0 ratings0% found this document useful (0 votes) 68 views66 pages❤️
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content,
claim it here.
Available Formats
Download as PDF or read online on Scribd
Construction
Techniques (III)
Structural Department
b=]
>
2
So
oat
Ss
o
>
=
+Bridge Construction
Main rule for the choice of the construction method:
The bridge should be constructed and / or erected with the most
reasonable method to minimize direct and indirect costs of
construction within required period of construction. The duration
of construction is important factor that should be optimized.
Criteria of choice:
I- Economic facilities Las JI ALG (3 525 gl
2~ Construction schedule ST Steg ojII Sgt plain!
3- Environmental aspects ¥J\ gle 43) Whee 815 yoy plee®)
Legal
Environmental.
The choice of the most suitable method of bridge
construction:
1- Max. span of the bridge and the total length,
2- The degree of occupation under the bridge.
3- The type of the bridge deck, e.g. concrete, steel, composite deck
4- The height of the bridge deck over the ground.
5- The condition of the traffic and public situation in the
surrounding region.Explain the main aspects for construction of bridge:
gp eciTscally: The construction should be completed safely without
any over-stressing and / or without any additional high residual
stresses of the bridge elements which could affect the design of
end bridge negatively.
ie, Construction should not govern the design of bridge different
structural elements.
Usa! le Rel) Slolan Ul) y35 Y a diols as Lyk WL! py
Aye! Sloe Yl ge
: Economically: yy , bridge should be constructed and/or erected
with the most reasonable method to minimize the direct and the
indirect costs of construction within required time as the duration
of construction is important factor that should be optimized.
“Sas Cy gel ody GUUS YBh Lb) Gay
¢ eeonmentally; The bridge construction shouldn't have
a negative influnce on the surrounding environment of the site
during construction.
Aland! Ball de gale Sb WS Gall 4b gS at
. Aesthetically, long period construction, the influnce of bridge
construction on the overall view in the surrounding region should
be considered.
Eaptally dyed! plod boa gle Quis) Ub 395 PoyDesigner main target and tasks:
1- Choose the most reasonable method for construction.
Las yt Lakel Lost ylast
2- Divide the construction method into stages.
+ dale A) Ql Te pb pp
3- Design each stage of construction stages and check stresses in
both formwork and in constructed elements at every stage.
Tome] Ge GholarZl 345 pac Go aSt ge UAB! Jota! pra pb
esd LSP UL! Las gf dina! Last go IS Gd Ly
4- Design the temporary elements if needed.
sed) Ra) wee LRU! LSP AGA) old prec
5- Determine the required equipment and devices for the
construction method.
I LST Ay plled) Slacwdly Sigs) was
6- Follow the progress of the construction.
BBS II QB) Joly deolDifferent methods of construction:
I- Cast in-situ technique on fixed or movable shuttering
supported on the ground.
|——_» Fixed shuttering over the whole length
|-——> Fixed shuttering supported on temporary columns
‘——+» Movable shuttering on movable columns
2- Precast technique.
[> Pre-cast beams and Cast in-situ slabs
|» Pre-cast beams and Pre-slabs
[> Pre-cast beams and Pre-cast slabs
|——-» Hybrid pre-cast technique
'__» Pre-cast segmental bridge
3- Deck push system for pre-cast concrete decks, steel decks and
composite decks.
4- Launching method using launching beams.
|——> Launching system with launching girder under the deck
|» Launching system with launching girder over the deck
‘———» Launching system for construction of pre-cast girders
5- Classic cantilever method.
+> Classic free cantilever method
'___» Classic free cantilever method with additional launching
beamsd- Cast in-Situ Technique:
A- Fixed shuttering over the whole length
BBS Ge GL Yo Gyo dal pos Agaee gf Add ab Go dle yo
AL Usiio cpg loaf gaer 9G SII Ge Egil! Me Yi Deck Ji
og) J883 Y yg Brac Go ogee gf Las UL oi of gf Ls sat!
Bad Uy) sey YL Deck Ii yo Jlol of
This system is suitable for small spans up to 30.0 m
Deck
Horizontal Wind bracing
x
Th
N
Dx
ING
7)
Dy
LT LINK
LEEELEN
43
Di
Ds
DD
De
Wind bracing in transverse direction
‘Max. spacing =3-6m
Vertical loads:
Vertical loads due to D.L., L.L., etc. will be carried by the verticals
then load transfer to the ground through the P.C. foundation.
Horizontal toads:
Hz. loads due to wind mainly will be carried by the diagonal
members then loads transfer to verticals then to the ground.) (Transverse bracing )
Vertical Wind bracing
in longitudinal directionB- Fixed shuttering supported on temporary columns
Basel gle Gyo G9Gy Space truss Asse. 55 We 3a Ye Le ye
ported Se tyeS ge Bree Yl Sy Ladd gf UL yi LB ys)
JO Go gg! Me 45. Space truss yc 3)le Temporary column
EAbES Go Gye! Leiaglie Gy pS! Sree! GLS} ue, YL Deck 435 ps
Deck 33335 835) Jom
Deck Deck Truss girder
| ON Za
———
Temporary Truss girder| Pier_
‘support
Temporary cablesin\//”
longitudinal direction Temporary column
Temporary cables in
transverse direction
Vertical loads:
Vertical loads due to D.L., L.L., etc. will be carried by the piers
and the temporary columns then transfered to the ground.
