Professional Documents
Culture Documents
M. Haddad
Lean Manufacturing
What is Cellular Manufacturing?
• A fundamental step in lean manufacturing that helps companies build a variety of
products with as little waste as possible:
– Workstations and equipment used for similar products are arranged in an efficient sequence
that supports a smooth flow of materials and components with minimal transport or delay
– Layout organizes process into a group of team members and machines in a way to work at the
same speed, with even workloads and no setups or wastes between different operations
o e.g. if a process for a product requires “Cutting” followed by “Drilling” and “Finishing”, the cell would
include all the workers and equipment for performing those processes, arranged in that order
o Can be done by many different types of clustering algorithms (rank order clustering is the simplest,
supplemented with machine capacity constraints is useful)
1 2 3 4 5 6 7
A 0.3 -- -- -- 0.6 -- --
B -- 0.3 -- 0.3 -- -- 0.1
Machines
• For the binary ordering portion, interpret rows and columns as binary numbers
Parts
1 5 7 3 4 6 2 Minimum #
Sum
of machines
D 0.2 -- 0.4 -- 0.3 -- 0.5 1.4 2
Machines
Parts
1 2 3 4 5 6 7
A 1 -- -- -- 1 -- -- 25 = 32
B -- 1 -- 1 -- -- 1 24 = 16
Machines
C 1 -- -- 1 -- 1 -- 23 = 8
D 1 -- 1 -- 1 -- 1 22 = 4
E -- 1 -- -- -- 1 -- 21 = 2
F -- 1 1 1 -- -- 1 20 = 1
26 = 64 25 = 32 24 = 16 23 = 8 22 = 4 21 = 2 20 = 1
• For the re-sorted matrix above, sort columns w.r.t. decreasing binary numbers
o The new parts order is: 1 – 5 – 7 – 3 – 4 – 6 – 2
Stage 2, Step 1 (Continued)
• The resorting of rows and columns is done based on the following totals
Parts
1 5 7 3 4 6 2 Binary Total
A 0.3 0.6 -- -- -- -- -- 23 = 8 68
E -- -- -- -- -- 0.5 0.4 20 = 1 34
Binary 26 = 64 25 = 32 24 = 16 23 = 8 22 = 4 21 = 2 20 = 1
Total 56 7 36 22 40 17 38
Stage 2, Step 1 (Continued)
• Assign (group) parts and their corresponding machines to cells (in sorting order)
– Add machines to cells until either:
o the capacity of some machine would be exceeded, or
o the maximum number of machines, or of duplicate machines, would be exceeded
e.g. if part 5 required more than 0.8 capacity of machine D, then cell 1 would need a duplicate of machine D,
which is OK since only 1 duplicate per machine is possible
e.g. if part 4 required more than 0.5 capacity of machine F, then it would require duplicate of machine F but in
this case it could not be made in cell 2 anymore since the maximum number of machines (4) would be exceeded
6 6 3 C, E C (0.7), E (0.5)
• Machines used:
– One machine each of types: A, E
– Two machines of types: B, D, F
– Three machines of type: C
Stage 2, Step 1 (Continued)
• Single-pass heuristic (of Askin and Standridge, 1993) is a simple heuristic not
necessarily optimal solution (not always minimum possible number of machines)
– Compare result with theoretical min number of machines
o need one more copy of machine B (2 instead of 1) and one more copy of machine C (3 instead of 2)
Parts
1 2 3 4 5 6 7 Theoretical Heuristic
Sum Min. # Min. #
Total 9 11
Stage 2, Step 2: Cell Layout
Cell Design • Layout of the Cell
• Machines placed close together with room for only a minimal quantity of WIP
• Process flow is often (but not always) counterclockwise to maximize right hand
maneuvers of operators
Stage 2, Step 2 (Continued)
• Clockwise U-shape example in detail
Stage 2, Step 3: Cell Operation
Cell Operation • Type of Production Control
• Decoupled cells use a storage area to store part families after a cell has finished working
on them
– Parts are retrieved from storage area when another cell is to operate on them
– Storage area acts as a decoupler, making cells and departments independent of each other
Integrated Decoupled
Challenges with CM Implementation
• It is not enough to simply arrange different equipment in sequence to make cellular
manufacturing really work
• Bottlenecks along the single process flow must be eliminated
– balancing the equipment capacities with each other
– choosing 'right-sized' equipment that match each other
– combining two or more smaller capacity equipment to match one larger-capacity equipment
– Total Employee Involvement (TEI): cellular manufacturing requires focus on operators with
multifunctional capabilities that are involved in teamwork
Challenges with CM Implementation
• Human resource issues:
– Cell teams need to be cross trained in cell operations (cross-functional training) compensation
– Supervisors need to also act as coaches compensation
– Operators need teamwork training
– Initial resistance to change
– Cells need support
• Operational barriers:
– Obtaining balance among cells is difficult
– Conversion to cellular manufacturing can involve costly realignment of equipment
– Shifts to production cells distributes painting, coating, washing or chemical milling operations to
multiple points requires adjustment in chemical and waste management practices to avoid
adverse impact to the environment and failure to comply with regulatory requirements