4th Quiz
Max time allowed is 20 mins
Please, answer all questions
Only one answer is correct per each question

Good Luck

mahmoud.kassab75@gmail.com Switch account


Not shared

* Indicates required question

First Name *

mahmoud

Family Name *

kassab

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 1/10
7/5/23, 11:43 AM 4th Quiz

SID *
Please, enter your student ID number

a00460292

A project has the precedence requirements and activity durations shown in 2 points

the table. After he draws the network, the project manager decides that
activities B, C, and D can be represented by a hammock activity. What are
the early start and late finish times associated with this hammock activity?

11, 30

7, 24

11, 24

7, 36

Clear selection

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 2/10
7/5/23, 11:43 AM 4th Quiz

A project's duration can be reduced by: 2 points

shortening the duration of critical path tasks.

adding tasks to the critical path.

adding shorter routes around the critical path.

completing the backward pass first.

Clear selection

Which technique would accelerate the completion of a project? 2 points

hammocking

bursting

laddering

passing

Clear selection

In general, the better candidates for shortening are: 2 points

early tasks opposed to later tasks.

later tasks opposed to early tasks.

merge tasks opposed to burst tasks.

burst tasks opposed to merge tasks

Clear selection

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 3/10
7/5/23, 11:43 AM 4th Quiz

Activities A and B have a finish to finish relationship and early start and 2 points
finish times as shown. What is the result of incorporating a 4 day lag
between activities C and B?

The early finish for A increases to 31.

The early start time for A increases to 24.

The early finish time for B increases to 31.

The early start time for D falls to 23.

Clear selection

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 4/10
7/5/23, 11:43 AM 4th Quiz

What is the early start time for activity C if it has the start to start 2 points
relationship shown?

day 20

day 25

day 27

day 29

Clear selection

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 5/10
7/5/23, 11:43 AM 4th Quiz

Which statement about this Gantt chart is best? 2 points

Activity a has a duration that could be as short as 1 day and as long as 10.

Activity b probably has activity a as a predecessor.

No progress has been made on activity c.

Activity d is the longest activity.

Clear selection

The process of accelerating a project is referred to as: 1 point

streamlining.

expediting.

rushing.

crashing.

Clear selection

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 6/10
7/5/23, 11:43 AM 4th Quiz

Which of these approaches will NOT accelerate the completion of a project? 2 points

Improve the productivity of existing project resources.

Increase the bureaucratic oversight.

Improve the working method.

Increase the quantity of personnel and equipment.

Clear selection

A project has the activity duration and cost information indicated in the table 2 points
where all times are in weeks. What is the total cost for completing this
project in 50 weeks?

$253,000

$237,000

$216,000

$207,000

Clear selection

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 7/10
7/5/23, 11:43 AM 4th Quiz

The One Shovel Construction Company is hired by the City of Edmond to lay 2 points

sewer pipe from the east end of town to the west end of town. While the
crew would like to begin at both ends simultaneously and have a dramatic
ceremony when both ends meet, they find themselves with a bit of a:

time constraint.

resource constraint.

mixed constraint.

partial network.

Clear selection

Use the information in the table and assume that a worker is expected to 5 points
devote half-time (four hours per day) to this project with work taking place
on a 5-day-per-week basis. Which week has the highest resource usage?

week 6

week 2

week 4

week 3

Clear selection

Page 1 of 1

Submit Clear form

Never submit passwords through Google Forms.


https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 8/10
7/5/23, 11:43 AM 4th Quiz

This form was created inside of The American University in Cairo. Report Abuse

Forms

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 9/10
7/5/23, 11:43 AM 4th Quiz

https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 10/10