Professional Documents
Culture Documents
period t and scenario s. have increased the complexities in balancing load with
𝑢𝑢𝑔𝑔𝑔𝑔 : Unit commitment status for generator g (0 down, generation and have introduced new challenges in regards to
1 online), which is obtained from the day-ahead maintaining system reliability. As a result, more flexible
solution. resources are needed to meet the increasingly stringent
𝑈𝑈𝑈𝑈𝑔𝑔 : Minimum up time for unit g. ramping requirements in the system.
𝛼𝛼𝑏𝑏𝑅𝑅 : Minimum duration of time (hour) that the Driven by the need to integrate higher penetration levels of
regulation reserves have to be maintained. renewable energy and to reduce the costs for serving peak
𝛼𝛼𝑏𝑏𝑆𝑆 : Minimum duration of time (hour) that the demands, recent interests have been focused on energy storage
spinning reserves have to be maintained. technologies. Energy storage can shift energy from peak-
𝜂𝜂𝑏𝑏𝐼𝐼𝐼𝐼 : Efficiency associated with the absorbing cycle for demand hours to off-peak-demand hours, or absorb excess
energy storage b. renewable energy to provide it back to the grid when desired.
The fast-ramping capability also makes energy storage a
𝜂𝜂𝑏𝑏𝑂𝑂𝑂𝑂𝑂𝑂 : Efficiency associated with the generating cycle
competitive resource to compensate for the variability and
for energy storage b.
uncertainty in renewable energy. By using energy storage, the
𝜋𝜋𝑠𝑠 : Probability for scenario s.
cycling of thermal units can be reduced, which is an advantage
Decision Variables (Index s Denotes Scenario and Index t since many thermal units are not designed to be ramped up
Denotes Time Period) and down frequently [1].
𝐸𝐸𝑏𝑏𝑏𝑏𝑏𝑏 : State of charge for energy storage b. Among all existing storage technologies, there is
𝑃𝑃𝑔𝑔𝑔𝑔𝑔𝑔 : Power output for generator g. substantial interest in batteries as an emerging solution to
𝐼𝐼𝐼𝐼 manage intermittent renewable resources. Compared with
𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 : Power absorbed by energy storage b.
𝑂𝑂𝑂𝑂𝑂𝑂 thermal units, batteries do not have a no-load cost and they are
𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 : Power generated by energy storage b.
generally considered to not have minimum power input/output
𝑃𝑃𝑘𝑘𝑘𝑘𝑘𝑘 : Real power flow on transmission line k. levels for charging/discharging. Compared to other storage
𝑆𝑆
𝑟𝑟𝑔𝑔𝑔𝑔𝑔𝑔 : Spinning reserve provided by generator g. technologies, such as pumped storage hydro and compressed
𝑅𝑅+
𝑟𝑟𝑔𝑔𝑔𝑔𝑔𝑔 : Up regulation reserve provided by generator g. air energy storage, batteries have higher power density. Even
𝑅𝑅−
𝑟𝑟𝑔𝑔𝑔𝑔𝑔𝑔 : Down regulation reserve provided by generator g. though the main barrier with battery technologies is their high
𝑁𝑁𝑁𝑁
𝑟𝑟𝑔𝑔𝑔𝑔𝑔𝑔 : Non-spinning reserve provided by generator g. capital costs, efforts are being made to reduce the capital costs
𝐿𝐿
𝑠𝑠𝑛𝑛𝑛𝑛𝑛𝑛 : Involuntary load shedding at node n. and improve the cost-effectiveness of different battery
𝐿𝐿𝐿𝐿𝐿𝐿 solutions [2].
𝑠𝑠𝑏𝑏,𝑡𝑡 : Slack variable to relax the lower bound of the
flexible operating range for energy storage b. Due to growing interests in energy storage, recent literature
𝑅𝑅+
𝑠𝑠𝑠𝑠𝑠𝑠 : Slack variable to relax system up regulation analyzes the scheduling problem of energy storage and the
requirement. different applications of energy storage in systems with
𝑅𝑅−
𝑠𝑠𝑠𝑠𝑠𝑠 : Slack variable to relax system down regulation increased renewable resources [3]-[8]. The application of
requirement n. battery storage is studied at both the transmission and
𝑆𝑆𝑆𝑆
𝑠𝑠𝑠𝑠𝑠𝑠 : Slack variable to relax system spinning reserve distribution system levels. In [9] and [10], the authors studied
requirement. the benefits of batteries in transmission systems with
𝑂𝑂𝑂𝑂 renewable resources using security-constrained unit
𝑠𝑠𝑠𝑠𝑠𝑠 : Slack variable to relax system operating reserve
commitment (UC) models. In [11] and [12], the application of
requirement.
𝑈𝑈𝑈𝑈 battery storage at the distribution level is studied. In [11], the
𝑠𝑠𝑏𝑏,𝑡𝑡 : Slack variable to relax the upper bound of the benefits of using battery storage in microgrids with renewable
flexible operating range for energy storage b. resources are evaluated using a three-step short-term
𝑊𝑊
𝑠𝑠𝑤𝑤𝑤𝑤𝑤𝑤 : Wind curtailment for wind farm w. generation scheduling approach. In [12], a unit commitment
𝑢𝑢𝑔𝑔𝑔𝑔𝑔𝑔 : Binary unit commitment variable for generator g model is formulated to study the problem of battery optimal
(0 down, 1 online). sizing in a microgrid system.
𝑣𝑣𝑔𝑔𝑔𝑔𝑔𝑔 : Startup variable for generator g (1 for startup, 0 While the study of battery storage in systems with
otherwise). renewable resources is not new, much of the previous work is
𝑤𝑤𝑔𝑔𝑔𝑔𝑔𝑔 : Shutdown variable for generator g (1 for based on day-ahead models or short-term look-ahead
shutdown, 0 otherwise). scheduling models [9]-[12]. In such look-ahead scheduling
𝑧𝑧𝑏𝑏𝑏𝑏𝑏𝑏 : Binary variable for energy storage b (1 for problems, scheduling for future time periods are optimized
production, 0 for consumption). together in one model based on forecast information.