Horizontal loads:
Hz. loads due to wind mainly will be carried by the temporary col.
but in most cases the temporary columns can be stabilised by
temporary cables to carry the hz. loads in the longitudinal direction
and sometimes we can use temporary cables in transverse directionC- Movable shuttering on movable columns
GL Eg he gy29Il Bree ole HGyo 4G TBaee dad Ye Tbe ve
gost) Los! Agee guy Leo yates Temporary column J\ 55S 5Ss
- This system is suitable for large spans greater than 30.0 m
- Short time construction high construction rate
id
ex ><
bY Pg
by RJ
Xx] bd
Movable column
Deck
Movable shuttering
——_—»
| Direction of
‘movement
scaeamaes2- Pre - Cast Technique:
Main advantages of application of pre-cast technique:
1- Reduction of construction formwork.
2- Reduction of construction duration.
3- Production of concrete with high quality (high performance
ie. high strength, modulus of elasticity and high durability )
A- Pre-cast beams and Cast in-situ slabs
G29 pl pS Sac gle pie Pre-cast 2) SI) 5555 Uz, bI) ode 5
Oy de WU Shear connectors plariul giz. Glo) Ges Uy! 305
Gob Se BS Gf ALI Qo JLo JH Yo 3H, Lb!
Shear connectors J\
Cast in-situ slab ve RFT of beam Cast in-situ slab
shear connectors Pre-cast beam
Shear connectors
Shear flow gle Lnayaad phy
Section A-A
Pre-cast beamB- Pre-cast beams and Pre-slabs
Ay Mab gl} ALI! paid ping Pre-cast SI 59% Li bil ode
Abd! ode pasidy LWW tye Jt palit! ly, Pre-cast 55 6-8 cm
Pre-cast ALi ja da N\ pizg Azle! BEML ALI! Wl Go 18S
Che OS Gob Oe pied) oS Used! Gloss
Pre-slab t na= 6-8 cm
Reinforced with the positive
reinforcement of the deck
Cast in-situ slab
ve RFT of slab Rough surface to Supporting area |,
| Pe RET of beam’ fo maintain bond for pre-slab Cast in-situ slab
ison
ears h oo ag Fee sora] [t= 25-30em
\ Pre-slab tmae= 6-8 cm |
Reinforced with the positive
reinforcement of the deckC- Pre-cast beams and Pre-cast slabs
Abo! cue py GIy Pre-cast ALY Sly By Go WS GSS Lill ode 5
Overlap loop & shear connectors plaxss\ ping gy! 3 pain
3 gl] LLY! Go Jitsy JLo gigi Say WL,
ve RET of beam Cast in-situ joint Anchorage RFT for slabs
30-40,cm
= |
Z 4 LA,
2-3cm |
‘Supporting area Pre-cast slab
‘for pre-cast stab Shear connectors
Pre-cast beam
|
RFT loops are '
‘staggered in plan |
‘Staggered in plan
The force movement in RFT between the two pre-cast spans
i
THT a7, ision Sion
RE wee tj Tiana wee
i} } I Comp. in
Ca tu concrete,
Pre-cast slab ‘concrete
Tension force in RFT
Ls, Compression confining concrete
L_, Tension in RFT on other sideD- Hybrid pre-cast technique
Pre-cast J\ plasiol, 4B) Go Abbie ely pladtel py LE bIl ode GS
Pre-cast beams and Cast in-situ slabs <——
Pre-cast beams and Pre-slabs <——_
Pre-cast beams and Pre-cast slabs <——
Hybrid pre-cast
4
LL
Cast in-situ slab
Pre-cast beam
\ precepts
Cast in-situ joint Pre-cast beam
! \ |
i |
Cast in-situ
‘foundation
E- Pre-cast segmental bridge
This system is suitable for spans 50 - 80 m and area under the
bridge is not accessible e.g. (water or deep valley )
oh LS Gy 9S 155 phy
1- Divide the bridge into segments 5 - 10 m each. Each segment
is to be casted in workshop or in site.
ode Lik pis 5-10 mals 55h5 SEYMENIS 55255) apoB pL
Pre-cast \o,lamt sf g3gul gd OW ll
2- Using the launching or cantilever method, the bridge segments
are to be lifted and erected into its position.
plidiol Lily GWeldl S55 Edy ee
Launching system or cantilever method D>3- The successive erection of the bridge segments is to be carried
out mutually with the prestressing of the proper erected
segment into the previous erected one.
Prestressing cable p\oxwol, LaxS 3 63 GU) OWS gl) by Le IN py
4- Progressive erection of the bridge segments lead to a full
construction of the bridge spans. At the end the final
prestressing cables are to be stressed.
Prestressing cable J\ a
GUS gl) Guam Ley sey
1 -aoalalsb aalolals]se
Phase I Phase II Phase HI
NOTES
I ged GIS GLU! ys Pre-cast segmental bridge p\a>i0\ pz
Box Section \ac\bi Tae wu
Segment ae Segment
@ 8
Segments J) 2.2%
Dry ‘Joints which contains multiple of non-1 reinforced shear key:Prestressing J) Jac pix segments J) S95 £13) glg2) Ur yall gf
Segments Iter) (32 Box Seay eld Gate 63 pins
Straight Prestressing cables peel qe
! aE tee PEt
A
feel on Io
Phase I Phase IT Phase IT
Straight Prestressing cables
Zero Eccentricity
Section (A-A)
Prestressing J\ Joc px segments J\ 553 acy 48) Us pd! 65
Bending Moment J\ JS% jk
Cc
{-T-+---] {-4---f{-
“tt et PE
«+
IC
Prestressing
Cables — Eos
Prestressins
Cables
Section (B-B) Section (C-C)
Box Section ¢\b3 J>\o Lsls Prestressing Cables 3) 53 ps‘3- Deck Push System:
- This system is suitable for spans up to 60 - 70 m.
