Professional Documents
Culture Documents
PROJECT PROPOSAL
TO MINE
LIMESTONE
(CONSTRUCTION STONE)
AT
HAKIM GARA
October,2022
INTRODUCTION
The aim and purpose of this project is to get involved in the construction
sector of our region (Harar National Regional state) and nearby towns of
neighbour regions by providing construction stones such as masonry rocks,
gravels, chips and cobble stones . At this scope we have aimed to invest in
mining activities. The project will opens opportunity of employment and plays
active roles in the construction sector that our and neighbour regions demand
by providing construction and industrial stones.
The geology of Harar region is characterized by five litho logical units ranging in
age from Pre-Cambrian to Neogen, according to Greitzer (1961). These are,
from old young;
It is within this formation (Hamanlei) that the Hakim Gara Limestone deposit is
found. Detailed geological study has also divided the limestone into two units,
namely upper and lower limestone units.
The lower limestone unit covers the area extending from the foot of the gentle
slope exposing the upper limestone up to the road. It shows vertical variation
in which a layer of micritic limestone overlies intercalation of thick and thin
beds. The micritic limestone, having more than 50 cm unit bed thickness, is
very fine grained, light gray to white in colour, compact, massive and hard
whereas the intercalation is fine grained grey to light grey, and has beds that
are up to 1m thick.
The upper limestone unit, which is a calcarenite limestone occupies part of the
area forming a gentle slope and lies over the lower limestone unit. It has
colours ranging from light brown though grey to light grey and is fine to
medium grained. An individual bed thickness in this unit is commonly between
50cm to 1m. Occasional fossil structures of bivalves are also embedded in this
rock type.
The limestone covering the whole area has remained unaffected by large scale
tectioc structure such as faults and folds since its deposition. It is, however,
affected mainly by north-west trending joint set which are vertical to sub-
vertical and rarely by south—west trending joint set.
The concession area is situated where one of the best limestone formations is
found in abundance. In our survey we have made traverses that enabled us to
observe and study the outcrops carefully with an eye on the deposit required
due to the presence of pre-existing quarry at the site which was used to extract
by artisanal as well as small scale miners. Since our interest is the limestone
deposit, we will deal with this unit in brief.
This unit has about 20 meters thickness above the ground and is finely
grained, aphanetic, light grey massive, compact, and hard, there might be
micro and macro fossils and other secondary sedimentary units. Therefore, this
has been considered as meeting the standard requirement for production of
the desired construction and cobble stones that fulfil the market demand.
1.2.1 Location
The area of Hakim Gara quarry is about 10,000 m 2.The thickness of the lime
stone above the foot of the hill is about 20 meters. The limestone deposit is
expected to extend to the depth of greater than 10m.
Initial stage of mining is started with the drilling of a series of vertical and
horizontal holes from one end of the quarry to another along the deposit’s
strike (i.e. from north to south) by compressor. Chisels of tungsten carbide
with different sizes are inserted through the holes to be drilled and pressure is
exerted using hammers of big sizes to break the boulders or chips from the
parent rock. Breaking is to be carried out in such a way that the width and
height of boulders to be produced is not greater than 250 and 400mm
respectively to make easy detachment of the rock. The running of such
permanent trench and its step wise follow up wide range provides free
operational space for dump trucks, and other quarry machineries for the
smooth operation of the quarry activity.
The detached boulders or chips are then selected and further re shaped in a
desired size and shape by hand hammers manually. The pieces are further
selected and collected in one place using wheel barrows to make ready
available for loading. Finally the collected stones will be loaded on trucks by
labourers and transported to the market demand.
As the project to fully operational it is expected to produce 50m 3 per day that
means based on 300 working days it will be 15,000m3 per year.
The project is not reach full capacity operation in the initial year due to some
preparation. But it is fully operational starting from the second year up to the
project life.
Chapter 3
Resources requirement
The main raw materials to be used for the production and processing
limestone chips will be the massive rock form to be mined from Hakim Gara .