+
𝜃𝜃𝑘𝑘𝑘𝑘𝑘𝑘 : Bus angle for the “from” bus of transmission line However, with a look-ahead type of scheduling model, the
k. challenges associated with managing the state of charge
−
𝜃𝜃𝑘𝑘𝑘𝑘𝑘𝑘 : Bus angle for the “to” bus of transmission line k. (SOC) of the battery are not properly captured. Different from
thermal units, the dispatch of energy storage is constrained by
I. INTRODUCTION their SOC. In real-time operation, as look-ahead functionality
is limited, decisions for time period t have to be made in
ITH increasing concerns about climate change and the
W need for a more sustainable grid, power systems have
seen a fast expansion of renewable resources in recent
advance without having perfect information about future
uncertainties. An inappropriate decision made for battery
storage in the current time period could potentially result in
years. The variability and uncertainty of renewable resources insufficient capacity to charge or discharge in future time
3
periods. These challenges are not adequately captured in as the post-stage analysis. The formulation used in the two-
independent day-ahead or short-term look-ahead scheduling step framework is described in the following subsections.
models.
A. Day-Ahead Scheduling and Stochastic Unit Commitment
In this paper, we study battery storage under the
assumption that it is a system asset operated by the system The stochastic UC is formulated as a mixed integer linear
operator. We propose a two-step modeling framework to study program (MILP) based on the formulation in [13] . In [13], the
the benefit and the operation of battery storage in transmission scheduling horizon is divided into several time blocks. Within
systems with renewable generation. The main contributions of each time block, wind scenarios are grouped into different
the paper are as follows. Firstly, we propose a flexible “buckets” based on their average wind forecast value. The
operational strategy for the use of energy storage in real-time non-anticipativity constraints are then enforced for scenarios
operations. The proposed approach is developed to utilize the that are in the same bucket in each time block. The advantage
flexibility of battery storage across multiple time periods, of this formulation is that it can provide a more flexible
given the limited look-ahead functionality and future schedule for the thermal generators as the commitment
uncertainty in real-time operation. Secondly, we extend the schedule is dependent on each bucket rather than being the
work in [13] to include energy storage. While the primary same for all the scenarios in the stochastic UC. It should be
motivation for [13] is to propose an improved stochastic noted that the day-ahead UC model is still solved for the full
formulation to enhance the flexibility of the commitment 24-hour time horizon. The introduction of time blocks is
schedule for thermal generators, we extend the formulation in primarily to introduce flexibility in the solution by allowing
[13] and take the advantage of its structure to develop the commitment decisions for thermal units to vary between
proposed battery operational scheme in this paper. Thirdly, we buckets and time blocks, as a function of the wind power
illustrate the benefits of the proposed algorithms in a case level.
study of the IEEE RTS system using realistic wind power The complete formulation of the stochastic UC with energy
uncertainty data. storage is presented in (1) - (29), where the objective (1) is to
This paper is different from previous studies as follows. minimize the system total costs and the costs of security
While stochastic UC models have been used to study battery violations (e.g., the cost of involuntary load shedding and
storage and other forms of energy storage in [9]-[12], [14]- violations of the reserve requirements). In the formulation,
[17], the studies in [9]-[12], [14]-[17] are conducted using constraint (2) guarantees the power balance at every bus.
day-ahead or short-term look-ahead scheduling models. None Constraint (3) represents the dc power flow on each line and
of [9]-[12], [14]-[17] addresses the challenges associated with (4) is the line-flow limit constraint. Limits on the power output
the real-time operation of energy storage. In [18]-[20], for each generator are presented in (5) and (6). The non-
different methodologies are used to improve the operational anticipativity constraints are shown in (7), where e is the index
scheme of the battery in real-time operation. However, the for buckets. In constraint (7), 𝑒𝑒 = 𝛽𝛽(𝑠𝑠, 𝑡𝑡) indicates that
studies in [18]-[20] are conducted from the viewpoint of the scenario s is assigned to bucket e in time period t. Note that
storage owner, whose objective is to maximize his/her own the non-anticipativity constraints are only modeled for the
profit. In this paper, the study is conducted from the viewpoint slow units and enforced for each individual bucket, i.e. not
of a system operator, whose objective is to optimally allocate across all the scenarios. The minimum up and down time
the resources in the system and minimize the total cost of the constraints are shown in (8)-(10). Constraints (11)-(14)
system. In [21], an energy restoration mechanism is proposed represent the ramp rates for regulation, spinning and non-
to maintain the SOC of energy storage at their preferred levels. spinning reserves for thermal units. In this paper, regulation
The approach in [21] is proposed to manage the SOC of reserve refers to the reserve that is used to follow the
energy storage when energy storage is used to provide automatic generation control (AGC) signal. For spinning and
regulation reserve. However, in this paper, the proposed non-spinning reserves, they are modeled to represent
approach is to improve the overall operational scheme of contingency reserve, which is used to respond to contingencies
battery storage in real-time operation, rather than focusing on in the system. The hourly ramp rate constraints are shown in
any one type of ancillary services provided by the battery. (15) and (16). The model for battery is shown in (17)-(24).
The remainder of the paper is organized as follows. In Constraints (17)-(20) represent the limits on regulation and
Section II, the mathematical model and the methodology are spinning reserves provided by batteries. Constraints (18) and
described. The results are reported and discussed in Section (20) indicate that a battery should be able to maintain its
III. The conclusion and future work are presented in Section output for duration of 𝛼𝛼𝑏𝑏𝑆𝑆 and 𝛼𝛼𝑏𝑏𝑅𝑅 hours to be qualified to