- Additional temporary columns could be needed during the
pushing of the deck.
- This method could be the most economical method for
construction of composite sections.
- The deck structures is to be designed for the resulting internal
forces (B.M. & S.F.) during the pushing process due to the
change of the statical system of the deck.
- The piers and the temporary columns are to be designed for the
vertical loads and the resulting horizontal loads due to friction
during the movement of the bridge.
pe 6 ed Ss Deck os lye! ao pe SUSY pb! Me
py Steel nose tys04 BS plasiol Piers 5525S) bree) ple LS 05
AST GRY Us ye Ge GS ALBY! plbI! pe SWhy G2 Tl Lele,
Stage 1:
- Supporting of the starting pier and preparation works for
casting the first segment
Steel cantilever beam (Steel nose )
Segment length Nose length
erent ne . | Mechnical push system
7
Strut or Cables ~
‘o resist pushing force 7
BMD.
R (ae aeStage 2:
- Pushing of the deck
- Preparation for casting the second segment
(Steet nose)
Ry
|-— Steet nose—-|
L_ Bridge deck—-|
Stage 3:
- Finishing of the third segment
- Pushing the system to be placed over the temporary column
- Preparation for casting segment 4
(Steel nose) Temporary column
(ees Or
7 > > ; Temporary cables
AN
» A> _IN
Ie BP.
Ry Ro R;
| Bridge deck—}-— steel nose—-|
Deck 33290) pase 9 Piers 53290) baech gy Woes! b9S of aoe
Piers ssc°\ gle Steel nose eh j>%; 72.3 io Hinged ConnectionVertical load
Temporary columns:
ECP OLET COLITIS: Friction load = 0.05 V,
Temporary columns are to be designed on
|—» Vertical loads ( max. reaction of deck ) Wind load
——+ Friction force = 5% of vertical force
(to simulate the friction bet. the deck and the bracing )
'___» Wind loads ( carried by temporary cables in transverse
and longitudinal direction )
Statical system of temporary columns
Statical system in case Statical system in case
without temporary cables with temporary cables4- Launching System:
- This system is suitable for spans 30 - 70 m if the area under the
deck is not accessible.
- Launching beam during construction should be designed to
carry all loads of the deck during construction.
- Piers are to be designed for the summation of the reaction
forces from the deck and launching system.
- Wind load on the launching beam in additional to wind load
on the deck should be carried by the piers.
- For decks with small height and spans up to 40 m and
a material delivery over the deck, the cast in-situ technique is
reasonable method using launching girder under the deck.
- For very high decks over ground > 30 m and spans > 60 m
the application of the pre-cast segmental bridge deck with
launching girder over the deck is an optimum choice.
Using launching girder Using launching girder
under the deck over the deck
1- Small heights, 1- Very high decks.
2- Span up to 40 m. 2- Span more than 60 m.
3- Using cast in-situ technique 3- Using pre-cast segmental
may be better. bridge.
4- Material delivery over the deck.A- Launching system with launching girder under deck
Stage 1:
Hardened concrete Formwork Carrier
WAVAN SIRI DAD
hae]
Section A-A
Hardened part _ Segment to be casted
B.M.D. in the deck Gee caeee
= iL /s E75
Pier
a; a
W= wt. of the next segment Py { z B+P
Launching beam P= wt. of lifted parts
Due to the own weight of
The launching beam only,
Reactions of launching
beam on piersStage 2:
=—=———— (Winch)
; 5
eriined COR Next segment to be casted Carrier
Yl ASK BE
2 sino RAZA
Direction of movement of taumching beam
WML
Not yet hardened
B.M.D. in the deck
TIT,
He we of the next segment
WILLA TIS TT TNL LI
a
ip aue to Carrier
Reactions of taunching
‘beam on piersB- Launching system with launching girder over the deck
Stage 1:
- The launching girder is supported on bridge piers.
- Winches which are mounted on the launching truss girder
are used to lift the bridge segments.
- The segments are to be fixed into the completed part.
Prestressing cables are to be stressed.
L
Own wt. of launching beam
| Pier 1
wind
Vy = 5 iv ic
Wpy= wt. of one segment V =wt. of vertical steel
(Ty
P v _ i, Roving B.MD. in launching girder
7 2
> My
B.M.D. in the deck
B.M.D. in pierStage 2:
- Supporting of the launching girder to the casted part.
- Lifting the segments of the pier.
- Successive erection of the deck segments.
Segments
‘of piers
_| Pier 1 Pier 2 Supported
B.M.D. in the deckStage 3:
- Propelling of the launching girder to be supported on the
deck and pier.
- Successive erection of the deck segments.
| Pier 2
wind Own wt. of launching beam
le OETA ATLL
v v
Wy Vv
wing BMD. in launching girder
B.M.D. in the deck
wind on column =W,=Cxqxb, BMD. in pier 2C- Launching system for construction of pre-cast girders
Stage 1:
- Supporting the launching girder over the deck and the pier
Launching truss girder
B.M.D. in launching girder
Own wt. of launching beam
Launching beam J
wind on column = W.=C x qx b,Stage
- Lifting of full scale pre-cast beam
As A
B.M.D. in launching girder =
Own we of launching beam
Launching beam
B.M.D. in deck
wind on column = W. =C x qx b,Stage 3:
- Placing of the pre-cast beam
B.M.D. in launching girder
TOA] Deck Reing
We
B.M.D. in deck
wind on column = W, =C %q be5- Classic cantilever method:
- This system is suitable for concrete bridges with spans up to
70 - 200 m where the area under the deck is not accessible.
