Gammon Construction Limited Chadtech Site Reports and E-Mail list Wednesday, 10 January 2024

Days Close off /


Report NCR NCR Email Reports - Email Open date outstanding
Finish off Re-Inspection
Reply Comments
No: Rep. No; release Date sent Heading / Issue work date date
reply Date
Repairs required and reinspection
1 Report No; 01 RM15 - Gutter damage during transport 21-Aug-23 142.0 ( Report with photo of the repair works )
Rework and call for inspection
2 Report No; 02 RM04 - Serious gutter and cassette misalignment 28-Aug-23 Completed 10 January, 2024 Pending reply
( Report with photo of the repair works )
Rework and call for inspection
3 Report No; 03 RM04 - Gutter misalignments 22-Aug-23 Completed 10 January, 2024 Pending reply
( Report with photo of the repair works )
Rework the palette packing and fixings need to be all installed and tight
4 Report No; 04 RM15 - Gutter unsafe packing during transport 22-Aug-23 Completed 10 January, 2024 Pending reply
Improvement works have been carried out and inspected on 04 Sept. 2023
Rework and call for inspection
5 Report No; 05 RM09 - Cassette installation misalignments 22-Aug-23 141.0 Completed Pending reply
( Report with photo of the repair works )
RM04 - Cassette damage / misaligned / Rework and call for inspection
6 Report No; 06 23-Aug-23 Completed 10 January, 2024 Pending reply
Gutter misaligned ( Report with photo of the repair works )

7 Report No; 07 Damage cement boards to re[place Completed 10 January, 2024 Pending reply

Rework and call for inspection


8 Report No; 08 RM04 damage gutters 23-Aug-23 140.0 ( Report with photo of the repair works )
RM01 - Safe working zone and works off the roof Follow the approved M.S to the letter
9 Report No; 09 25-Aug-23 Completed Pending reply
for Fascia cladding Tool box meeting and M.S. has been implemented
RM04 - Over sized cassette joints Gutter is not safe and sitting on a 10mm edge
10 Report No; 10 26-Aug-23 Completed 10 January, 2024 Pending reply
and gutter safe support. ( Report with photo of the repair works )
Rework the palette packing and fixings need to be all installed and tight
11 Report No; 11 RM15 - Unsafe cassette packing 26-Aug-23 Completed Pending reply
Improvement works have been carried out and inspected on 04 Sept. 2023

GCL-NCR
12 Report No; 12 22-Dec RM04 - over sized holes on the stools 5-Sep-23 127.0 No action Rework the oversized cut holes and submit remedial proposal
3908-270
GCL-NCR Subject to Replacement works
13 Report No; 13 22-Dec RM08 - Facia cladding panel damage 9-Sep-23 123.0 ( Report with photo of the repair works )
3908-269 AA handover
GCL-NCR As build survey and remedial case
14 Report No; 14 22-Dec RM01 - End Cloud Bullnose wrong level and positioning 25-Sep-23 107.0 (Survey report required and remedial case.)
3908-268
Damage skylight to be reworked and inspected
15 Report No; 15 RM15 - Skylight Damage panels 26-Sep-23 106.0 ( Report with photo of the repair works )
GCL-NCR Repair and complete the assembly works
16 Report No; 16 22-Dec RM15 - Sump gutter damage and uncompleted works 27-Sep-23 105.0 ( Report with photo of the repair works )
3908-267
As build survey and remedial case
17 Report No; 17 RM01 - Feather Bullnose wrong level and positioning 29-Sep-23 103.0 ( Report with photo of the repair works )

GCL-NCR As build survey and remedial case


18 Report No; 18 22-Dec RM01 - End Cloud Bullnose wrong level and positioning 4-Oct-23 98.0 No action
(Survey report required and remedial case.)
3908-266
RM01 - South end Bullnose structural Remedial case and inspection for reworks
19 Report No; 19
fixing issues and wrong positioning
6-Oct-23 96.0 ( Report with photo of the repair works )
GCL-NCR Subject to Survey report and remedial case
20 Report No; 20 22-Dec RM01 - North end louvre frame wrong positioning level and location 12-Oct-23 90.0 No action
( Report with photo of the repair works )
3908-265 AA handover
RM01 - Fascia cladding panels misalignment
21 Report No; 21 13-Oct-23 Completed 10 January, 2024 Pending reply Re work and make safe
and temporary fixings not safe
GCL-NCR Subject to
22 21-Dec 17-Oct-23 RM08 - Fascia cladding panels damage 17-Oct-23 85.0 Replacement panels and inspection
3908-264 AA handover

23 17-Oct-23 RM01 - PVC and Smoke vent bottom interface 17-Oct-23 85.0 Completed Rework and follow all others the same

