KERJA-KERJA PEMBAIKAN KECIL DAN PENYELENGGARAAN KELAS, PUSAT

SUMBER DAN BILIK GURU SEKOLAH SK RASO

KADAR JUMLAH
BIL. HURAIAN UNIT KUANTITI HARGA (RM)
(RM) (BQ/KONTRAK)
1 KELAS TAHUN 1
a. Lampu Kalimantang unit 4 160.00 640.00
b. Kipas Syiling unit 4 580.00 2320.00
c. Soket Kuasa (Power Socket) unit 10 158.00 1580.00
d. Pintu unit 2 880.00 1760.00
e. Lantai L/S L/S 3500.00 3500.00

2 KELAS TAHUN 2
a. Lampu Kalimantang unit 6 160.00 960.00
b. Kipas Syiling unit 6 580.00 3480.00
c. Soket Kuasa (Power Socket) unit 12 158.00 1896.00
d. Pintu unit 2 880.00 1760.00
e. Lantai L/S L/S 3500.00 3500.00

3 PUSAT SUMBER SEKOLAH


a. Lampu Kalimantang unit 4 160.00 640.00
b. Kipas Syiling unit 4 580.00 2320.00
c. Soket Kuasa (Power Socket) unit 10 158.00 1580.00
d. Pintu unit 1 880.00 880.00
e. Lantai L/S L/S 3500.00 3500.00
f. Jubin Lantai (Floor Tile) L/S L/S 4850.00 4850.00

4 BANGUNAN BILIK GURU


Tingkap roovers di tukar kepada sliding
a. L/S L/S L/S 3850.00
window 1 set 4 daun, 2 set
Pasang plywood di atas tingkap berukuran
b. L/S L/S L/S 1950.00
(60' x 3')

Dinding yang masih ada papan 4' x 20' di


c. L/S L/S L/S 5980.00
ganti dengan dinding bata serta diplaster

d. Lantai L/S L/S L/S 3500.00


e. Jubin Lantai (Floor Tile) L/S L/S L/S 6800.00

Pendawaian semula (Pusat sumber, Tahun


5
1 dan Tahun 2)
L/S L/S L/S 8400.00
Cat bangunan (Pusat sumber, Tahun 1 dan
6
Tahun 2)
L/S L/S L/S 4354.00

JUMLAH KESELURUHAN 70,000.00