- It is used for construction of cable stayed bridge with spans
250 - 1000 m.
- Itis used for construction of arch bridges over navigational
channels or high valleys.
A- Classic free cantilever method
The following rules should be applied:
1- The joint between deck and pier should be a rigid joint.
2- The length of the starting segment is equal or greater than the
width of the pier.
3- The construction progress should be performed on both sides
simultaneously to reduce the transferred bending into erection
piers. ;
4- The weight of the winches should be taken into consideration
during the erection of the bridge segments. Therefore an
additional counter weight can be placed at the other side to
reduce the uplift forces which should be carried by the deck.
5- The capacity of the lifting carriage depends on the max. weight
of the lifted bridge segments.
GEAdditional Carrier
to reduce the uplift forces
a i
PK
Ry i]
phere | Eerie | na. lifted weight
7 vam
B.M.D. due to vertical loads
forcase Le pig > Letp
The joint between deck and pier should be a rigid joint (Fixed Joint).
Segments Jax)
~
h
~
3h -e[2|ifaise
Rigid Joint,
Phase I Phase IT Phase ITB- Classic free cantilever method with additional launching beam
In this system we use additional launching steel girder over the
deck, This girder helps in material transport and segment lifting
and in some cases it can be used in supporting the erection
carriage of the cantilever method.
Stage 1:
- Cantilevering of bridge deck from pier 1 and pier 2.
~ The launching steel beam helps in material lifting and
segments lifting.
Length of segments ranges
wen Se Tom
he
fee een
Winches
PIV IVI VIII
Launching girder
We. of segment
ert
BE oe
] ). in Pier 1
B.M.D. in Pier 2 B.M.D. in PierStage 2:
- Just before closing the first intermediate span of the deck.
WITT
oA
Pier 3 Pier 2 eae
B.M.D. in launching girder
Nora
cD
B.M.D. in the deck
Pier 2 Pier 1
Stage 3:
- Cantilevering from pier 2 and pier 3.
Pier 3 Pier 2 eee
Sl B.M.D. in launching girder
E oar
B.M.D. in the deck
WT
ole aad g
Pier 3 Pier 2 aaFixed shuttering over
Fixed shuttering
Movable shuttering
the whole length
on temporary col.
on movable columns
J- Span up to 30 m.
2- Area under bridge \\2- Area under bridge
is accessible,
3- Temporary columns
are used if span
1- Span up to 60 m.
is accessible.
- Span more than 30 m.
)- Area under bridge
is accessible.
'- Short time
construction high rate.
greater than 30 m.
Deck Push System
1- Span up to 60 - 70m.
2- Temporary columns are used
if span greater than 30 m.
3- More economic for composite
sections.
Using launching girder
under the deck
I- Small heights.
2- Span up to 40 m.
3- Using cast in-situ technique
may be better.
4- Material delivery over the deck.
Classic Cantilever method
1- Span up to 200 m.
2- For cable stayed bridges.
3- For arch bridges.
4- Very high decks.
Using launching girder
over the deck
1- Very high decks.
2- Span more than 60 m.
3- Using pre-cast segmental
bridge.Example (1):
For the following bridge systems, choose the most suitable technique
for the construction of each bridge deck and explain why. Show some
of the construction stages and draw each stage with diagrammatic
sketches, the main internal forces (e.g. B.M.D.) in both structural
elements of construction equipment and in the bridge deck.
Bridge 1: Pre-stressed Concrete Bridge with a box section
(The area under the deck is not accessible )
+4
AY HWL. ta om
> =
Le ed ett
30.0 mr=-—— 40.0 m | 46.0 m =| 40.0 m=} 50.0 m= 30.0 =|
-&—— 120-——__4
20
4
Section A-A
Bridge 2: ;
Bridge 2: Composite Bridge Deck
(Only temporary columns are allowed )
+4
ta
4
300m 50.0 m——-|-— 50.0 nr F 50.0. —-— 50.0 ar ; F "50.0 mr=|
k cee
2.40
‘Section A-A |Bridge 3: caste stayed Bridge with approaches
Note: Differentiate between the consruction technique in main
and approach spans
[ Area is not accessible
Area is not accessible Yj 73.0
fom som, 120m 300m 120m _ 40m, 40m, fom,
Approaches Main bridge 1. Approaches __,
Concrete Deck Composite Deck structure _1_ Concrete Deck _,Bridge 1: Pre-stressed Concrete Bridge with a box section
( The area under the deck is not accessible )
Sa
30.0 mr---— 40.0 m——}-— 46.0 m-—-}>— 40.0 m——-|-—— 50.0 m= 30.0 mr-|
2m
—» Using Segmental precast units erected using launching girder
over the deck
As the area under the deck isn't accessible and the cross section of the
bridge using prestressed concrete enables the usage of precast segments.
We erect this segments using the launching girder over the deck. As the
span is less than 70 m we can use this construction technique.
Stage
DIT IITS
Winches A gq V
+}-——— 30.0 » ——_—+|
wind Own wt. of launching beam
ind Rene THEO
My = we of one segment V =wt of vertical steel
ST Ld t 7 B.M.D. in launching girder
2
Wp
copiaSegments
“of piers
R;
Wp wt. of pier segment
BMD. in the deck
_[Pier 2
Own wt. of launching beam
TUL
M.D. it
B.M.D. in the deck
EyBridge 2: Composite Bridge Deck
( Only temporary columns are allowed )
300m
+ 30.0 ar} 50.0 m——-}-—- 50.0 mm} 50.0 m=} 50.0 m= 30.0 ta
—> Using Deck Push system
As this method is much more economical method for composite sections
with big heights over the ground. It will be more economical to use
Shorter steel nose as temporary columns are allowed. In this system we
will push the still section and then concrete stab will be casted in-situ.