GCL-NCR RM01 - Skylight and Gutters structural fixing plated cut


24 21-Dec 17-Oct-23
and unacceptable for edge distance
17-Oct-23 85.0 Remedial case and inspection for reworks
3908-263

25 18-Oct-23 RM03 - Roof EPDM membrane short and unacceptable 18-Oct-23 84.0 Completed Rework / placement panels and inspection

26 18-Oct-23 RM02 - Roof EPDM membrane short and unacceptable 18-Oct-23 84.0 Completed Rework / placement panels and inspection

RM01 - PVC and Smoke vent bottom interface,


27 21-Oct-23
has repeated the same issues as 17-10-2023
21-Oct-23 81.0 Completed Rework and follow all others the same

RM01 -02 - 03 & 08 - Bullnose installation works Complete the works prior to bullnose installation or open all bottom access panels
28 21-Oct-23 21-Oct-23 Completed Pending reply
without the water test reported and signed off for the water membrane application and test approval

GCL-NCR RM05 - Dormer door cassette badly cut Rework / placement panels and inspection
29 21-Dec 01-Nov-23
and damage panels
1-Nov-23 70.0 ( Report with photo of the repair works )
3908-262
Gutter is not safe and sitting on a 10mm edge
30 01-Nov-23 RM05 - Gutter misalignment and serious damage 1-Nov-23 70.0 ( Report with photo of the repair works )
RM01 - Roof access door exit Smoke vents Absents of the Smoke vent bottom fixing is holding back water tightness and door fixing,
31 07-Nov-23
missing brackets North & south
7-Nov-23 64.0 No action
these works need to be expedite by 15/11/2023
RM02 - Roof Valley standing seans sheets are dangerous Replacement works and cutting of the excess length urgent.
32 07-Oct-23 7-Nov-23 Completed Pending reply
and replacement of damage sheets has not been done yet. Works have been completed and cut in Oct. 2023
GCL-NCR RM02 - Louvre frame and RM01 Louvre frame
33 20-Dec 07-Nov-23
are not mirror and need to be justified
7-Nov-23 64.0 Survey report and as build
3908-255
GCL-NCR RM05 - Roof cassette at Bay 1 are structurally
34 20-Dec 08-Nov-23 8-Nov-23 Completed 10 January, 2024 Pending reply Remedial case needs to be submitted and works inspected and approved by GCL
3908-254 inadequate for the numerous holes and excessive cutting
Work Subject to
35 08-Nov-23 RM02 - Roof valley metal sheets damage replacement 8-Nov-23 63.0 Replacement works and call for inspection , prior to proceeding
in progress AA handover
GCL-NCR RM01 - Skylight and Gutters structural fixing plated cut
36 20-Dec 08-Nov-23
and unacceptable for edge distance
8-Nov-23 63.0 Remedial case and inspection for reworks
3908-253
GCL-NCR
37 20-Dec 08-Nov-23 RM02 - Seriously damage roof cassette 8-Nov-23 63.0 Remove and repair works off site then installation for approval of repair work
3908-252
RM01 & RM02 - Temporary walk way and fall arrester Waiting M.S
38 09-Nov-23
system is inadequate and dose not follow any M..S
9-Nov-23 62.0 approval
The System must follow an approved M/.S and respect the installation method.

GCL-NCR All structural works need to be repair and remedial works submitted
39 20-Dec 10-Nov-23 RM01 - RM02 & RM03 - Skylight structural fixing issues 10-Nov-23 61.0 No action
for approval with calculations.
3908-251
GCL-NCR All skylights need to follow a designed grid line and fixed within the tolerance required,
40 11-Dec 10-Nov-23 RM01 - RM02 & RM03 - Skylight out of tolerance positioning copping issues 10-Nov-23 61.0 No action
any variation must be proposed/approved with inspection.
3908-250
RM14 - Roof cassette are seriously damage Reworks are require or removal from site with follow up inspection for approval
41 10-Nov-23
and repairs or replacement required
10-Nov-23 61.0 ( Report with photo of the repair works )
GCL-NCR RM02 & RM03 - End cloud bull nose are damage
42 11-Dec 10-Nov-23
and out of position for levels as well as gutter
10-Nov-23 61.0 As build survey and cladding / gutter repair replacements
3908-249
RM02 - Damage gutter covered with PVC membrane Works Assembly parts at the yard where loose
43 13-Nov-23
and loose sheet
13-Nov-23 58.0 in progress and site no one has fixed the bord before PVC welding works
Improved Packets can not be at multiple layers and need thicker packing
44 13-Nov-23 Bull nose RM02 over packing and not acceptable. 13-Nov-23 Pending reply
and completed if the gap is greater than 20mm
RM07 Skylight area is held back for a mistake from
45 13-Nov-23
C.T. Drawing and Stoll need to be replaced
13-Nov-23 58.0 Stool replacement from C.T. is required ASAP

