DIVISION 15 MECHANICAL
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 1 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
03
04
05
06
07
08
09
10
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 2 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
TABLE OF CONTENTS
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 3 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
1.1 GENERAL
c) The Contractor shall provide sufficient detail to allow the design of the
primary settlement tank base.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 4 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
b) The tanks shall be designed such that the net volumes and surface
areas are as required by the Contract, and will under operational
conditions contain raw sewage and sewage sludge at ambient
temperatures with a pH in the range 3 - 8. The specific gravity of the
contents is expected to be 1.0.
f) All pipework and pipework connections for Primary Tanks, Humus Tanks
and Storm Tanks shall be 150 mm diameter. Hydrostatic desludge
pipework shall be extended upwards beyond the desludge level to just
below the mesh floor panels. A suitable cut out shall be provided at this
point for water or air line insertion into the desludge line or to be used as
a rodding point if required.
g) The location of the inlets and outlets of pipework for each tank shall be
agreed with the Engineer prior to manufacture and will be indicated at
the time of order, if known.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 5 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
j) All mesh flooring shall be galvanised steel or GRP and cover panels
shall be designed to carry a uniform loading of 5 kN/m2. Mesh flooring
shall not be provided over the launder channels.
k) Each tank cover panel shall not weigh more than 25 kg and shall be
designed to be interlocked and secured to the main body of the tank and
access bridge by padlocks in such a way as to prevent their removal
unless the padlocks are removed.
The disc support spindle shall be of galvanised mild steel hollow section with
mild steel stub shafts supported in split bearings fitted with automatic grease
lubricators. The spindle assembly shall be designed to operate with the
minimum of deflection particularly following prolonged plant shutdown.
Where shafts are split they shall be connected by a flexible coupling.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 6 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
c) Chains shall be either Duplex or Triplex. Single link chains are not
acceptable.
a) The Static Bio filter shall comprise a filter unit and sump arrangement
complete with irrigation pumps, access hatches, lifting davits and socket,
desludge valves and pipework.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 7 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
c) The static bio filter unit shall be classified as a zone one area.
f) The unit shall be provided with 100mm sludge draw off pipework
complete with isolation gate valve which will allow settled sludge to flow
by gravity to a sludge sump adjacent to the Bio filter unit. The sludge
settlement zone within the unit shall be designed to allow complete draw
down of the unit thus eliminating any possibility of stagnation areas.
b) The unit shall consist of Settlement and Aeration tank, bridge and
access walkway plus ladders, air blowers and air supply control system,
desludging and sludge transfer system.
c) All tanks shall be constructed from either welded stainless steel or pre-
drilled glass coated steel sections coated with a minimum adhesive
strength of not less than 34,000 kN/m2. All tanks to be in accordance
with Section 15200: Sectional Storage Tanks.
d) Pipe entries, sensing pockets, access hatches etc shall all be purpose
made sections and shall be fully reinforced and totally coated.
e) All joints shall be mastic sealed and the sealant shall be allowed to
extrude so that a fillet is formed over the edge of the sheet.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 8 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
f) Where holes are drilled in situ all exposed edges shall be encapsulated
in mastic as part of the seal between the bolt and the glass coated steel.
g) Clamping of the sheets, ladders, hand railing etc. shall be by high tensile
steel bolts, hot dip galvanised with ABS coated heads. The bolts shall be
bedded in the mastic sealant. After tightening the threads of the bolt
shall protrude from the nuts by not less than one thread and not more
than the diameter of the bolt unless the protruding thread is to be used
for insulation fixing. Plastic caps shall be fitted to the nuts after
tightening.
h) Where tanks are open topped the periphery of the tank shall be
reinforced with glass coated or galvanised steel angles for stiffening.
Covered tanks shall be suitable for pedestrian access otherwise suitable
markings and access ways shall be provided to limit entry.
j) Where access hatches are specified and the fixing is by bolting then all
nuts, bolts, washers, removed as a routine shall be grade 316L stainless
steel.
