WPD Quiz 7 on 09-Nov-2021 Total points 33/35

Marks: 35. Duration: 30 minutes.


CLO 2: Improve industrial work systems by using principles of work and process design.

The quiz comprises three sections: A, B, and C.


For each question, you have to choose one answer, unless specified otherwise.
The number of best answers are mentioned within parentheses for questions having more
than one best answers.

Best of Luck!

Email *

razamianali947@gmail.com

0 of 0 points

Roll Number and Name e.g. 01 Muhammad Asjid *

24-ALI RAZA TARIQ

Please enter password. *

wpd_quiz7

Section A 10 of 12 points

Some questions may have more than one best answers.

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 1/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

What is the formula to calculate capacity of a process? 1/1

Actual output / actual input

Available time / time utilized

Available time / demand

Available time / processing time

For a manufacturing system in which different tasks are performed in a 1/1


sequence e.g. an assembly line, the capacity of the line is equal to:

The capacity of the last operation

The capacity of the first operation

The process with the lowest capacity

The process with the highest capacity

How can the capacity of a process be increased? ( 2 best answers) 0/2

By reducing the cycle time of the process

By adding resources to the process

By increasing the waiting time for the process

By decreasing the utilization of the process

By increasing the steps of the process

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 2/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

The time required for a product to move all the way through a process or a value 1/1
stream from start to finish is called:

Takt time

Cycle time

Lead time

Up time

Number of products made in a unit time (e.g. an hour or a day) is called: 1/1

Utilization

Flow rate

Productivity

Inventory turnover

What is the formula to calculate utilization of a worker or a machine? 1/1

Time available / time utilized

Time available / cycle time

Time utilized / time available

Time utilized / time not utilized

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 3/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

Which of the following statements are true about the utilization of a resource 2/2
(labor or machine)? (2 best answers)

Utilization can never be greater than 100%

Increasing utilization will decrease productivity

Utilization will decrease if process is standardized

Utilization can be greater than 100%

Utilization can be increased by reducing idle time

Which of the following are bottleneck principles / characteristics? (3 best 3/3


answers)

The bottleneck operation has the lowest utilization

Bottleneck is always a process with changeover time

The capacity of the system depends on the capacity of the bottleneck

Time saved at a nonbottleneck saves the system nothing

Bottleneck should always be the last operation to improve

There can be more than one bottlenecks in the system

Section B 15 of 15 points

The questions in this section are based on the following statement:

There are three tasks performed in a line with the following cycle times (processing times):
Task 1: 2 minutes;
Task 2: 4 minutes;
Task 3: 5 minutes.
The tasks are labor-intensive with one worker at each task.

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 4/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

How long does it take the process (in minutes) to produce 50 units starting with 3/3
an empty system?

550 minutes

256 minutes

261 minutes

211 minutes

200 minutes

What is the capacity of each task in units / hr? 3/3

Task 1: 15; Task 2: 30; Task 3: 20

Task 1: 12; Task 2: 15; Task 3: 30

Task 1: 30; Task 2: 15; Task 3: 12

Task 1: 30; Task 2: 12; Task 3: 15

If the wage rate is 100 rupees / hr for each worker, what is the cost of direct 3/3
labor in rupees / unit?

Rs. 30 / unit

Rs. 15 / unit

Rs. 25 / unit

Rs. 20 / unit

Rs. 35 / unit

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 5/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

If another (4th) worker is to be added to the line, to which task should he be 2/2
added?

Task 3

Task 1

Task 2

What will be the minimum manufacturing lead time (flow time) of the part in the 1/1
system?

2 minutes

4 minutes

5 minutes

11 minutes

What can we expect if each task produces at the pace of the bottleneck task i.e. 3/3
we want to avoid inventory between tasks? (3 best answers)

The line will balance automatically

Utilization of task 1 will be about half of task 2

Task 3 will have the highest utilization

Task 2 will have the highest idle time

Task 1 will have the lowest utilization

Task 3 will have the highest idle time

Section C 8 of 8 points

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 6/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

The questions in this section are based on the following statement:

The Speedy Pizza Palace is revamping its order-processing and pizza-making procedures.
In order to deliver fresh pizza fast, six elements must be completed.

If the demand for pizzas is 120 per night (5:00 p.m. to 1:00 a.m.) during week 2/2
nights, what should be the cycle time, in minutes, to meet the demand?

3.75

3.5

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 7/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

What is the minimum number of workstations required to meet the demand? 2/2

If the demand increases to 200 pizzas on weekends, what will be the new 2/2
desired cycle time, in minutes, to meet the demand?

2.4

2.6

3.2

3.5

What is the minimum number of workstations required to meet the new 2/2
demand?

This content is neither created nor endorsed by Google. - Terms of Service - Privacy Policy

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 8/10
10/09/2023, 18:30 WPD Quiz 7 on 09-Nov-2021

Forms

https://docs.google.com/forms/d/e/1FAIpQLScohPqBX803wTj-TaLpj3HHfS9MPbY4mSxrEARVtgMhyXyvbQ/viewscore?vc=0&c=0&w=1&flr=0&views… 9/10