IV. provide spinning and regulation reserves respectively.
Constraint (21) is the power balance constraint for energy
II. MATHEMATICAL MODEL AND METHODOLOGY storage. Regulation reserve variables are included in (21) to
estimate the change in SOC as a result of the deployment of
A two-step framework is implemented to evaluate the
the regulation reserves. We ignore the impact of the wind
benefits of battery storage in transmission systems with
penetration level on the requirement for regulation reserves,
renewable generation. In the first-step, which is referred to as
and assume that 20% of the scheduled regulation reserve
the day-ahead scheduling, a two-stage stochastic day-ahead
capacity will be activated regardless of the wind penetration
unit commitment model is formulated. In the second-step,
levels studied. The limits on consumption and production for
stochastic simulation is performed to test the day-ahead
the battery are presented in (22) and (23). Constraint (24)
solution against wind scenarios that are not included in the
represents the energy capacity for the battery. The constraints
day-ahead stochastic UC. The second-step is later referred to
4
𝑃𝑃𝑔𝑔,𝑠𝑠,𝑡𝑡 − 𝑃𝑃𝑔𝑔,𝑠𝑠,𝑡𝑡−1 ≤ 𝑅𝑅𝑔𝑔60+ 𝑢𝑢𝑔𝑔,𝑠𝑠,𝑡𝑡−1 + 𝑅𝑅𝑔𝑔𝑆𝑆𝑆𝑆 𝑣𝑣𝑔𝑔𝑔𝑔𝑔𝑔 , ∀𝑔𝑔, 𝑡𝑡, 𝑠𝑠 (15) Minimize:
′
𝑡𝑡 +𝑖𝑖 ′
+𝑖𝑖 𝑣𝑣𝑣𝑣 𝐿𝐿
𝑃𝑃𝑔𝑔,𝑠𝑠,𝑡𝑡−1 − 𝑃𝑃𝑔𝑔,𝑠𝑠,𝑡𝑡 ≤ 𝑅𝑅𝑔𝑔60− 𝑢𝑢𝑔𝑔𝑔𝑔𝑔𝑔 + 𝑅𝑅𝑔𝑔𝑆𝑆𝑆𝑆 𝑤𝑤𝑔𝑔𝑔𝑔𝑔𝑔 , ∀𝑔𝑔, 𝑡𝑡, 𝑠𝑠 (16) ∑𝑔𝑔 ∑𝑡𝑡=𝑡𝑡′ �𝐶𝐶𝑔𝑔 �𝑃𝑃𝑔𝑔𝑔𝑔 � + 𝑐𝑐𝑔𝑔𝑁𝑁𝑁𝑁 𝑢𝑢𝑔𝑔𝑔𝑔 + 𝑐𝑐𝑔𝑔𝑆𝑆𝑆𝑆 𝑣𝑣𝑔𝑔𝑔𝑔 � + ∑𝑛𝑛 ∑𝑡𝑡𝑡𝑡=𝑡𝑡′ 𝑐𝑐 𝑠𝑠𝑛𝑛𝑛𝑛 +
′
𝑡𝑡 +𝑖𝑖 𝑣𝑣𝑣𝑣+ 𝑅𝑅+ 𝑣𝑣𝑣𝑣− 𝑅𝑅− 𝑣𝑣𝑣𝑣𝑣𝑣 𝑆𝑆𝑆𝑆 𝑣𝑣𝑣𝑣𝑣𝑣 𝑂𝑂𝑂𝑂
∑𝑡𝑡=𝑡𝑡′�𝑐𝑐 𝑠𝑠𝑡𝑡 + 𝑐𝑐 𝑠𝑠𝑡𝑡 + 𝑐𝑐 𝑠𝑠𝑡𝑡 + 𝑐𝑐 𝑠𝑠𝑡𝑡 � (30)
𝑆𝑆
𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏 𝑅𝑅+
+ 𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏 ≤ 𝑃𝑃𝑏𝑏𝑂𝑂𝑂𝑂𝑂𝑂_𝑚𝑚𝑚𝑚𝑚𝑚 − 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏
𝑂𝑂𝑂𝑂𝑂𝑂 𝐼𝐼𝐼𝐼
+ 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 , ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (17)
Subject to:
𝛼𝛼𝑏𝑏𝑆𝑆 𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏
𝑆𝑆
+ 𝛼𝛼𝑏𝑏𝑅𝑅 𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏
𝑅𝑅+
≤ 𝜂𝜂𝑏𝑏𝑂𝑂𝑂𝑂𝑂𝑂 (𝐸𝐸𝑏𝑏𝑏𝑏𝑏𝑏 − 𝐸𝐸𝑏𝑏𝑀𝑀𝑀𝑀𝑀𝑀 ), ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (18)
𝑢𝑢𝑔𝑔𝑔𝑔 = 𝑢𝑢𝑔𝑔𝑔𝑔 , ∀𝑔𝑔 ∈ Ω𝐺𝐺𝐺𝐺 , 𝑡𝑡 ∈ {𝑡𝑡 ′ , … , 𝑡𝑡 ′ + 𝑖𝑖} (31)
𝑅𝑅−
𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏 ≤ 𝑃𝑃𝑏𝑏𝐼𝐼𝐼𝐼_𝑚𝑚𝑚𝑚𝑚𝑚 − 𝐼𝐼𝐼𝐼
𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 + 𝑂𝑂𝑂𝑂𝑂𝑂
𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 , ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (19)
Constraints (2)-(6), (11)-(29) , 𝑡𝑡 ∈ {𝑡𝑡 ′ , … , 𝑡𝑡 ′ + 𝑖𝑖} (32)
𝛼𝛼𝑏𝑏𝑅𝑅 𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏
𝑅𝑅−
≤ (𝐸𝐸𝑏𝑏𝑀𝑀𝑀𝑀𝑀𝑀 − 𝐸𝐸𝑏𝑏𝑏𝑏𝑏𝑏 )/𝜂𝜂𝑏𝑏𝐼𝐼𝐼𝐼 , ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (20) 𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊 𝑊𝑊𝑊𝑊𝑊𝑊𝑊𝑊
𝑃𝑃𝑤𝑤𝑤𝑤 = 𝑃𝑃𝑤𝑤,𝑡𝑡−1 , ∀𝑤𝑤, 𝑡𝑡 ∈ {𝑡𝑡 ′ ′
+ 1, … , 𝑡𝑡 + 𝑖𝑖} (33)
𝐼𝐼𝐼𝐼 𝐼𝐼𝐼𝐼 𝑂𝑂𝑂𝑂𝑂𝑂
𝐸𝐸𝑏𝑏𝑏𝑏𝑏𝑏 = 𝐸𝐸𝑏𝑏,𝑠𝑠,𝑡𝑡−1 + 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 𝜂𝜂𝑏𝑏 − 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 ⁄𝜂𝜂𝑏𝑏𝑂𝑂𝑂𝑂𝑂𝑂 + 0.2𝛼𝛼𝑏𝑏𝑅𝑅 (𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏
𝑅𝑅− 𝐼𝐼𝐼𝐼
𝜂𝜂𝑏𝑏 −
𝑅𝑅+ 𝑂𝑂𝑂𝑂𝑂𝑂
𝑟𝑟𝑏𝑏𝑏𝑏𝑏𝑏 /𝜂𝜂𝑏𝑏 ), ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (21) C. Battery Operation with a Fixed Operating Schedule
To address the limited look-ahead functionality in real-time
𝑂𝑂𝑂𝑂𝑂𝑂
0 ≤ 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 ≤ 𝑃𝑃𝑏𝑏𝑂𝑂𝑂𝑂𝑂𝑂_𝑚𝑚𝑚𝑚𝑚𝑚 𝑧𝑧𝑏𝑏𝑏𝑏𝑏𝑏 , ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (22) operation, one approach is to use the solution obtained through
