

15 0.53 1024 10.00 553.00 1.605 0.61 541.41


.365

.275

40.67
16 1025 10.00 12.00 40.670 0.61 297.70

40.52
17 1026 10.00 12.00 40.520 0.61 296.61

2.22
1. 1

18 1227 12.00 108.00 4.160 0.87 390.87


6

0.78

7.56
19 1228 12.00 108.00 7.560 0.87 710.34

21.30
20 1029 10.00 60.00 21.300 0.61 779.58

0.65

21 2.7 2030 20.00 72.00 4.250 2.46 752.76


0.25
0.65
0.61-0.40
0.65
0.61-0.40

2.62-2.47

22 0.035-0.215 0.65 2031 20.00 25.00 4.324 2.46 265.93


0.61-0.40
0.25 0.25

0.65

0.35
2.45

23 0.25 2032 20.00 236.00 4.200 2.46 2438.35

0.25 0.25
0.65

0.20
2.35

24 0.375 1633 16.00 180.00 4.075 1.58 1158.93

0.25 0.25
0.65

6.35
25 2034 20.00 8.00 6.350 2.46 124.97

6.35
26 2035 20.00 8.00 6.350 2.46 124.97

0.1
27 2036 20.00 16.00 4.990 2.46 196.41
3.
32

1.57

0.1

28 3. 2 2037 20.00 16.00 4.890 2.46 192.47


7
1.57

10.92
29 2038 20.00 8.00 10.920 2.46 214.91

10.92
30 2039 20.00 8.00 10.920 2.46 214.91
10.72-7.84
31 1040 10.00 48.00 8.750 0.61 256.20

0.30
2.60

32 1641 16.00 70.00 6.100 1.55 661.85

0.30
0.32-2.44

33 1642 16.00 60.00 2.280 1.55 212.04

5.75
34 2043 20.00 9.00 5.750 2.46 127.31

5.75
35 2044 20.00 9.00 5.750 2.46 127.31

0.1

36 2045 20.00 18.00 4.940 2.46 218.74


3. 5
4
1.30

0.1

37 3. 2046 20.00 18.00 4.900 2.46 216.97


50

1.30

10.92
38 2047 20.00 9.00 10.920 2.46 241.77

10.92
39 2048 20.00 9.00 10.920 2.46 241.77

6.31-10.70
40 1049 10.00 72.00 8.350 0.61 366.73
0.20

2.60
41 1650 16.00 75.00 5.800 1.58 687.30

0.30-2.60 0.30

42 1651 16.00 84.00 3.500 1.55 455.70

0.65

43 2.90 2052 20.00 68.00 3.550 2.46 593.84

0.61-0.40

2.62-2.47

44 0.035-0.215 2053 20.00 28.00 3.470 2.46 239.01

0.30
0.35

2.45
45 2054 20.00 236.00 3.425 2.46 1988.42
0.375

0.25

0.20
2.35

46 1655 16.00 180.00 3.175 1.55 885.83


0.375

0.25

47 MESH TYPE 1A 12.00 4.00 24.246 0.87 84.38

48 MESH TYPE 1B 12.00 4.00 5.398 0.87 18.79

49 MESH TYPE 2A 12.00 4.00 25.611 0.87 89.13


50 MESH TYPE 2B 12.00 4.00 7.548 0.87 26.27
51 MESH TYPE C 10.00 4.00 11.774 0.87 40.97
52 SPIRAL REINFORCEMENT (9 TURNS EACH) 16.00 32.00 7.100 1.55 352.16
Total Quantity till date 34825.97 KG
Sub Total 34.83 MT

