MONTHLY SAFETY STATISTICS REPORT- DEPOT PEB (CA-141)

REPORT FOR MONTH ENDING:DECEMBER -2023


Project Name – MMRDA MUMBAI METRO NEXT UPDATE DUE ON 1STFEB 2024
COMMENCEMENT DATE : 01/02/2021 SCHEDULED COMPLETION DATE: 30/09/2024

S No. ACCIDENT STATISTICS SUMMARY FOR MONTH CUMMULATIVE TARGET REMARK

1 MILLON AS
1 Nos. of Safe Man hours worked 51491 225236 INPROCESS
CUMULATIVE VALUE
2 Nos. of Safe Man day’s worked 4681 20476 NA NOT APPLICABLE

3 Nos. of Man hours worked 51491 225236 NA NOT APPLICABLE

4 Nos. of Man day’s worked 4681 20476 NA NOT APPLICABLE


5 Nos. of day’s worked 31 209 NA NOT APPLICABLE
6 Nos. of Reportable Fatal Accidents 0 0 ZERO ACHIEVED
ZERO FOR EVERY
7 Nos. of Reportable Non-Fatal Accidents 00 00 ACHIEVED
MONTH
ZERO FOR EVERY
8 Nos. of Non-Reportable Accidents(First Aid) 01 02 ACHIEVED
MONTH
ZERO FOR EVERY ACHIEVED
9 Nos. of Dangerous Occurrences 00 00
MONTH
10 Nos. of Man hours lost 00 00 NA NOT APPLICABLE

Nos. of Man day’s lost 00 00 NA NOT APPLICABLE


11

12 Nos. of Near Miss 0 0 0

Dangerous Occurrences Frequency Rate=


Nos. of work related Accident ×10,00,000 0 ACHIEVED
13 0
Total no of man hour worked

Accident Frequency Rate=


Nos. of work related injuries ×10,00,000 ACHIEVED
14 0 0
Total no of man hour worked
Severity rate =
Total No. of Man days lost Due To ACHIEVED
0 0
15 LTI×10,00,000
Total no of man hour worked
Incident Rate (IR) =
16 Total No of Accident × 1000 0 ACHIEVED
0
Total No. person employed
Average Nos. of Workers daily
17 Average Staff: - 16 151 847 NA NOT APPLICABLE
Average labour:- 135