a look-ahead scheduling stage. However, as the SOC is a
𝐼𝐼𝐼𝐼
0 ≤ 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 ≤ 𝑃𝑃𝑏𝑏𝐼𝐼𝐼𝐼_𝑚𝑚𝑚𝑚𝑚𝑚 (1 − 𝑧𝑧𝑏𝑏𝑏𝑏𝑏𝑏 ), ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (23)
second-stage decision in the day-ahead stochastic UC, one
𝐸𝐸𝑀𝑀𝑀𝑀𝑀𝑀
𝑏𝑏 ≤ 𝐸𝐸𝑏𝑏𝑏𝑏𝑏𝑏 ≤ 𝐸𝐸𝑀𝑀𝑀𝑀𝑀𝑀
𝑏𝑏 , ∀𝑏𝑏, 𝑡𝑡, 𝑠𝑠 (24) battery schedule is obtained for each scenario. Therefore, in
5
𝐿𝐿𝐿𝐿𝐿𝐿
the post-stage analysis, for each wind scenario to be tested, the 𝐸𝐸𝑏𝑏,𝑡𝑡 = 𝑚𝑚𝑚𝑚𝑚𝑚 {𝐸𝐸𝑠𝑠̅0,𝑡𝑡 , 𝐸𝐸𝑠𝑠̅1,𝑡𝑡 , … , 𝐸𝐸𝑠𝑠̅𝑚𝑚,𝑡𝑡 }, ∀𝑏𝑏, 𝑡𝑡 (35)
most appropriate battery schedule should be selected from the
𝐿𝐿𝐿𝐿𝐿𝐿 𝐿𝐿𝐿𝐿𝐿𝐿 𝑈𝑈𝑈𝑈 𝑈𝑈𝑈𝑈
day-ahead solution. In this paper, the battery schedule is 𝐸𝐸𝑏𝑏,𝑡𝑡 − 𝑠𝑠𝑏𝑏,𝑡𝑡 ≤ 𝐸𝐸𝑏𝑏,𝑡𝑡 ≤ 𝐸𝐸𝑏𝑏,𝑡𝑡 + 𝑠𝑠𝑏𝑏,𝑡𝑡 , ∀𝑏𝑏, 𝑡𝑡 (36)
selected based on the similarity between the post-stage wind 𝐿𝐿𝐿𝐿𝐿𝐿 𝑈𝑈𝑈𝑈
scenario and the day-ahead wind scenario. The similarity where 𝐸𝐸𝑏𝑏,𝑡𝑡 and 𝐸𝐸𝑏𝑏,𝑡𝑡 are the lower and upper bound for the
between the two wind scenarios is measured by the Euclidean flexible operating range in time period t for the battery. The
distance. Therefore, for each post-stage wind scenario, 𝑠𝑠, the flexible operating range is formulated as a pair of limits on
𝐿𝐿𝐿𝐿𝐿𝐿 𝑈𝑈𝑈𝑈
day-ahead wind scenario 𝑠𝑠̅0 that is closest to it is identified. SOC. Variables 𝑠𝑠𝑏𝑏,𝑡𝑡 and 𝑠𝑠𝑏𝑏,𝑡𝑡 are slack variables used to relax
Then the battery schedule that corresponds to scenario 𝑠𝑠̅0 is the flexible operating range when necessary by incurring a
used in the post-stage scenario 𝑠𝑠. Denote this battery schedule penalty cost. The penalty cost is computed as
as 𝑬𝑬𝒔𝒔�𝟎𝟎 , where 𝑬𝑬𝒔𝒔�𝟎𝟎 is a vector with each element representing a 𝐿𝐿𝐿𝐿𝐿𝐿 𝐿𝐿𝐿𝐿𝐿𝐿 𝑂𝑂𝑂𝑂𝑂𝑂 𝑈𝑈𝑈𝑈 𝑈𝑈𝑈𝑈
target SOC in each time period. ∑𝑏𝑏 ∑𝑡𝑡(𝑐𝑐𝑏𝑏𝑏𝑏 𝑠𝑠𝑏𝑏𝑏𝑏 𝜂𝜂𝑏𝑏 + 𝑐𝑐𝑏𝑏𝑏𝑏 𝑠𝑠𝑏𝑏𝑏𝑏 /𝜂𝜂𝑏𝑏𝐼𝐼𝐼𝐼 ). (37)
For each post-stage scenario, the corresponding battery For the proposed flexible operating range approach, the
schedule has to be determined before the first time period is penalty cost term shown in (37) is added to the objective
solved. To reflect the fact that wind generation cannot be function of the hourly-dispatch problem (30). In this paper,
perfectly forecasted while not over-complicating the 𝐿𝐿𝐿𝐿𝐿𝐿 𝑈𝑈𝑈𝑈
𝑐𝑐𝑏𝑏𝑏𝑏 and 𝑐𝑐𝑏𝑏𝑏𝑏 are both assumed to be the highest marginal
simulation process, the wind generation profiles in the first six costs of all the online slow units. The reason for using such a
hours of each post-stage scenario are used to determine the penalty price is that constraint (36) should be relaxed if it can
closest day-ahead wind scenario. The underlying assumption avoid the commitment of an additional fast unit, which
is that the wind forecast for the first six hours has relatively typically happens when all the slow units are fully dispatched.
low forecast errors and can be used as an acceptable As turning on an additional fast unit will incur not only
approximation to determine which day-ahead schedule should marginal fuel cost but also no-load cost and start-up cost, the
be used. The battery schedule obtained using the above commitment of an additional fast unit is expected to be more
method is later referred to as the “fixed schedule” and will be expensive than using the energy stored in the battery. The
used as a benchmark approach to be compared with our procedure to implement the proposed approach in the post-
proposed method. stage analysis is summarized in Fig. 1.
