Professional Documents
Culture Documents
ENGR. (DR.) VICTOR O. OYENUGA, PPNIStructE, FNSE, FNIStructE, FNICE, FNIHTE, MNIOB
Chief Executive Officer: Vasons Concept Consultants Ltd.
(Consulting Engineers and Town Planners)
1.0 INTRODUCTION
Some architectural designs pose a huge pressure on the thinking faculty of the Structural Engineer to achieve both a
safe and yet economical structure. Such structures include cantilevered galleries and cantilevered rooms.
These are required either to allow for more space over the ground level which cannot be accommodated at the ground
floor because of town and physical planning restrictions and setbacks or simply to provide additional space as in the
case discussed here under.
The central theory behind their design is that the cantilever must be provided with adequate tie-back structure to
prevent uplift due to negative shear that can develop at the other support. The tie-back beams must be longer than the
cantilever beam and loaded, with the other end encastred (fixed) into the supporting column.
• A 6.7m cantilever gallery to sit 150students. The required space was for 450students in the Faculty of Law of
a private University and only 300students can be accommodated at the raked and elevated ground floor level
due to space constraint.
• Cantilevered rooms on 2nd and 3rd Floors of a multi-purpose Alumni-building of a College of Technology and
• Multi-level Conference hall such as the World Hall, opposite CNN Headquarters, Atlanta, Georgia.
The sketches in Figures 1 through 4 show the various types as described above and Plates 1 through 3 revealed the
pictures of some of such buildings.
1|Page
L1
L1 > L2
1st Floor
1st Floor
r
The black colour shows the essential frames (columns and beams) for each of the Cases. The tie-back here is well
evident. In the cases of Figures 3 and 4, the external façade will also be framed.
The discussions and design following elucidate the design procedure that is typical for each. However, the case
considered here is that as illustrated in Figure 1 and Plate 1.
2|Page
3.0 DESIGN OF A TYPICAL MIDDLE FRAME.
3|Page
A Column previously
inserted by the Architect.
4|Page
For clarity, the actual gallery structural layout is as shown in Figure 9 since this is a live project not a theoretical one.
The typical frame on gridline D is designed to illustrate the procedure. The frame beam size is 1350 by 600mm and
the main column size is 600mm by 600mm.
5|Page
3.2.1 Analysis
Figure 10: Force Diagram of Gallery Beam on Gridline D.
P1kN P2kN P3kN P4kN
wkN/m wkN/m
LOADING:
Library live load = 5.0kN/m2.
Galleries live load = 5.0kN.m2.
Point Load P1
Roof loading: 2.25(0.6 +1.350/2)(7.5 + 6.41)/2 = 19.95kN.
Roof beam 5.0 (7.5+6.411)/2 = 34.78kN.
Col own, say = 10.00kN.
So, the total point load, P1, = 19.95 + 34.78 + 10 = 64.73kN., say = 65kN.
Point Load P2
Slab own load 15.5(9.055)/2 = 70.17kN/m.
Beam own load and finishes = 5.00 ,,
Total = 75.17kN/m.
So, the total point load, P2, 75.17 x (7.5 + 5.541)/2 = 490.15kN say = 490kN.
Point Load P3
Slab own load 20.5 x 3.225 = 66.11kN/m.
Beam own load and finishes = 5.00 ,,
Total = 71.11kN/m.
So, the total point load, P3, 71.11 x (7.5 + 4.085)/2 = 411.9kN say = 412kN.
Point Load P4
Slab own load 20.5 x 3.225/2 = 33.05kN/m.
Beam own load and finishes = 5.00 ,,
Total = 38.05kN/m.
So, the total point load, P4, 38.05 x (7.5 + 3.535)/2 = 209.94kN say = 210kN.
6|Page
Thus, we have:
1 3
Bending Moment.
M1 = 65 x 1.35 + 25 x 1.352 x 0.5 = 111kN.m.
M3 = (210 x 6.450) + (412 x 3.225) + (25 x 6.452 x 0.5) = 3203kN.m.
490 𝑥 4.605 𝑥 4.450 4.528
Mfreespan (at the midspan) = 25 x 9.0552 x 0.125 + 𝑥 = 1,346.60kN.m
9.055 4.605
490 𝑥 4.605 𝑥 4.450
Mfreespan (at the 490kN) = 25 x 9.055 x 0.5 x 4.605 – 25 x 4.6052 x 0.5 + = 1,365.06kN.m.
9.055
Using the higher value at the point load, being maximum, because the udl is small and the point load is large. The span
free span moment = 1,365.06kN.m. or 1365kN.m.
Based on the principle of superimposition, we have the following Bending Moment Diagram shown in Figure 12.
111kN.m
318.5kN.m
Shear
V1,left = 65 + 1.35 x 25 = 98.75kN.
25 𝑥 9.055 490 𝑥 4.45 (111 − 3203)
V1,right = + + = 12.525kN.
2 9.055 9.055
25 𝑥 9.055 490 𝑥 4.605 (3203−111)
V3,left = + + = 703.850kN.
2 9.055 9.055
V3,right = 210 + 412 + 25 x 6.45 = 783.25kN.
7|Page
3.2.2 Design
Shear Reinforcements.
The following procedures are enunciated in EC2 for shear design.
The maximum shear resistance when 𝜃 is 22o is calculated from:
VRd,max(22) = 0.124bwd(1 – fck/250)fck N.
And when 𝜃 is 45o, we have:
VRd,max(45) = 0.180bwd(1 – fck/250)fck N.
Noting: V – the ultimate shear force at the center of bearing of the member,
VEf – the ultimate shear force at the face of the column,
VEd – the ultimate shear at a distance, d, from the face of the column,
Vwd – the shear force in the link and
VRd,s – the shear resistance of the links
VRd, max – the maximum design value of the shear which can be resisted by the concrete strut.
When VRd,max(22) < VEf < VRd,max(45) then 22o < 𝜃 < 45o. When VEf > VRd,max(45) the section must be increased, or a
higher concrete strength chosen.
8|Page
𝐴𝑠𝑤 0.78𝑑𝑓𝑦𝑘 𝑐𝑜𝑡𝜃
Spacing of the links , s, is calculated from s =
𝑉𝐸𝑑
157 𝑥 0.78 𝑥 1300 𝑥 410 𝑥 2.5
s = = 219.55mm.
743.25 𝑥 1000
Provide 4legs Y10mm at 425mm c/c as links.
𝐴𝑠𝑤,𝑚𝑖𝑛 0.5
0.08𝑓𝑐𝑘
= 𝑏𝑤
𝑠 𝑓𝑦𝑘
783.25
Y10mm @ 300mm c/c links. 2 x Y10mm @ 425mm c/c 702.625 Y10mm @ 300mm c/c links.
Vmin VEd
links. Vmin 290.625 210.00
12.52
65.00 98.75
102.605
592.605
703.85
The middle band, around gridline 3, is where the calculated shear links is required (as shown). Outside this band the
shearing force is less than 543.927kN., hence, the minimum shear links of Y10mm @ 300mm will be used.
9|Page
APPENDIX
10 | P a g e