For this raw material the project will pay the government a royalty and tax
which has to be paid according to the Ethiopian mining proclamation from the
total sales revenue and taxable income respectively.
List of equipments required for the quarry activity is given in the table below.
1. Consultancy fee-------------------------------------------------------5,000
2. Road construction inside quarry---------------------------------10,000
3. Project promotion (license fee, land rent etc.)----------------3,000
Total--------------------------18,000
Fuel consumption-----------------------------------------------------132,000
Perdiem --------------------------------------------------------------------5,000
Environmental rehabilitation-----------------------------------------15,000
Total ------------------------157,000
CHAPTER 4
Environmental Aspects
Some parts of the project area are naturally covered by floras (small trees) so
that it will be necessary to use the excavator to clear the area with a minimum
environmental risk if the project is implemented. The quarry and stone
crushing plant sites are located at a considerable distance away from
settlement area and the existing infrastructures such as road, power lines, etc.
So the exposure of the locals to noise, vibration, dust and any other
environmental hazards resulting from the project operation is minimal. Dust
will be controlled if possible by frequently showering with water for the safety
of the workers as well as the society in relatively distant areas around the site.
For the purpose in the later case, water is available from the nearby source as
much as possible because there is no water source at the site.
Planting appropriate trees and other intervening vegetation, and assuring their
growth then will afforest the area at the end, according to the planned
environmental rehabilitation program. In order to protect workers from
personal injuries and damages to human life in the processes of quarrying and
stone crushing, appropriate protection measures such as providing safety
wears, including safety goggles, helmet etc. will properly be considered.
CHAPTER 5
5.1 Revenue
During the initial year of operation the mine may not attain the envisaged full,
capacity, mainly due to the preparation period which may extend through the
first six months, and to some extent due less gained technical experience, to
fully run the project. Hence capacity utilization in the first year is assumed to
the 50% of the annual production capacity that of the remaining years being
100%
The financial and profitability analysis of the project is due considering the
following assumptions.
Based on these assumptions and the data in the preceding sections, the
projects financial evolution, in terms of profit and loss statement, is presented
in the following table.
Description Year
1 Cash flow 0 1 2 3 4 5 6 7 8 9 10
A Pre- 18
production
cost
B Fixed cost 925
C Operating 499
cost
Total 1,442
2 Sales rvenue 1,500 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000 3,000
3 Rayality 45 90 90 90 90 90 90 90 90 90
(3%)
4 Depreciation 94.3 94.3 94.3 94.3 94.3 94.3 94.3 94.3 94.3 94.3
5 Operating 249.5 499 499 499 499 499 499 499 499 499
cost
6 Total cost 388.8 683.3 683.3 683.3 683.3 683.3 683.3 683.3 683.3 683.3
7 Taxable 1,111.2 2,316.7 2,316.7 2,316.7 2,316.7 2,316.7 2,316.7 2,316.7 2,316.7 2,316.7
income
8 Income tax 388.92 810.85 810.85 810.85 810.85 810.85 810.85 810.85 810.85 810.85
(35%)
9 Net profit 722.28 1,505.15 1,505.15 1,505.15 1,505.15 1,505.15 1,505.15 1,505.15 1,505.15 1,505.15
10 cash flow -943 -220.72 1,284.43 2,789.58 4,294.15 5,799.88 7,305.03 8,810.18 10,315.33 11,820.48 13,325.63
CHAPTER 6
About 1 kilometre rod will be constructed to provide all season access to the
quarry site. As the path leading to the area is muddy and water logged during
rainy season, this will contribute towards alleviating accessibility problems
existing in the area.
The project will also contribute to satisfying the demands of the ever-
increasing construction activates in and around Harar Town.
The project’s employee will benefit from salaries and wages. The revenue to
be generated from the project implementation will benefit the investor and
government, in the form of income from profit and income tax & royalty
payment respectively. The investor’s ten years cumulative earning from profit
is forecasted to be 13,325,630 birr, while that of the Government is 8,533,630
birr. The local community will also benefit from compensation made during the
project area land acquisition. The overall benefit goes to the economic
development of the country, in general.