D. Battery Operation with a Flexible Operating Range E. Renewable Scenario Generation
Next, we propose an approach that aims at flexibly Wind power forecasts are affected by several sources of
operating battery storage in real-time operation while taking uncertainty that include data and physics modeling. In this
into account future uncertainties. Two goals are to be achieved study the wind scenarios account for the errors in the
by using the proposed method. First, the approach should be numerical weather predictions (NWP) and are generated using
able to provide instructions to the battery of when to charge, Gaussian process (GP) regression [23]. The GP is built to
discharge, and provide reserves, so that the battery will have estimate the differences between a state-of-the-art NWP
enough capability in current as well as future time periods. forecasts, WRF v3.6 [24], and observations (corresponding to
Second, the proposed method should provide enough room for NOAA Surfrad network). The NWP forecasts are initialized
adjustment in real-time operation, such that the fast-ramping using North American Regional Reanalysis fields. Simulations
capability of the battery can be utilized when renewable are started every day during August 2012 and cover the
generation deviates away from its planned production. The continental U.S. on a grid of 25x25 Km. A GP is calibrated to
proposed method is referred to as the flexible operating range reproduce the discrepancy between forecasts and observations
approach, and constitutes an improvement to the fixed- at 10m height (mean and variance). Samples from this
schedule approach. In the proposed method, an operating distribution are extrapolated from 10m to 100m hub height
range is determined for the battery in each time period. The and passed through a standard power curve to obtain the wind
fundamental idea of the proposed method is to use the day- scenarios for representative locations [25]. In the paper, only
ahead UC solution to generate an operating range around the wind generation is considered. Other renewable resources,
fixed schedule for the battery in real-time operation. The such as solar generation, are not considered in the study, but
detailed procedure for determining the flexible operating range could also be represented in the model.
is described as follows.
Firstly, obtain a fixed schedule for the battery for each F. Experimental Setup
post-stage scenario s using the procedure described in the Firstly, wind scenarios are generated based on the approach
previous subsection. This is done prior to the beginning of the outlined above. The scenario reduction approach in [26] is
simulation for each post-stage scenario. Denote this fixed applied to select a predetermined number of scenarios to be
schedule as 𝑬𝑬𝒔𝒔�𝟎𝟎 . Secondly, prior to solving the hourly-dispatch used in the day-ahead UC. Secondly, the stochastic UC is
problem for each time period, find the day-ahead scenarios solved with the reduced scenario set. The day-ahead solution
that are in the same bucket as the post-stage scenario s and is then tested against wind scenarios that are not included in
denote the corresponding day-ahead battery schedules as the day-ahead UC (i.e. out-of-sample) in the post-stage
𝑬𝑬𝒔𝒔�𝟏𝟏 , … , 𝑬𝑬𝒔𝒔�𝒎𝒎 . Then the upper and lower limit of the flexible analysis. In the post-stage, the scenarios have equal
operating range are determined as probabilities. Lastly, the performance of the proposed flexible
𝑈𝑈𝑈𝑈
operating range approach is compared with other benchmark
𝐸𝐸𝑏𝑏,𝑡𝑡 = 𝑚𝑚𝑚𝑚𝑚𝑚 {𝐸𝐸𝑠𝑠̅0,𝑡𝑡 , 𝐸𝐸𝑠𝑠̅1,𝑡𝑡 , … , 𝐸𝐸𝑠𝑠̅𝑚𝑚,𝑡𝑡 } , ∀𝑏𝑏, 𝑡𝑡 (34) methods.
6
TABLE II. EXPECTED SYSTEM RESULTS FOR DAY-AHEAD UNIT COMMITMENT without battery storage. This result indicates the variations of
the total system costs are also lower for the cases with battery
ETCH ETCH
Involuntary storage than those of the cases without battery storage if not
Wind Reserve for for
Wind Load considering the outliers (the red “+”). Though not shown, an
Curtailment Violations Slow Fast
% Shedding
(MWh) (MWh) Units Units ANOVA test was also conducted to confirm that the expected
(MWh)
(h) (h) costs are significantly different between the two cases with
With Battery
15% 0.0 4 0.0 297 144
and without battery storage.
20% 0.0 99 0.4 282 140
TABLE IV. EXPECTED SYSTEM RESULTS FOR POST-STAGE ANALYSIS
25% 0.0 221 0.2 271 137
30% 0.0 1036 0.1 278 135
ETCH ETCH
No Battery Involuntary
Wind Reserve for for
15% 0.0 5 0.3 369 144 Wind Load
Curtailment Violations Slow Fast
20% 0.0 56 5.4 345 147 % Shedding
(MWh) (MWh) Units Units
25% 0.0 468 4.1 331 147 (MWh)
(h) (h)
30% 0.0 1460 2.9 311 146 With Battery
15% 0.0 0 4.0 297 145
TABLE III. EXPECTED SYSTEM TOTAL COSTS AND COST SAVINGS FOR DAY- 20% 0.0 7 9.0 282 145
AHEAD UNIT COMMITMENT 25% 0.4 130 9.9 272 140
30% 2.0 741 30.4 279 138
Cost Cost
Wind Total Cost with Total Cost without No Battery
Savings Savings
% Battery ($) Battery ($) 15% 0.0 0 5.1 367 146
($) (%)
20% 0.0 8 16.1 339 147
15% 806,287 930,440 124,154 13.3%
25% 0.0 124 22.4 321 147
20% 765,307 887,480 122,173 13.8%
30% 1.3 1009 31.0 313 147
25% 733,779 849,963 116,184 13.7%
30% 712,808 827,570 114,762 13.9%
TABLE V. EXPECTED SYSTEM TOTAL COSTS AND COST SAVINGS FOR POST-
STAGE ANALYSIS
2) Post-Stage Analysis with the Fixed Operating Schedule
In the post-stage analysis, we first test the fixed-schedule Wind Total Cost with Total Cost without
Cost Cost
approach, where the battery is not allowed to deviate from the Savings Savings
% Battery ($) Battery ($)
($) (%)
schedule. The same metrics used in the day-ahead scheduling
15% 847,874 971,823 123,948 12.8%
stage are used in the post-stage analysis. The results for post- 20% 827,291 943,955 116,664 12.4%
stage analysis are reported in Table IV and Table V. From 25% 808,768 936,378 127,610 13.6%
Table IV and Table V, the same trend as in the day-ahead 30% 876,424 957,140 80,715 8.4%
scheduling stage can be seen, as battery storage can help
dispatch more wind generation; it decreases the total number 1.8
of hours that slow and fast units are committed and reduces
the system total costs. The security violations are also reduced, 1.6
in general, for the cases with the battery. The results in Table
Total System Cost ($M)
V indicate that the cost savings are similar for the three lowest 1.4
wind penetration levels, but lower for the 30% wind scenario.