Stage 1:
4
50.0 m1 —}—— 50.0 21 =} 50.9 tr -— 50.0 m—} 30.0 mb
ae BMD.
co
1 30.0m -— 50.0 m-—}-— 50.0 m——-}-— 50.0 mn——-— 50.0 m=} 30.0 m b=
an BMD.Stage 3:
Cd “
aN BMD.
Ars
cee tere
Stage 4:
[e
cy
aN Ads
Nae —- A BMD.
SEA,
ca
at NN
Stage 6:
E E
Aas Ads A. BMD.
ss soo 4 So iaLE Joly BYE of Gey poy C2 STs ele! gue py bay ¥Bridge 3: Cable Stayed Bridge with approaches
Note: Differentiate between the consruction technique in main
and approach spans
Area is not accessible
Area is not accessible 730
Y
40m 40m, 120m 300m 120m _,40m, 40m, 40m
Approaches ,_ Main bridge Approaches
Concrete Deck _ Composite Deck structure 1. Concrete Deck _,
— For approaches: Using Cast in-situ launching under the deck
For Main bridge: Using Classic cantilever method.
For approaches as area is not accessible and span = 40 m and small
height, that is why using launching under the deck is the best system
For main bridge as it is cable stayed bridge, cantilever method is the
required technique.
Q
\JFor approaches
Stage 1:
a (Winch)
Hardened concrete Formwork, Carrier
om
Hardened part _ Segment to be casted
Lifting carriage
B.M.D. in the deck
op bie ohn
eae
We wt ofthe next segment Fi i BR PtP
Launching beam 1 p= ws. of lifted parts
M=Pxa
Due to the own weight of B= M/a
1 1
‘ihe Taunching beam only
BMD. in launching girder
Reactions of launching
‘beam on piersFor main bridge
Stage I:
Erection of steel tower
Steet Tower
Approaches constructed
Using Cast in-situ
launching under the deck
Stage 2: Erection of Cables
Steel Tower
Approaches constructed Cables
Using Cast in-situ
Jaunching under the deck
FADE
Stage 3:
Finishing Erection of Cables
Steel Tower
Cables
Approaches constructed
Using Cast in-situ WZ
launching under the deg
8] 6i4{ 2s [Ts [7 Po
‘Bridge deck =Example (2):
Indicate if the following statements is right (A) or is wrong (X)
1- Assuming the fulfillment of the technical safety during construction
of a bridge, the aesthetical aspect is the most important aspect for the
choice of the construction technique. (X )
Correct
Assuming the fulfillment of the technical safety during construction
of a bridge, the economical aspect is the most important aspect for the
choice of the construction technique.
2- Over-stressing and residual stresses of the different structural elements
of the end bridge should be avoided during the construction of the
bridge. (v-)
3- For bridge construction in Egypt, the deck push system is the most
frequent used technique. (X )
Correct
For bridge construction in Egypt, the fixed shuttering system is the
most frequent used technique.
4- Wooden shuttering is the much more durable than metal shuttering.(X )
Correct
Metal shuttering is the much more durable than wooden shuttering.
5- For the construction of a cable stayed bridge the launching method is
the most suitable method. (X)
Correct
For the construction of a cable stayed bridge the cantilever method is
the most suitable method.
6- For the application of the deck push system, the connection between.
deck and piers must be hinged. (v~) oe7- The pre-slab technique can be adapted with a max. spacing between
longitudinal beams of 6 m. (X)
Correct
The pre-slab technique can be adapted with a max. spacing between
longitudinal beams of 3 m.
8- Launching method with truss girder over the deck level can be
combined with the pre-cast technique to construct segmental concrete
bridges with spans up to 60 m over very high valley. (v~)
9- If the area under the bridge location is not available to arrange
shuttering during the construction of bridges with spans ranges
between 30 and 60 m, the cantilever method is the most suitable
technique to be adapted. (X)
Correct
If the area under the bridge location is not available to arrange
Shuttering during the construction of bridges with spans ranges
between 30 and 60 m, the launching under the deck method is the
most suitable technique to be adapted.
10- For construction of a composite deck of a bridge with a height of 30 m
over the water level and spans up to 50 m, the push deck system is
an alternative, which could be adapted. (X )
Correct
For construction of a composite deck of a bridge with a height of 30m
over the water level and spans up to 50 m, the launching over the deck
system is an alternative, which could be adapted.
I1- Pre-cast technique is the most suitable method for construction of
bridges with steel decks and spans up to 30m. (X)
ooCorrect
Deck Push System is the most suitable method for construction of
bridges with steel decks and spans up to 30 m.
12- The construction rate of high concrete towers using climbing (jumping)
forms is faster than the use of the slip forms, {(X)
Correct
The construction rate of high concrete towers using slip forms is
Saster than the use of the climbing forms.
43- During the deck pushing, the produced friction forces between the deck
and piers are close to be zero. (X )
Correct
During the deck pushing, the produced friction forces between the deck
and piers must be considered in design.
14- The use of additional beams (aids beams )with the launching systent
reduces the internal forces in the deck during the construction. (v~)
15~- During the construction of a bridge using the classic cantilever method,
the influnce of the wind load can be neglected. (X)
Correct
During the deck pushing, the produced friction forces between the deck
the influnce of the wind load can not be neglected.Example (3):
For the following bridge system, a fixed wooden shuttering on the
whole length of the bridge was chosen for the construction of each
bridge span. For all the shuttering elements, Calculate the design
Sorces using the simplified method, Design the different structural
elements of the shuttering system.
