Question No.1

A team member from research and development tells you that her work is too creative to provide you
with a fixed single estimate for the activity duration . You came across three different duration (hrs.)
values describing pessimistic, most likely and optimistic values i.e., a) 47 (b) 27 (c) 14 respectively.
You both decide to use a three-point estimation technique. Answer the following questions. Also
compare outcomes of both triangular and beta distribution estimates. (10) (CLO2)

a) Expected activity duration.


b) Standard deviation
c) Range of estimate