At 30% wind penetration level, the increase in the violation 1.2
cost offsets the reduction in operating cost, which causes the
system total cost for the 30% wind scenario to be higher than 1
that of the 25% wind scenario. This is also a result due to out-
of-sample testing, i.e., the stochastic program takes into 0.8
consideration a subset of potential scenarios whereas the post-
stage analysis tests the proposed solution against a wider range With15% No15% With20% No20% With25% No25% With30% No30%
of potential scenarios. Cases
Fig. 2 presents a boxplot of the total system costs for each Fig. 2. Boxplot of total system costs for each case in the post-stage analysis.
case in the post-stage analysis. The edges of the box are the
25th and 75th percentiles and the whiskers represent the Comparing the results for day-ahead scheduling to those for
maximum and minimum without considering outliers. The post-stage analysis, it can be observed that the cost savings by
horizontal red lines represent median values and outliers are having battery storage in the system are lower in the post-
shown in red “+”. The plot shows the median value as well as stage analysis than those in the day-ahead scheduling. The
the variation in samples of system’s total costs for each case. reason is as follows. The post-stage analysis is formulated to
The cases labeled “With x%” are the cases with the battery for approximate the real-time operation, where each dispatch
“x%” wind penetration level; the rest are the cases without the problem is solved with limited foresight of future information
battery. From Fig. 2, it can be noted that with the battery in the (i.e. one hour look-ahead forecast) using a rolling horizon.
system, both the maximum and minimum value of the total When the realized wind generation deviates from the day-
system costs are reduced. Also, for wind penetration levels of ahead forecast, the day-ahead battery schedule may not be
15%, 20% and 25%, the boxes for the cases with battery able to address the unexpected deviation. Therefore, as shown
storage span much shorter ranges than those of the cases in Table IV, the system reserve violations are higher in the
8
post-stage analysis than those in the day-ahead scheduling, each scenario. Note that the energy used for deployment of
especially at higher wind penetration levels. As the flexibility spinning and regulation reserves is not counted in (39).
of the battery cannot be fully utilized with a fixed-schedule 𝑂𝑂𝑂𝑂𝑂𝑂 𝑂𝑂𝑂𝑂𝑂𝑂
∑𝑡𝑡 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 /𝜂𝜂𝑏𝑏
approach, reserve requirements are violated to ensure the 𝐷𝐷𝐷𝐷𝐷𝐷𝐷𝐷𝐷𝐷_𝐷𝐷𝐷𝐷𝐷𝐷𝐷𝐷ℎ𝑎𝑎𝑎𝑎𝑎𝑎𝑎𝑎_𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶𝐶 = 𝜋𝜋𝑠𝑠 ∑𝑠𝑠 (39)
𝐸𝐸𝑏𝑏𝑀𝑀𝑀𝑀𝑀𝑀 −𝐸𝐸𝑏𝑏𝑀𝑀𝑀𝑀𝑀𝑀
feasibility of the problem. Therefore, as renewable penetration
level increases, a more flexible operating approach is needed TABLE VII. EXPECTED DISCHARGING CYCLES FOR THE BATTERY
for battery storage.
6-Day Yearly
It should be noted that this work simplifies the generation D219 D225 D230 D232 D236 D243
Sum Sum
scheduling process adopted in industry today, where a short- 2.1 3.0 2.9 3.0 2.3 2.8 16.2 988.2
term unit commitment is usually solved between the day-
ahead scheduling stage and the real-time economic dispatch Assume the battery used in the study is a lithium-ion (Li-
stage [36]. This is also one of the reasons that the benefit ion) battery. The cycle life for the battery is obtained from the
provided by the battery is lower in the post-stage analysis than DOE/EPRI energy storage handbook [33]. In [33], such
that in the day-ahead scheduling. During such an intermediate batteries are assumed to last 15 years with a daily cycle, i.e.
stage, the day-ahead schedule for the battery could be updated the total number of cycles is assumed to be 365 × 15 = 5475
based on the short-term wind forecast. Even though such a cycles. Assuming the battery can be fully discharged at most
short-term unit commitment stage is not formulated in this 5475 cycles, the expected life time (number of years) in our
paper, the two-step framework still captures the main analysis can be calculated using the expected yearly
challenges in scheduling battery storage in a system with discharging cycles obtained from Table VII. Hence, the
increased uncertainties: 1) real-time operation has limited expected life time for the battery is calculated as
look-ahead functionalities and 2) the schedule obtained from a 5475
look-ahead scheduling process may not be able to fully utilize 𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸𝐸 = ≈ 5.5 Years. (40)
988.2
the flexibility of battery storage when uncertainties increase.
3) Cost-Benefit Analysis of the Battery This result indicates that the battery is expected to last for
In this subsection, a cost-benefit analysis is performed to about five and half years for the duty cycle in our case study.