X- Girder
(300 1200)
Deck each 5m
} -——10.
: 1 O30 REE 12
Be a a ~~ 371 | i x a SC iT
g \ |
S
ee * __ —___ = eee = : = ees eae _ J
Xu
3 1 | t ; i
: fi
| (eS te err ee dd
L q 1 y i
' 6 x 2.50 = 15.00 m ' 250-5. 00 —~=2.50-}
Elevation (Longitudinal bracing ) (Transverse bracing )
I Vertical Wind bracing
AH in transverse direction
a
i
H
}\ Horizontal Wind bracing
4x 2.50 = 10.00 m
I) \ Vertical Wind bracing
in longitudinal directionGiven:
¢ For Wood
- Allowable strength in bending and tension (F,) = 72 kg/cm’
- Allowable strength in compression (Fy ) = 56 kg/eut”
- Allowable shear strength (F,)=14 kg/eu’
- Available dimension of wood elements 8 x 8, 10x10, 12x12 cm
* Live load = 100 kg/m?
¢ Wind load
- Pressure intensity of wind (q )=70 kg/m?
- Drag factor for deck (c ) = 1.50
- Drag factor for shuttering (c ) = 2.00Solution:
Vertical member:
[Pp rota Ppx.+ Pry + P. wind]
. Span
No. of X-girder = Spacing ==
Weight of X-girder = No. of X-girders*L xb x(t - t,)* Se
Weight of X-girder = 3% 10 x 0,3 x(1.2- 0.3) *2.5 =20.25 t
Own weight = wt. of slab + wt of main beams + wt. of X-girders’
Area
_ 15 X10 x 0.3 2,54 215% OMX (1.2 = 0.3) *2.5 + 20.25
= 15x10
= 1.065t/m?
frome
—> Pp, = 1.065 2.52.5 = 6.661
Pry =0.1%2.5%2,5 = 0625 t
To get P wing we have to catculate the
forces on the horizontal & vertical
bracing
sb i235 3. Vertical memberg3 CL) Ge A230! ysl] Gls pb
gS Aas yl iyeg Transverse direction 2 y0J\ e363 cyl
Longitudinal direction (3) jb) ol23¥) 3 CLI
ZT>
al
Bote
Roc oeSeb
SESSA
Resesry
SS
S
SOSA wind in Longieu
Wind in Transvers SS] LP Wind in Longitudinal
direction CS direction CEHorizontal bracing:
a- Wind in transverse direction
g PIX PP = je _ ih?
XX, SH SRSatspr
DXDDAXD DX! isepesepel
6 x 2.50 = 15.00 m 250-500} 2.50-4
(Transverse bracing )
Plan
Ww,
wi
Chol Ge AAS gH) Glan gp Mind
ina = CX Q XH
SS
bracing UV guise JS aie W vind Py
Waa Le
For level (1) y
W vwind= Cdeck * 1 *M deck (iY
duction fac
+ Csnuttering * 1 * 1 shuttering * aeaed Gal
= 150.07 *1.2 + 2.0*0.07* 1,5 * 0.3 = 0.189 tm
Assume reduction factor for voided area = 0.3 - 0.5 if not given
For level (2)
Wein
= 2.00.07 3.0 X 0.3 = 0.126 Um
Cyutering * 1 *H shuttering * teduction factor for voided area
>
©For level (3)
Wy Cstuuttering xqXx 4 shuttering X reduction factor for voided area
wind
= 2.0% 0.07% 2.25 x 0.3 = 0.0945 ttm
—» Solve for bigger value of Niying which is on level I
M50 750
a : Note:
& is the angle between the
member and the loaded side
Design ier. direction (Hz. direction)
2 2
id= 0.665 WE = 0.665
2
SE = 1.329 i ‘i :
g ‘Max, reaction transverse vertical bracing (T.V.B.)
is to be designed at this location
0.375 wL
= 0.532 ‘eee wwe tee
'
There is 2 braced panels
0.375 wL a
= 0.532 0.625 w L= 0.886
Max. force in diagonais
Omax.
(Fiagonal max.) = 3H sin ox
\ Na. of bracing panels
No. of diagonals There is 2 diagonals
0.886
(Fiagonal max.) = 3X3 x sin G5 = 9-313 t
Foi .
a Pige amas = 6.513 % 1000 = 5.593 cm?
» —& Use8x8em (Ag, 9= 64cm?) CLEThe design of the vertical bracing in transverse direction is to be
carried out at the bracing resisting the max. reaction from the
horizontal bracing i.e. transverse bracing no. 2
For transverse wind bracing (2)
There is 2 braced panels
n=2
nie Ry = 17726 emery
y
i
La B126 _ '
RyX pp = L772 Gig = L181 t |
i
q
1
i
1
SED. Design members ceca gag ae
= tan 5 = 59.04°
Note:
& is the angle between the
member and the loaded side
direction (VI. direction) p
3.839 Ry = Ry Gea 1.772 2S =0.8861 >Max. force in diagonals
(Fiagonal max.) = Fy sin we ~Fu2x sins9.04 = 1-119 t
No. of diagonals” \ No. of bracing panels
— ~Poiagonat max. _ 1.119 x 1000 _
. F, ~ 56
A m7 = 19.986 cm?