The air blowers shall be of the rotary piston type which shall deliver oil free
air at the minimum rate required for air diffusion. The blower shall be
packaged units in accordance with the Section 15100 - Compressed Air
Systems supplied as an automatic 1 duty & 1 standby arrangement, and
include unloading valves.
Air supplies shall discharge into a common air supply manifold of galvanised
mild steel or stainless steel, via non-return and isolating valves. Each
discharge shall also incorporate a pressure relief valve. A pressure operated
under pressure switch shall trip the blower on loss of air supply. A discharge
pressure gauge shall be provided on the delivery branch of the air supply
manifold.
a) The non return valves shall be of the wafer pattern or nozzle ring check
pattern with valve bodies of high grade cast iron with stainless steel
fulcrum pins, stainless steel stops and inconel return springs. Valves to
be in accordance with Section 15020: valves, penstocks and actuators.
b) The pipework shall be arranged such that it forms an air ring mesh
around the aeration tank with a suitable number of branches dropping
into the tank containing bubble diffusers. Diffusers shall comply with
Section 15130: Aeration Equipment.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 9 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
a) All tanks and process zones shall be provided with 100mm de-sludging
pipework brought to above ground level and terminating in 100mm male
tanker connectors positioned so as to allow for ease of connection to a
quick fit tanker inlet pipe.
c) One set of de-sludging pipework shall be provided for each 5m2 of plan
area of sludge storage zone, measured at the upper limit of the zone.
d) The unit shall be supplied with a suitable method of sludge transfer for
the return of the sludge to the aeration tank or transferring to the storage
zone. Where submersible pumps are used these shall be supplied as
duty/standby. The unit shall be supplied with 100 NB sludge draw off
pipework completed with isolating gate valves.
c) Access panels shall be sized, suitably hinged and provided with props
so as to enable one person to lift and secure the panel(s) from one
working position.
d) Where access hatches are located greater than 0.4 metres above
surrounding ground level ladders and access platforms shall be provided
to allow maintenance of the plant.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 10 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
Membrane Bio Reactor units shall be in accordance with Section 15270 and
the Particular Specification.
a) The Contractor shall provide guarding and hand railing such that it
safeguards operating personnel from the works and plant. The access
walkway shall comprise galvanised mild steel, non slip floor plates and
hand railing across and around the tanks.
b) The walkways, guards and hand railing for the plant and works shall be
so designed that they aid operation, attendance, inspection and
maintenance. This is particularly relevant in the area of the drive end of
the R.B.C. where all round access to the gearbox etc. is essential if
adequate maintenance is to be achieved.
g) The humus tank bridge shall be constructed from rolled steel channel
beams and designed to withstand the total loadings imposed by the
bridge and its associated equipment plus a superimposed load of
250kg/m2 without exceeding a total deflection of 1/360th of the bridge
span.
h) The maximum permitted noise level, with covers fitted, shall not exceed
80 dbA at 1 metre.
1.8 WASHWATER
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 11 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
a) The washwater tank shall be a proprietary GRP unit complete with lid
and of suitable dimensions to provide a minimum of 15 mins. of wash
time. The tank shall be capable of being fitted in the plant room of the
kiosk together with the washwater pump and associated pipework.
a) The Contractor shall supply a GRP kiosk to house the washwater set
and also the Local Control Panel for the package sewage treatment
system.
c) If GRP, the kiosk shall be weather proof, constructed from resin bonded
glass fibre inner and outer skins totally encapsulating a rigid core
weather and boil proof to BS1203 ('U' value 1.5 W/m²/deg.C). The doors
shall also be GRP/rigid core sandwich with box section steel
encapsulated into the edges and frames. Heavy duty high tensile non-
corroding extruded alloy hinges with stainless steel pins and through
bolts shall be used. Walls and roofs shall be continuously internally
bonded.
e) The kiosk shall have a partition wall to segregate the washwater system
and the local control panel. The kiosk will have access doors to both
sections.
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 12 of 13
Treatment Plant
General Specification for Mechanical Works
Abu Dhabi Sewerage Services Company
(ADSSC)
END OF SECTION
Packaged Sewage
ADSSC/GSMW Division 15 Section 15190 Rev: 02 Jan. 2011 Page 13 of 13