For Footpath

0.05 1.20
1 1018 10.00 870.00 1.300 0.61 689.91

0.05 1.20
2 1019 10.00 386.00 1.300 0.61 306.10

0.05 1.20
3 820 8.00 364.00 1.300 0.39 184.55

0.05 3.73
4 621 6.00 298.00 3.830 0.22 251.09

3.73

5 0.05 622 6.00 298.00 3.830 0.22 251.09

1.20

6 623 6.00 848.00 1.300 0.22 242.53


Sub total 1.93 MT

For Railing
0.10

1 1613 16.00 128.00 1.720 1.55 341.25


1.47
0.15

0.10

2 1614 16.00 128.00 1.720 1.55 341.25


1.47
0.15

0.11
0.11

15 615 6.00 256.00 0.550 0.22 30.98

Sub total 0.71 MT


Approach Road

1 0.15 3.4 AS1 12 50 3.70 0.87 160.95

0.15 3.4 AS2 12 50 3.70 0.87 160.95

0.15 7.4 AS3 12 24 7.70 0.87 160.78

7.4
0.15 AS4 12 24 7.70 0.87 160.78

Sub total 0.64 MT


For Both sides 1.29 MT
Grand Total 38.75 MT
g]kfn ;/sf/
ef}lts k"jf{wf/ tuyf oftfoft dGqfno
;8s ljefu
;+l3o ;8s ;'kl/j]If0f tyf cg'udg sfof{no
;8s l8lehg dx]Gb|gu/
e]l/Pzg cfb]z ;DaGwL ljj/0f
l;=g+= ljifo ljj/0f
1 of]hgf ÷ sfof{nosf] gfd M ;8s l8lehg dx]Gb|gu/
DROMNR/3371574/073/74-092; Construction of
2 7]Ssf g+= / gfd M RCC Bridge over Sutiya Nadi near Chinimill on
Belauri Na Pa 13, Kanchanpur
3 l8hfOg sG;N6]G6 k|fljlwssf] gfd M BDA-GSLP-CEC J/V, Lalitpur
4 ;'k/lehg sG;N6]G6 k|fljlwssf] gfd M gePsf]
5 7]Ssf sfo{sf] k|s[tL / d'Vo sfo{x? M k'n lgdf{0f sfo{
6 z'? nfut cg'dfg c+s -Eof6 sG6]Gh]G;L afx]s_ M Err:509
e]l/Pzg kZrft sfod x'g] nfut cg'dfg c+s -Eof6 afx]s_
7 Err:509
M
8 nfut cg'dfg 3l6 jf a9L k|ltzt M Err:509
9 z'? ;Demf}tf c+s -Eof6 sG6]Gh]G;L afx]s_ M Err:509
10 e]l/Pzg kZrft sfod x'g] /sd -Eof6 afx]s_ M Err:509
11 7]Ssf c+s 3l6 jf a9L k|ltzt M Err:509
उक्त पुलको Right Side तर्फ को Approach Road बाट थप दुइ तर्फ
Branch Road हरु पर्ने र उक्त Branch Road हरुको
Embankment Formation, Retaining Structure को
Quantity शुरुको BoQ मा नरहेकोले Embankment,
12
e]l/Pzg ug'{ kgf{sf] sf/0f -d'Vo yk36 ePsf] ljj/0f_ Subbase, RRM wall र Gabion Wall को Quantity बढ्न
M गएको; Right Side तर्फ को Approach Road र Branch
Road को लागि Embankment Formation गरिसके पछि सडक
छेउमा रहेका घर टहराहरुमा ponding हुने र शुरुको BoQ मा
Drainage को लागि आइटम नरहेकोले Hume Pipe को नयां थप हुन
गएको ।
13 e]l/Pzgn] 7]Ssf cjlw a9\g\ jf ga9\g] M gj9\g] .
14 e]l/Pzgdf gofF cfO6d ePsf] jf gePsf] M ePsf] .
15 e]l/Pzgdf gofF b//]6 ePsf] jf gePsf] M ePsf] .
lgdf{0f sfo{sf] Drawing, Design tyf Specification abNg'
16 gkg]{ .
kg]{ jf gkg]{ M
abNg' kg]{ ePdf lgdf{0f sfo{sf] cfwf/e't k|s[lt jf If]q
17 gx'g] .
kl/jt{g x'g] gx'g] M
e]l/Pzgsf] sf/0f x'g] nfut cg'dfgsf] ;+zf]wg z'? nfut
18 gk/]sf] .
cg'dfgsf] @% k|ltzt eGbf a9L km/s k/] jf gk/]sf] M
z'?df c:jfefljs nfut cg'dfg tof/ u/]sf] sf/0fn] vl/b
19 gx'g] .
sfo{ k|efljt x'g] jf gx'g] M
20 :jLs[t ah]6 tyf sfo{qmddf k/] jf gk/]sf] M k/]sf]
21 e]l/Pzgsf] k|fljlws k'i6\ofO{ eP jf gePsf] M ePsf] .
22 e]l/Pzg kmd]{6 eP jf gePsf] M ePsf] .
Rate Negotiation

A meeting held in Road Division Mahendranagar on 22nd September 2021 for Rate Negotiation concluded follwing rates for more than
BoQ quantity of following items of Contract No: DROMNR/3371574/073/74-092; Construction of RCC Bridge over Sutiya Nadi near
Chinimill on Belauri Na Pa 13, Kanchanpur :
Original Contract wrt
Item Engineer's Estimate Engineer's Estimate Negotiated Rate
Description of Item Unit
No (NRs.) (21.94% below) (NRs.)
(NRs.)
Contract No. :
2.6 Err:509 Cu.m. Err:509 Err:509 8000.00
### Err:509 Cu.m. Err:509 Err:509 3400.00
### Err:509 Cu.m. Err:509 Err:509 3400.00
### Err:509 Cu.m. Err:509 Err:509 6250.00
New Item

