You are on page 1of 3

Project name:

COLLECTION

S.No Description Total Cost Remarks

1 TOTAL MANPOWER + RESOURCES COSTS -

2 TOTAL SITE OFFICE COSTS -

3 TOTAL MAINTENANCE COSTS -

GRAND SUMMARY FOR PRELIMINARIES -

Preliminaries cost 3 Company Name


Project name:

Installation Cost
Sl. No. Category of manpower Qty. Durn. Unit rate Total rate Remarks

1 Project Manager 1 12 -

2 Project Engineer 1 12 -

3 Planning Engineer 1 12 -

4 Quantity Surveyor (Post-tender) 1 12 -

5 HSE Engineer 1 12 -

6 QA/QC Engineer 1 12 -

7 Site Inspector/Foreman Civil 1 12 -

8 Land Surveyor 1 5 -

9 Document Controller 1 12 -

Total Manpower Costs -

Estimation for Resources

Sl. No. Category of resource Qty. Durn. Unit rate Total rate Remarks

1 Accommodation incl. services 2 12 -


2 Furniture & fixture, Entertainment etc 2 12 -
3 BHK for 2 nos
Managers 1 12 -
Engineers 5 12 -
Cost of Vehicles & Equipments :
Pickups 4WD 1 12 -
3 S.H
SUV 4WD PARADO or Equivalent 1 12 -
Tipper truck 3T 1 12 -
Fuel for Vehicles and Machineries. 3 12 -
4
Maintenance of Vehicles & Machines. 3 12 -
Hiring of crane 1 10 -
TBD
Transportation of material (sundries) 1 12 -
5
Transportation of Labour 1 12 - 120 Nos
Accommodation of Labour 1 12 - 150 Nos
6 GSM Bill for Engineer 8 12 -
7 GSM Bill for supervisor 1 12 -
8 Miscellaneous expanditure 1 12 0.000
9 Insurance cost LS LS -
Total Resources Costs -

TOTAL MANPOWER + RESOURCES COSTS -

Preliminaries cost 3 Company Name


Project name:

MOBILISATION / DEMOBILISATION
SITE OFFICE/CAMP ESTABLISHMENT & client facilities

Unit rate (in Total Amount


Sl. No. DESCRIPTION Unit Qty. Remarks
R.O) (in R.O)

1 Portacabin for ATE & Client (Office) nr 2 -

2 Associated civil + elect. works for PC nr 2 -

3 Office f & f (tables, chairs) including a/c l/s 2 -

4 Project Sign Board nr 2 -

5 Site Hoarding R.m. -

6 Temp. fencing for ATE materials yard R.m. 50 -

7 Gate 1m nr 2 -
8 Gate 5m nr 2 -
9 Transportation of pc/containers nr 2 -
10 Crane for loading & unloading nr 2 -
Supply arrangement for site (Transfo,
11 LS 1 -
feeder pillar cable etc)
Supply and fixing of Site as well as
12 Office area should be covered with LS 1 -
CCTV camera.
13 O/H tank with structure - GRP l/s 3 -
14 Stationary l/s 12 -
Misc. Items (such as xerox m/c + fax
15 l/s 1 -
m/c + tel) ATE Office
Misc. Items (such as xerox m/c + fax
16 l/s 1 -
m/c + tel) Client Office
17 Tea boy (1 man) month 12 -
18 Electricity Bills month 12 - DG 250 Kva
19 Water Bills month 12 - 7 Trip (5k. G)
20 Sewage Bills month 12 - 2 Trip
21 Telephone and Internet Bills month 12 -
Entertainment/ Refreshment/site
22 month 12 -
meetings (cleaning items etc)
Maintaining the office & accomodation
23 month 12 -
(cleaning items etc)
Salalah Free zone gate pass charges for
24 Nos 300 -
contractor's staff/workers
25 De-Mobilization & Site Cleaning LS LS -

Total Site Office Costs -