study if the cost savings achieved by using the battery can Assume the yearly cost saving obtained by using the battery is
offset the investment cost of the battery. The cost-benefit the same for the five and half years and that the discount
analysis is performed using the results from the day-ahead factor is 6% per year. The present value, PV, of the system
stage for the 20% wind penetration level. The same cost- cost saving over this period is computed as
benefit analysis could also be done based on the real-time 𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦𝑦_𝑐𝑐𝑐𝑐𝑐𝑐𝑐𝑐_𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠𝑠
𝑃𝑃𝑃𝑃 = ∑𝑡𝑡 = 191,387,407($). (41)
results from the post-stage analysis. (1+𝑖𝑖𝑑𝑑 )𝑡𝑡
The day-ahead cost savings from six representative days A wide range of cost estimates exist for Li-ion batteries
are summarized in Table VI. The yearly total cost saving is [33]-[35]. In [33]-[35], the capital costs for batteries are
computed using the cost savings from the six representative calculated with the assumption of a specific battery
days. In Table VI, “D219” represents representative day 219 technology and a specific configuration of the battery (power
and similarly for the other representative days. rating and energy capacity). In the paper, we assumed a capital
TABLE VI. SUMMARY OF DAY-AHEAD COST SAVINGS ($K) cost, CC, of 3,000 $/kW for the battery. This number is
estimated based on the capital costs for Li-ion batteries with
D219 D225 D230 D232 D236 D243
6-Day Yearly similar power ratings and energy capacities that reported in
Sum Sum [33]-[35]. With a capital cost of 3,000 $/kW, the net present
103 110 124 122 122 102 684 41619
value, NPV, of the battery is calculated as shown in (42):
As battery storage suffers from degradation effects, the 𝑁𝑁𝑁𝑁𝑁𝑁 = 𝑃𝑃𝑃𝑃 − 𝐶𝐶𝐶𝐶 = 191,387,407 − 150,000,000 =
impact of cycling on the life time of the battery should be 41,387,407 ($) (42)
taken into account. The expected daily and yearly discharging
cycles are computed for the battery and summarized in Table We also calculate the breakeven cost for the battery, i.e. the
VII. The daily expected discharging cycle is computed using capital cost that would give a zero NPV. The breakeven cost is
(39). The maximum depth of discharge (DOD) of the battery found to be 3,828 $/kW. The breakeven cost of the battery is
is assumed to be 80%, since the battery has a minimum energy plotted versus different values of discount factors in Fig. 3: it
level of 30 MWh and a maximum energy capacity of 150 ranges from about 3,943 $/kW to 3,612 $/kW when the value
MWh. As shown in (39), the daily expected discharging cycle of discount factor is selected in the range of 0.05 to 0.08.
is calculated on an aggregated base. It is assumed in the cost- The results of the cost-benefit analysis indicate that battery
benefit analysis that the life time of the battery is sensitive storage is beneficial to this system when current capital cost
only to the total number of equivalent full discharging cycles, estimates, the degradation effect and its impact on the lifetime
i.e. the DOD of each discharging cycle has little to no effect of the battery, are considered. However, it should be noted that
on the life time of the battery. This is a reasonable assumption as the costs for batteries vary depending on the battery
for some battery technologies [17], [34]. Since the initial SOC configuration and technology, the conclusion may not apply to
is required to be the same as the final SOC in the day-ahead all battery storage technologies. Moreover, the estimated
UC, the number of daily equivalent full discharging cycles benefits only apply to the specific test power system, which is
will be the same as the daily equivalent full charging cycles in small and has high fuel costs. Larger systems with lower fuel
costs are likely to see lower benefits of energy storage.
9
However, with that being said, the study in this section in terms of MWs. Therefore, at higher wind levels, with the
provides an adequate analysis to demonstrate the benefits and proposed approach, the battery can be used to compensate for
the cost-effectiveness of battery storage in systems with the deviation in wind generation and provide more cost
renewable resources. As the cost of battery storage is expected savings. In Fig. 4, there is only one case (D225, 15%) in
to be further reduced in the next five to ten years [2], the which the performance of the proposed method is worse than
benefits of battery storage will be more prominent in the the fixed-schedule case; and the cost difference is about 1%.
future. The cause of the cost degradation in the case of (D225, 15%)
is explained as follows. For day 225, at the day-ahead stage,
4,000 the battery is scheduled to provide a large amount of spinning
Battery Breakeven Cost
the penalty cost. For most of the time periods, the battery is
operated within the range provided by the proposed method. 30%
As the flexible operating range is obtained using the day- D243
Wind Level
ahead schedules, it provides a policy for the battery of when to 25% D232
discharge and charge. As shown in Fig. 7, the battery is forced D236
by the limits to increase its SOC level during hours 10 to 13, 20% D230
and to decrease its SOC level during hours 14 to 15. D225
Compared with the fixed-schedule approach, the proposed 15%
D219
method can provide an operating range for the battery in each
time period rather than a fixed operating point. As renewable -2.0% 0.0% 2.0% 4.0% 6.0% 8.0% 10.0%
generation deviates from forecasts, the battery is allowed to be Cost Saving%
operated within the operating range, and even possibly exceed Fig. 6. Cost savings in percentage of the proposed method to the 3-hour look-
the range, to compensate for the uncertainties in renewable ahead method.
generation. By using the proposed approach, the flexibility of
the battery storage can be better utilized to address the 200
intermittency in renewable resources.
Energy (MWh)
150
100
30% D243 50
D232
Wind Level
0
25% 1 3 5 7 9 11 13 15 17 19 21 23
D236
20% Time
D230 Proposed Method Upper Bound
D225 Lower Bound Fixed-Schedule
15%
D219 Fig. 7. Illustration of the proposed flexible operating range approach (Day
-2.0% -1.0% 0.0% 1.0% 2.0% 3.0% 4.0% 236, scenario 3, 30% wind level).
Cost Saving%
In Fig. 8, the energy and ancillary services scheduled for
Fig. 4. Cost savings in percentage of the proposed method to the fixed-
schedule method. the battery for day 236, scenario 3 with 30% wind level are
presented. The blue solid bars in Fig. 8 represent the power
TABLE VIII. SIX-DAY COST SAVINGS OF THE PROPOSED METHOD COMPARED output of the battery, where positive value indicates
TO THE FIXED-SCHEDULE METHOD FOR 15% WIND PENETRATION
discharging and negative value indicates charging. From Fig.
6-Day 6-Day 8, it can be seen that the battery is scheduled mainly to provide
D219 D225 D230 D232 D236 D243 Sum Sum ancillary services, which is because of its fast-ramping
($) (%) capability. Also, it can be noted from Fig. 8 that the ancillary
4,584 -8,000 12,024 11,054 4,277 10,333 34,273 1.1% services provided by the battery are sometimes larger than its
maximum power rating of 50 MW. This result occurs because
the battery requires a short transition time between charging
and discharging mode. In charging mode, a battery can stop
D243 charging and transition to discharging mode to provide up
30%
D232 reserves. The maximum up reserve that the battery can
𝐼𝐼𝐼𝐼 𝑂𝑂𝑢𝑢𝑡𝑡_𝑚𝑚𝑚𝑚𝑚𝑚
25% D236 provide in this case is 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏 + 𝑃𝑃𝑏𝑏𝑏𝑏 . This result suggests
that the flexibility of battery storage will be more valuable
Wind Level
D230
20% when providing ancillary services.