RM14 Evening cassette installation has various units with big and serious mud stains
46 13-Nov-23 RM14 - Roof cassettes are seriously dirty and need to be cleaned 13-Nov-23 58.0 that need to be cleaned before installation
GCL-NCR RM08 and RM09 Vertical joints V gaskets falling / Subject to
47 11-Dec 14-Nov-23
protruding to vision area and can be a safety issue to public.
14-Nov-23 57.0 No action Falling / protruding V gaskets must be re-work and made safe
3908-248 AA handover
GCL-NCR
48 11-Dec 14-Nov-23 RM03 cassette vertical gap V gaskets protruding 14-Nov-23 57.0 No action Falling / protruding V gaskets must be re-work and made safe
3908-247

49 14-Nov-23 RM03 damage cassette at the ceiling level 14-Nov-23 57.0 Cassette has serious damage that needs to be repaired before ceiling works take place

50 14-Nov-23 RM08 damage cassette that need repairs 14-Nov-23 57.0 Cassette has serious damage that needs to be repaired before ceiling works take place

51 14-Nov-23 RM15 damage cassette that need repairs 14-Nov-23 57.0 Cassette has serious damage that needs to be repaired before ceiling works take place

52 14-Nov-23 RM08 damage cassette by others that need repairs 14-Nov-23 57.0 Cassette has serious damage that needs to be repaired before ceiling works take place

Subject to
53 14-Nov-23 RM08 & RM09 - Skylight fixings and issues 15-Nov-23 56.0 No action C.T. needs to follow up the structural and wrong doing issues a swell as the bad misalignments.
AA handover
GCL-NCR
54 11-Dec 15-Nov-23 RM03 serious dent of end cloud bull nose 15-Nov-23 56.0 C.T to repair or replace the cladding panel
3908-246

55 15-Nov-23 RM14 Damage cement boards and dirty cassette 15-Nov-23 56.0 C.T. to replace the broken boards and clean the ceiling

56 15-Nov-23 RM01 Completion of works and watertightness outstanding progress 15-Nov-23 56.0 No schedule C,T. is unable to complete the works with the acceptable quality standards

GCL-NCR
57 11-Dec 15-Nov-23 RM01 End cloud bull nose and cassette structural and uncomplete fixings 15-Nov-23 56.0 C,T. is unable to complete the works with the acceptable quality standards
3908-245
RM02 End cloud bullnose unacceptable installation manner,
58 21-Nov-23
by bracket removal on the roof cassette edge.
22-Nov-23 49.0 C.T. Needs to re-instate all brackets as per the Dwg

59 22-Nov-23 RM01 North skylight and gutter cladding works unacceptable 23-Nov-23 48.0 No schedule The provided cladding panels are defected and can not be used

GCL-NCR RM01 & RM02 End cloud bullnose and


60 11-Dec 22-Nov-23
roof cassette unacceptable installation works
23-Nov-23 48.0 No action C.T. needs to follow the approved ITP and fix back the structural fixings for the roof cassettes
3908-244
C.T. needs to remove the roof sheets are re-work the sheets with the proper curve and 40-45mm gap between
61 22-Nov-23 RM01 Roof standing seams unacceptable installation works 23-Nov-23 48.0 gutter and sheets.

62 23-Nov-23 RM14 & RM07 wrong units installed with different tag numbers 23-Nov-23 48.0 C.T. to change the traceability tag number of the wrongly installed units.

63 23-Nov-23 RM16a & RM18 wrong units installed with different tag numbers 23-Nov-23 48.0 C.T. to change the traceability tag number of the wrongly installed units.

64 25-Nov-23 RM08 Smoke vent bottom closer dose not follow the Dwg no insulation 25-Nov-23 46.0 C.T. to follow up works as the approved dwg all area to be re-work

65 25-Nov-23 RM09 & RM10 Skylight aliment issues 25-Nov-23 46.0 No action C.T. to follow up works as the ITP approved and come up with a proposal for the re-work