— > Use &x8em (Agyg= 640m”)
Vertical member | PSO
L
Pyina =F diagonal max. * COSC [
— Py
=1.119 x cos 59.04 =0.576t eemmen- eennee
= tan 3 = 59,04°
oeb- Wind in longitudinal direction
Deck
2g
TS Bracing dt Tevet Cl) S77 FSS bsp fe tS
: LS
= i
g i
8) haa mat Salmo * lhawae
i
$ i ne | {2.50
3 1
P | 50 V e225
“| |WoS> me det
i racing i evel (3 1
i 6 x 2.50 = 15.00 m
Hoi
DL
LL
oo
Ds
Ls
Wind = 4 * A circunsference * Friction factor
deck
= (10 x2 +2*0.3+4*0.9) X15 = 363 m?
A circumference
Wing = 0.07 * 363% 0.03 = 0.762
deck
Wing = og = 0.0241 Umi
deck
the shuttering supports one third of
the wind load on the deck in
longitudinal direction
eg giyball oleS¥t Gd Chol Ge GSW JLo 1/3 AyS5I) I Jans
LsLs Gye cel le Slot 23 p55 LewAssume Friction factor = 0.025 ~ 0.03 if not given
W,
= Cn uttering * 1 * "shuttering * Teduction factor for voided area
‘wind
shutterinj
"= 2.0% 0.07% 1.5 X0.3 = 0.063 /m*
W, = Wing + Woing = 0.025 + 0.063 = 0.0885 tm
wind deck shuttering
For level (2)
W, a Csuttering * 1 * 1 shutering * teduction factor for voided area
= 2.0% 0.07 *3.0 x 0.3 = 0.126 Unt
For level (3)
Ys nd Csnuttering * Y * "shuttering * Teduction factor for voided area
= 2.0% 0.07% 2.25 * 0.3 = 0.0945 tm
—» Solve for bigger value of Wyying which is on level 2
W,= 0.126 Um There is 3 braced panels
COO
( eeppeeenaees cceereemanaal|
0.5w L =0.63 0.5w L =0.63
Choy! Jal ye ll shear J\ 4% U35 Hz. diagonal J practi py
cht Jlol ge QW! shear J\ 5 J3l Longitudinal direction 3
Transverse direction 33
There is 2 diagonalsDX
LOLS
LEY
LLLLLY
DX
There is 3 braced panels
=3
5 0.0885 ”
7 9.63% F706
0.443 Pi See =
= 0,443 t 4 fi
\ 1
7 Ry = 0.63t—r ike aS ee
= W3 0.0945
15416 Rs Ra% 7, ~ 863% 7 176 _ {eS
= O473t y i
S.F.D. Design members Nee
S 25 =
= tan -5- = 59.04°
Max. force in diagonals Ona te
(Froiagonat max.) ="2n sincx ~2x3xsin59.04 =O3¢t
No. of diagonals, \ Na of bracing panels
a Eggat ns. = 25 x1000 _ 5.366 cm?
—» Use 8x8em (As, 3= 64m)
EESVertical member J PO
Ph
Prind =F Diagonat max. * COSC
Longitudinal [>
=0.3x cos 59.04 =0.154t cae
& = tan 23 = 59,04°
25
Design of vertical elements
—» Take Pring the max. of P wind transverse & P wind tongitudinal
Prot = Por. + Prr. + Pwina
Transverse
= 6.66 + 0.625 + 0.576 = 7.861t
— Prot _ 7.861% 1000 _ 2
Ae Fe ee 40.375 cm
—* Use 12x 120m (Aj41)= 144 cm?)
Design of horizontal members
1- Dead load
[J
a 50-
—» Assume 10x 10cm S wood = 500 kg/m?
Own weight = Bx t x Swooa
= 0.10 x 0.10 « 0.5 = 0.005 ttm
2
M, = 0.005x *:5— = 0.0039 mt
©2- Settlement of support
— > take5 =0.5cm
E =90x10 kg/m? & =~ L = 500.em to
F 3
= BE _ 100x109" _ 933 om! La
1, Lv
3
= eX 50) _,. By = 14.3942 keg
48 90x 10° x 833
& TF Seton Sport
x5
R,
M, = 0? = 0.018 mat 280 —f 2590 —§,
Pa
= ;
NOTE ee
Assume allowable settlement = 0.5 cm if not given
Pq
4 Moment due to settlement
Mz
2 = 0.009 mt
2 My = 7** 20.018 me
oes Moment due to dead load
M, M, = 0.0039 mt
Sec): M, + M,
M;
Sec.(2): M, + 3*
I
0 + 0.018 =0.018 mt take
8 | bigger
0.0039 + 9918 = 9.9129 ms} "88
U
Design moment = 0.018 mt
EeNormal force due to wind
N =1.772 t (max. reaction from both longitudinal and transverse
direction )
a
Normal force due to wind
Normal force due to wind
in transverse direction
in longitudinal direction
Check stresses of M & N
-_N Mxy
het Mee
=. 1.778 x10? 0.018 x10°x 5 _ 2
te=- 10? 333 28.24 kg/cm
<56 Safe
h-- 1.778 x10" , 0.018 x10°x 5
= 2
10? $33 =~ 6.916 kg/cm
<56 Safe
Check shear
Py = 0.0144t & = 0.005 Um
0.5 Req BxS
| = 2 pe
0 = fa 4 SxS _ 0014 0.005» 25 — 9.9134 1
2 2
3
q = 2310” 0.13 kglen?
<14 Safe EEExample (4):
For the construction of the following bridge, a steel truss system
was chosen to support the bridge deck during construction. The
supporting space truss system is supported on piers and temporary
steel truss column.
It's required to :
- Calculate the loads on longitudinal truss girder and caiculate
the internal forces in different structural elements on this truss.
Also calculate the maximum deflection of this truss during
construction stage.
