RENCANA ANGGARAN BIAYA

KEGIATAN : PT. SANJAYA MITRA MAKMUR


PEKERJAAN : RUMAH TYPE 45 EXCLUSIVE
LOKASI : KARANGBENDO BANYUWANGI
TAHUN : 2023

HARGA JUMLAH
NO. URAIAN PEKERJAAN Q'TY SAT SATUAN HARGA
(Rp) (Rp.)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
1. Bouwplank 1.00 Ls 500,000 500,000.00
500,000.00
II PEKERJAAN TANAH
1. Pek. Galian 11.33 m³ 70,000 792,750.00
2. Urugan pondasi + pemadatan 12.00 m³ 80,000 960,000.00
1,752,750.00

III PEKERJAAN PASANGAN


1. Pas. Batu Kali 25.20 m³ 500,000 12,600,000.00
2. Pas. Bata Merah 190.00 m² 100,000 19,000,000.00
3. Pas. Beton Sloof (Besi 10/6) 1.50 m³ 3,000,000 4,500,000.00
4. Pas. Beton Kolom (Besi 10/6) 1.30 m³ 3,000,000 3,900,000.00
5. Pas. Beton Balok Ring (Besi 8/6) 1.80 m³ 2,800,000 5,040,000.00
6. Pas. Beton Dak (Atap / Talang) Pakai Bondex 1.40 m³ 4,000,000 5,600,000.00
7. Pas. Beton Topian Teras Jendela 0.70 m³ 2,500,000 1,750,000.00
8 Pas. Beton Dak Septytank 0.20 m³ 2,000,000 400,000.00
52,790,000.00
IV PEKERJAAN KAYU + ATAP + PENGGANTUNG
1. Pas. Kusen ky 6/12 48.60 m¹ 70,000 3,402,000.00
2. Pas. Daun Pintu Doble Depan (Panel) 1.00 bh 1,300,000 1,300,000.00
3. Pas. Daun Pintu Single (Panel) 3.00 bh 700,000 2,100,000.00
4. Pas. Daun Pintu PVC 1.00 set 400,000 400,000.00
5. Pas. Daun Jendela Kaca Kamar 5mm 3.00 bh 300,000 900,000.00
6 Pas. Daun Jendela Kaca Dapur 5mm 1.00 bh 200,000 200,000.00
7 Pas. Jendela Kaca R. Tamu 5mm 1.00 bh 200,000 200,000.00
8 Pas. Kaca Jendela Atas Kaca 5mm 1.00 set 400,000 400,000.00
9 Pas. Handle + Kunci Pintu Utama 1.00 set 250,000 250,000.00
10 Pas. Handle + Kunci Pintu 3.00 set 120,000 360,000.00
11 Pas. Engsel Pintu & Jendela 10.00 set 50,000 500,000.00
12 Pas. Grendel Jendela + Kait Angin 3.00 set 30,000 90,000.00
13 Pek. Kap Baja Ringan 42.66 m² 120,000 5,119,200.00
14 Pas. Kalsiplank 26.60 m¹ 70,000 1,862,000.00
15 Pas. Genteng 52.14 m² 80,000 4,171,200.00
16 Pas. Genteng Bubungan 15.20 m¹ 50,000 760,000.00
22,014,400.00
V PEKERJAAN FINISHING
1 Plesteran + Acian 243.30 m² 35,000 8,515,500.00
2 Pas. Plafond Gypsum Rangka Hollow 58.23 m² 80,000 4,658,400.00
3 List Plafond 60.20 m¹ 15,000 903,000.00
4 Pas. Keramik Lantai 50x50 53.00 m² 125,000 6,625,000.00
5 Pas. Keramik Lantai Toilet 25x25 3.00 m² 110,000 330,000.00
6 Pas. Keramik Dinding KM/WC 14.00 m² 130,000 1,820,000.00
7 Pas. Keramik Dinding Depan Motif 3.74 m² 125,000 467,500.00
8 Pengecatan Dinding 243.30 m² 25,000 6,082,500.00
9 Pengecatan Plafond 58.23 m² 25,000 1,455,750.00
10 Pengecatan Atap Genteng 56.13 m² 30,000 1,683,900.00
11 Pengecatan Kayu (Kusen, Pintu, Jendela) 30.43 m² 50,000 1,521,500.00
32,541,550.00

Page 1 of 2
HARGA JUMLAH
NO. URAIAN PEKERJAAN Q'TY SAT SATUAN HARGA
(Rp) (Rp.)
1 2 3 4 5 6
VI PEKERJAAN SANITAIR
1 Pas. Pipa air kotor PVC 'D' 3"+ass 1.00 Set 200,000 200,000.00
2 Pas. Pipa air kotor PVC 'D' 2½"+ass 1.00 Set 300,000 300,000.00
3 Pas. Pipa Air Bersih PVC AW 1/2"+ass 1.00 Set 200,000 200,000.00
4 Pas. Kran air 1/2" 2.00 bh 30,000 60,000.00
5 Pas. Shower 1.00 bh 200,000 200,000.00
6 Pas. Zet Shower Kloset 1.00 bh 150,000 150,000.00
7 Pas. Kloset Duduk (Volk) 1.00 bh 1,500,000 1,500,000.00
8 Pek. Sumur Bor + Pipa 'D' 4" 1.00 ls 5,000,000 5,000,000.00
9 Mesin Pompo air 1.00 bh 650,000 650,000.00
10 Tandon Air 750 Liter 1.00 bh 1,250,000 1,250,000.00
9,510,000.00
VII PEKERJAAN INSTALASI LISTRIK
1 Titik Stop Kontak 7.00 Ttk 150,000 1,050,000.00
2 Titik Lampu 6.00 Ttk 200,000 1,200,000.00
3 Titik Lampu Downlight 3.00 Ttk 350,000 1,050,000.00
4 MCB 2 (1 Group) 1.00 Set 300,000 300,000.00
5 Biaya Pemasangan 2200 VA 1.00 Set 2,200,000 2,200,000.00
6 SLO 1.00 Unit 150,000 150,000.00
5,950,000.00

JUMLAH TOTAL (Rp) 125,058,700.00


DIBULATKAN (Rp) 125,000,000.00
Terbilang: (Seratus Dua Puluh Lima Juta Rupiah)
Banyuwangi, 14 Januari 2023
Dibuat oleh, Mengetahui,

Ach. Aliem R, A.Md. Edy Santoso


Perencana Direktur Utama/Owner

Page 2 of 2