### Err:509 Err:509 Err:509 11500.00


Err:509

Recommended By: Approved By:


(Roshan Prasad Bhatt) (Laxman Datt Joshi) (Narendra Prasad Bhatt)
Contractor Engineer Act. Division Chief
M/S Rajendra Nirman Sewa, Dadeldhura Road Division Mahendranagar
Government of Nepal
Ministry of Physical Infrastructure and Transport
Department of Roads
Division Road Office, Mahendranagar, Kanchanpur

Major Quantities for Variation


Project Name:
Contract No. :

Quantity
Item No. Description of Works Reason for Quantity Change Remarks
Varied in %
Quantity of Dry Soling increased due to
Supplying and placing of 150mm of Dry Stone Layer for
Err:509
Foundation
Err:509 increase in RRM Wall on Approach and
Branch Road

Quantity of PCC increased due to increase in


Err:509 Err:509 Err:509
RRM Wall on Approach and Branch Road

Quantityof subbase for Branch Roads was


Err:509 Err:509 Err:509
not included in Original BoQ
Insufficient quantity of Gabion work in
Err:509 Err:509 Err:509
Original BoQ as per Site Condition
Quantityof embankment for Branch Roads
Err:509 Err:509 Err:509
was not included in Original BoQ
Insufficient quantity of Gabion work in
Err:509 Err:509 Err:509
Original BoQ as per Site Condition
Quantity of RRM Retaining for Branch
Err:509 Err:509 Err:509
Roads was not included in Original BoQ
Fabrication of hexagonal mesh type 100mm*120mm gabion
New
boxes/Item
mattresses with diapharagms, with binding wire 12 swg,
mesh wire 10 swg and selveged wire 8 swg, including rolling,
cutting and weaving; assembling gabion boxes mattresses, placing Item for Drainage Storm water and waste
Err:509 in position including stretching, forming compartments;tying with water from Chinimill was missing in Original
brcing wires and tie wires; tying down the lid complete; and BoQ
providing and filling stone/boulder in gabion boxes/mattresses etc.
including dressing, bending, bonding and all transportation as per
specification.

Prepared By:- Checked By:- Approved By:-


सार्वजनिक खरिद ऐन, २०६३ को दफा ५४ र सार्वजनिक खरिद नियमावली, २०६४ को नियम ११८ बमोजिम
गठित समितिको मिति २०७७/०६/०६ मा बसेको बैठकले DDROMNR/3371574/073/74-092 को भेरियसन
आदेश पेश गर्ने निर्णय गरियो ।

उपस्थिति
१. का.मु.डिभिजन प्रमुख श्री नरेन्द्र प्रसाद भट्ट

२. लेखा अधिकृ त श्री सनत कु मार जोशी


३. ईन्जिनियर श्री लक्ष्मण दत्त जोशी
४. सव ईन्जिनियर श्री नरेश प्रसाद भट्ट
५. सव ईन्जिनियर श्री सरस्वती बडाल

निर्णय
ठे क्का नं. DROMNR/3371574/073/74-092 को Construction of RCC Bridge over Sutiya Nadi near
Chinimill on Belauri Na Pa 13, Kanchanpur कार्यको लागि निर्माण व्यवसायी श्री थेगिम/गल्वा जे.भी. ले
मिति २०७४/०२/०७ मा सम्झौता गरि कार्य भईरहेकोमा तपसिल उल्लेखित विविध कारणहरुले गर्दा पेश हुन
आएको ४.५४ प्रतिशत बढीको भेरिएसन स्वीकृ तको लागि सिफारिस गर्ने निर्णय गरियो ।

उक्त पुलको
भेरियसन Right
हुनुका Side तर्फ को Approach Road बाट थप दुइ तर्फ Branch Road हरु पर्ने र उक्त Branch
कारणहरु
Road हरुको Embankment Formation, Retaining Structure को Quantity शुरुको BoQ मा नरहेकोले
Embankment, Subbase, RRM wall र Gabion Wall को Quantity बढ्न गएको; Right Side तर्फ को
Approach Road र Branch Road को लागि Embankment Formation गरिसके पछि सडक छेउमा रहेका घर
टहराहरुमा ponding हुने र शुरुको BoQ मा Drainage को लागि आइटम नरहेकोले Hume Pipe को नयां थप हुन
गएको ।