- Calculate reaction and forces due to wind loads on the piers of
the bridge.
- For temporary columns, calculate loads and internal forces and
design the different structural elements for the following cases:
a- Without temporary supporting elements and the temporary
columns are connected horizontally into the deck.
b- With temporary cables connected into the top of the column
in longitudinal direction, and temporary columns are not
connected into the deck in transverse direction (design cables)
c- With temporary cables in both direction (design cables)
Design Data:
~ St. 37 for truss girder and temporary columns
~ St. 15700 for spiral cables, allowable tensile strength in bending
(CF, ) = 8000 kg/cm”
~ Live load = 100 kg/m?- Wind load
+ Pressure intensity of wind (q)= 70 kg/m?
° Drag factor for deck (c)=1.50
¢ Drag factor for shuttering (c)= 2.00
200
b--—-- 15,9 —_-}--_-— 159 ———-|
Bridge supporting system in longitudinal direction _ Cross section of bridge
{ ‘russ bridge
A
\
\
08
Cross section of the shutteringSolution:
Vertical loads
LLL. (given) = 100 kg/m? = 0.1 tn?
Wp1= Ax d
= (0.3 x (4546.0 + 2x 1.6))x 2.5 +
= 11.4 Ym
Wry, = 0.1% 8.0 =0.8 tm
Wi = Wort Wyi= 1140+ 0.8 =12.2 vm
There are three vertical trusses carrying this load
(P2EOIS x 2x25)
2
GE = 57.23 | YE = 57.23
R=125wL =765t
from each truss
Internal forces in truss members
Sec 1
M 114.47
C=T=y =F = I4E
San = 1.4 Hem?
A, = 24 = 68.14 cm? —» No need to choose section
ae)=1.4 Vem’ if not given
ll
Assume allowable steel strength (F,
Horizontal loads
a- Transverse direction
6.00 —~|
200-4
Weruitering
—>| ae Wind in Transverse
direction
Woina = Waeck + Wenuttering
= reduction factor
Woind = Caeck * 1% deck * Csumering * 1 *Wsutering * for voided area
= 1.50.07 *2.2 + 2.00.07 1.2 * 0.5 = 0.315 tin
N
|
Ryier = 1.89 t
Reenp = L2*O.315%15 = 5.671 op s67t
‘temp
Ryier = 0.4% 0.315 *15 = 1.89 t
‘pier
NOTE
Reactions can be calculated using 1.25wL and 0.375wL as before
Assume reduction factor for voided area = 0.3 - 0.5 if not givenb- Longitudinal direction
Wind in Longitudinal
direction
Weoina = Weer + Menutering
Ween = 9 * Acircumference * Friction factor
A circumference = (2 *8.0 +216) *30 = 576 m?
Wee = 0.07% 576% 0.025 = 1.01
Woaratering= © shuttering * 1 *Ashuttering * reduction factor for voided area
= 2.0*0.07x (1.2 4.5) X0.5 = 0.38 t
Wnt = 10 + 0.38 =1381
longitudinal
This load is resisted by 2 Piers and 1 temporary column (3 elements)
Woina Tesisted by each element = 438 = 0.46t
Total wind loads on pier ie
- Reactions are multiplied by 2 as calculated reactions is due half
bridge only
- Assume Friction factor = 0.025 - 0.03 if not given eePier
1.891)
Temp. Column
Pier
Loads on temporary columns
Case (a): No temporary cables and column is o.45. 229-5
connected horizontally into the deck
5 5.76
Vertical loads
The column is supporting 3 trusses Longitudinal
. direction
Ry =3%76.5 = 229.5t Transverse
direction a
NOTE eo Ke
Each load is transfered to no. of braced panels
zs
2 Peay M6 925
376 = 208,
576 = 28
OR
Vertical Longitudinal Transverse CE
direction direction directionWind loads in transverse direction
=Cxq* 4 x 0.5
\No. of bracing panels
= 2 x 007 x4 x 0,5 = 0.07 Umi
— 114.75 32.3
Nana = + G5 = 64.55 t
As= ES = 43.04 em?
Bay Qrnax. 3.58
Max. force in diagonals (F; ‘Diagonal max. )= WDsincx ~Ixsin66.03
No. of diagonals, =1.95t
195 _ NOTE
‘ =e 1.399 em? & is the angle between the
7 member and the loaded side
‘ax. force in Horizontal = Qing = 3.58 \Terri, (V1. direction)
4,= 332 = 2.557 em?
ind loads in longitudinal direction ees
b 0.23. 0.23
Wy = Cx qx * 0.5
= 2x0,07x-45 50.5 = 0.157 Ym 8 ho
_ ATS , 1015 _
Nae = 9 + 62.45 t 18 1015:
Z et
3 . 4 Sy x
2 of
t 14.0- 124 TA.
1 = 0.46 + 0,314 xP = 2.034 Teascx , R,
=Rr__ _ 2.038 T
T= cos CX cos 35.53 249 CO Pa
8
Ap= PEI 031 on?
—» Very smait vaiue use minimum
available cables
Case (c): Temporary cables in longitudinal and transverse direction
We designed temp. cables in logitudinal direction in previous step
876, R,
Toa { 7 N
- 4 ~
A! g Z \
i 7 N
. 4 ae
x 4 ~
8 “ N
7 sof~ N
R, = 5.76 + 014x402 = 6.461 [ROE
We designed temp. cables in
T= Ri ES 6.46 =7.46t longitudinal direction in previous
COS cos 30 : step
Ay= 746m 1000 0.93 cm? —» Very small value use 7.0)
min. available cable: G4)