3) SR omnibus reason ......poor coal quality....

some more detailing like other stations such as GCV for


which designed; GCV of supplied coal.....we could write to CEA separately on this aspect with copy
to MOP. Also I recollect Yermaras is designed for 25% blended coal but KPCL was not importing
and in one of the meetings they said they would start importing. This was in Sep 23 or so. What is
the situation now?

Sl Gen Station Designed Indegineous Imported Remarks


GCV Coal GCV coal
kcal/kg kcal/kg Expected
(getting)
1 RTPS U1 & U2 4300 3300 4000MT Second week of Jan 2024
2 RTPS U3 to U7 3500 3300 4000MT Second week of Jan 2024
3 RTPS U8 4500 3300 4000MT Second week of Jan 2024
4 Bellary 4500 3300 12000MT Second week of Jan 2024
5 YTPS U1 4700 3300 20000MT Second week of Jan 2024
&U2(800MW)
6 VTPS U1- 3686 2600 NiL No imported Coal purchase order
U6(210MW)
7 VTPS 4400 3600 Nil No imported Coal purchase order
U7(500MW)
8 VTPS 4800 3600 Nil No imported Coal purchase order
U8(800MW)
9 RYTPS U1-U5 3686 2600 Nil No imported Coal purchase order
(210MW)
10 RYTPS 4400 3600 Nil No imported Coal purchase order
U6(500MW)
11 Krishnapatnam 4800 3600 100000MT PO placed on Adani on Feb 2023 for
U1-U3(800MW) 7.5lacs and being used in blending
ratio of 70(ing):30(Imp).supplied
6.5lac and 1lac yet to be received.
12 Bhadradri U1- 4375 3206 Nil No Imported coal as of now.
U4(270MW)

Note: 1) KPCL placed order for imported coal on 22-11-2023 expected tentative delivery on 20-12-
2023 for total quantum of 36000MT through Smart Gen Infra Pvt Ltd, Hyderabad for all their KPCL
generators Sl.No 1-5.But On 05-12-2023 release order issued for 2.5Lacs MT and expected delivery
on second week of Jan 2024.

Indigenous coal supply currently from Mahanadi, Singereni and KEMTA whose GCV is 3300kcal/kg.

4) Kudgi……Actually it appears Ancillary down of 450MW has gone during evening peak;should we
show it as partial outage?

Ancillary down was given during peak hours. Hence , the reason for less generation is written as
“Generated as per schedule”. However, reason should not be shown in partial outage as due to “
TRAS or SCED DOWN”.