D225
15% D219
150
0.0% 5.0% 10.0% 15.0%
Cost Saving% 100
Fig. 5. Cost savings in percentage of the proposed method to the no-schedule RegDn
50
method.
0 RegUp
MW
-50 Spinning
-100 NetOut
-150
1 3 5 7
9 11 13 15 17 19 21 23
Time (h)
Fig. 8. Schedule for the battery using the proposed method (Day 236, scenario
3, 30% wind level).
11
[31] DOE Global Energy storage Database, “Rokkasho village wind farm,” and as Vice President-Subdivisions and President of the Institute for
[Online]. Available: Operations Research and the Management Sciences (INFORMS). Prof. Birge
http://www.energystorageexchange.org/projects/385 is former Editor-in-Chief of Mathematical Programming, Series B. He also
[32] DOE Global Energy storage Database, “ASE Larurel Mountain,” serves on the editorial boards of Mathematical Programming, Series A,
[Online]. Available: Operations Research, Management Science, Interfaces, Naval
http://www.energystorageexchange.org/projects/164 ResearchLogistics, Computational Optimization and Applications, and
[33] Sandia National Laboratories, “DOE/EPRI 2013 electricity storage Management Science. He chaired the Fifth International Conference on
handbook in collaboration with NEECA,” Jul. 2013. [Online]. Stochastic Programming in 1989, the XV International Symposium on
Available: Mathematical Programming in 1994, and the XX International Symposium on
http://energy.gov/oe/downloads/doeepri-2013-electricity-storage- Mathematical Programming in 2009. He was selected as an Office of Naval
handbook-collaboration-nreca-july-2013 Research Young Investigator in 1986 and received the Medallion Award from
[34] International Renewable Energy Agency, “Battery storage for the Institute of Industrial Engineers in 2002, the Fellows Award from
renewables: market status and technology outlook,” Jan. 2015. [Online]. INFORMS in 2002, the George Kimball Prize from INFORMS in 2008, and
Available: the Distinguished Fellow Award from the Manufacturing and Service
http://www.irena.org/DocumentDownloads/Publications/IRENA_Batter Operations Management Society (MSOM) in 2013. In 2011, he was elected a
y_Storage_report_2015.pdf member of the National Academy of Engineering.
[35] Electric Power Research Institute, “Cost-effectiveness of energy storage
in California,” Jun. 2013. [Online]. Available: Emil M. Constantinescu received his Ph.D. degree in Computer Science
http://www.cpuc.ca.gov/NR/rdonlyres/1110403D-85B2-4FDB-B927- from Virginia Tech, Blacksburg, in 2008. He is currently a Computational
5F2EE9507FCA/0/Storage_CostEffectivenessReport_EPRI.pdf Mathematician in the Mathematics and Computer Science Division at
[36] California ISO, “Market process,” [Online]. Available: Argonne National Laboratory, Argonne, IL. His research interests include
http://www.caiso.com/market/Pages/MarketProcesses.aspx uncertainty quantification in weather and climate models and their
applications to energy systems.
Nan Li (S’11) received the B.E. degree in electrical engineering from North
China Electric Power University, in Beijing, China and the M.S. degree in Kory W. Hedman (S’05, M’10) received the B.S. degree in electrical
electrical engineering from Arizona State University, Tempe, AZ, in 2010, engineering and the B.S. degree in economics from the University of
and 2012 respectively. Currently, he is pursuing the Ph.D. degree in electrical Washington, Seattle, in 2004 and the M.S. degree in economics and the M.S.
engineering from Arizona State University, Tempe, AZ. His research interests degree in electrical engineering from Iowa State University, Ames, in 2006
include power system economics, operations, energy storage, and the and 2007, respectively. He received the M.S. and Ph.D. degrees in industrial
application of data science in power system. engineering and operations research from the University of California,
Berkeley in 2008 and 2010 respectively.
Canan Uçkun received the B.Sc. degree in industrial engineering from Currently, he is an assistant professor in the School of Electrical, Computer,
Marmara University in 2003, the M.Sc. degree in industrial engineering from and Energy Engineering at Arizona State University. He previously worked
Koç University, Istanbul, Turkey, in 2006, and the Ph.D. degree in operations for the California ISO, Folsom, CA and he has worked for the Federal Energy
management/management science from the University of Chicago, Booth Regulatory Commission, Washington, DC. His research interests include
School of Business, in 2012. She is a Researcher in Engineering Systems power systems operations and planning, power systems economics, operations
Modeling in the Center for Energy, Environmental, and Economic Systems research, stochastic programming, and market design.
Analysis (CEEESA) at Argonne National Laboratory, Argonne, IL, USA. She
has done research on electricity markets, smart grid, demand response, Audun Botterud (M'04) received the M.Sc. degree in industrial engineering
revenue management, and inventory systems. Her current work includes and the Ph.D. degree in electrical power engineering from the Norwegian
stochastic unit commitment, renewable integration, grid-level energy storage, University of Science and Technology, Trondheim, Norway, in 1997 and
and demand response related projects. 2004, respectively. He is a Principal Energy Systems Engineer in CEEESA at
Argonne National Laboratory, Argonne, IL, USA. He was previously with
John R. Birge received the A.B. degree in mathematics from Princeton SINTEF Energy Research in Trondheim, Norway. His research interests
University, Princeton, NJ, USA, and the M.S. and Ph.D. degrees in operations include power systems planning and economics, electricity markets, grid
research from Stanford University, Stanford, CA, USA. He is currently the integration of renewable energy, energy storage, and stochastic optimization.
Jerry W. and Carol Lee Levin Professor of Operations Management at the Dr. Botterud is co-chair for the IEEE Task Force on Bulk Power System
University of Chicago Booth School of Business. Previously, he was Dean of Operations with Variable Generation.
the McCormick School of Engineering and Applied Science and Professor of
Industrial Engineering and Management Sciences at Northwestern University
from 1999 to 2004. He also served as Professor and Chair of Industrial and
Operations Engineering at the University of Michigan, where he was from
1980 to 1999, as Vice-Chair of the University of Michigan Senate Assembly,