Professional Documents
Culture Documents
4th Quiz
Max time allowed is 20 mins
Please, answer all questions
Only one answer is correct per each question
Good Luck
First Name *
mahmoud
Family Name *
kassab
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 1/10
7/5/23, 11:43 AM 4th Quiz
SID *
Please, enter your student ID number
a00460292
A project has the precedence requirements and activity durations shown in 2 points
the table. After he draws the network, the project manager decides that
activities B, C, and D can be represented by a hammock activity. What are
the early start and late finish times associated with this hammock activity?
11, 30
7, 24
11, 24
7, 36
Clear selection
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 2/10
7/5/23, 11:43 AM 4th Quiz
Clear selection
hammocking
bursting
laddering
passing
Clear selection
Clear selection
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 3/10
7/5/23, 11:43 AM 4th Quiz
Activities A and B have a finish to finish relationship and early start and 2 points
finish times as shown. What is the result of incorporating a 4 day lag
between activities C and B?
Clear selection
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 4/10
7/5/23, 11:43 AM 4th Quiz
What is the early start time for activity C if it has the start to start 2 points
relationship shown?
day 20
day 25
day 27
day 29
Clear selection
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 5/10
7/5/23, 11:43 AM 4th Quiz
Activity a has a duration that could be as short as 1 day and as long as 10.
Clear selection
streamlining.
expediting.
rushing.
crashing.
Clear selection
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 6/10
7/5/23, 11:43 AM 4th Quiz
Which of these approaches will NOT accelerate the completion of a project? 2 points
Clear selection
A project has the activity duration and cost information indicated in the table 2 points
where all times are in weeks. What is the total cost for completing this
project in 50 weeks?
$253,000
$237,000
$216,000
$207,000
Clear selection
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 7/10
7/5/23, 11:43 AM 4th Quiz
The One Shovel Construction Company is hired by the City of Edmond to lay 2 points
sewer pipe from the east end of town to the west end of town. While the
crew would like to begin at both ends simultaneously and have a dramatic
ceremony when both ends meet, they find themselves with a bit of a:
time constraint.
resource constraint.
mixed constraint.
partial network.
Clear selection
Use the information in the table and assume that a worker is expected to 5 points
devote half-time (four hours per day) to this project with work taking place
on a 5-day-per-week basis. Which week has the highest resource usage?
week 6
week 2
week 4
week 3
Clear selection
Page 1 of 1
This form was created inside of The American University in Cairo. Report Abuse
Forms
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 9/10
7/5/23, 11:43 AM 4th Quiz
https://docs.google.com/forms/d/e/1FAIpQLSdpizClSNwKCPKHog5Slg_KZQ7-6rhW0SoopYoKRF3r4zdQSQ/viewform 10/10