GCL-NCR C.T. needs to follow the approved method of cutting the bolts in height with a minimum of 3 treads exiting the nut
66 01-Dec 27-Nov-23 RM04 End cloud structural issues for cut bolts 27-Nov-23 44.0 No action
level when double note is tightened. Bolts to be replaced
3908-225
GCL-NCR
67 27-Nov-23 RM05 Cassette miss alignments unacceptable 27-Nov-23 44.0 C.T. Needs to adjust all the cassette within 1 day from the actual installation works ( Oct. )
3908-228
GCL-NCR
68 08-Dec 28-Nov-23 RM17a Gutter bolt fixing with structural defects 28-Nov-23 43.0 No action C.T. to follow up works as the ITP approved and come up with a proposal for the re-work
3908-229
GCL-NCR
69 08-Dec 28-Nov-23 RM06 Gutter bolt fixing with structural defects 28-Nov-23 43.0 No action C.T. to follow up works as the ITP approved and come up with a proposal for the re-work
3908-230
C.T. needs to follow a predesignated line for the alignment and avoid going back for adjustments and new hole
70 28-Nov-23 RM14 Gutters and Skylight must follow a straight line as normal practice 28-Nov-23 43.0 drilling works
GCL-NCR RM02 damage roof cassette has not been repair and C.T. to follow up works as the ITP approved and come up with a proposal for the re-work, with inspection for o
71 04-Dec 28-Nov-23
has cement boards hanging
28-Nov-23 43.0 No action
defects
3908-227
GCL-NCR
72 08-Dec 28-Nov-23 RM02 Unfished fixing and missing 30-Nov-23 41.0 No action C.T. to follow up works as the ITP approved and come up with a proposal for the re-work
3908-231

73 30-Nov-23 RM04-05-07 Dormer unfinished works of assembly 30-Nov-23 41.0 No action C.T. to complete the works at site and call for inspection of coemption of cement board and membrane

74 30-Nov-23 RM01-02-03 Non typical bullnose color deviation 30-Nov-23 41.0 C.T. to justify the acceptance or replace the cladding works.
GCL-NCR
75 11-Dec 30-Nov-23 RM03 bullnose unauthorized site cutting and modification works 30-Nov-23 41.0 C.T. to follow up works as the ITP approved and come up with a proposal for the re-work
3908-241

76 23-Nov-23 RM01 Skylight & Gutter cladding sample rejection 23-Nov-23 48.0 C.T. must replace the cladding as it has numerous stub bolt marks, even if it is only a sample

77 25-Nov-23 RM07 Cassette miss alignments unacceptable 25-Nov-23 46.0 C.T. Needs to adjust all the cassette within 1 day from the actual installation works

78 02-Dec-23 RM09 damaged Smoke vent panel SV10A to be replaced 2-Dec-23 39.0 C.T. to follow up replacement works

GCL-NCR Subject to
79 11-Dec 02-Dec-23 RM10 Skylight holes structurally inadequate 2-Dec-23 39.0 No action C.T. to follow up works as the ITP approved and come up with a proposal for the re-work
3908-242 AA handover
GCL-NCR
80 11-Dec 05-Dec-23 RM02 Louver frame fixings uncompleted 5-Dec-23 36.0 No action C.T, to completed the fixings ASAP on own cost and time
3908-243

81 09-Dec-23 RM01 -02-03 Wrong smoke vent connection box location query 9-Dec-23 32.0 C.T. to assist with DWG and assembly dwg to justify the random connection box at high level

Smoke vent wrong location of connection box Mark-up


82 12-Dec-23
RM01-2-3-4-5-7-8-9-10-15&16
12-Dec-23 29.0 C.T. to reply for the wrong doing or have a new DWG with explanation.

Subject to
83 18-Dec-23 RM04 Crystal skylight level or fabrication issue to clarify 18-Dec-23 Pending reply C.T. to check and confirm if the gutter has the wrong fabrication, replace or re-work
AA handover

84 18-Dec-23 RM05 Damage gutter cladding 18-Dec-23 23.0 C.T. to carryout the site repairs ASAP

C.T. to ensure that the tack screws fixing has the proper calculations and B.D. approval for inspections and fixing
85 Report No; 22 27-Dec-23 RM01 -02-03 smoke vent fixing connection/ tack screws and in-house testing 27-Dec-23 14.0 handover to A.A.

86 30-Dec-23 RM07 skylight installation alignment issues 30-Dec-23 11.0 C.T. to perform a better and acceptable alignment works during the actual installation

87 30-Dec-23 RM06 Gutters unacceptable installation status. 30-Dec-23 11.0 C.T. to perform a better and acceptable alignment works during the actual installation

88 Report No; 23 03-Jan-24 RM13 damage gutter in need of ceiling panels replacement 3-Jan-24 7.0 C.T. to carry out the site repairs best way possible and replace the ceiling panels

GCL-NCR C.T. to Rework/Replace steel stools if required, as well as a Remedial case supported by calculation.
89 05-Jan-24 RM10 Skylight holes and stool over cut and damage, structural integrity compromised. 5-Jan-24 5.0 No action
3908-271 Inspection will be required with records of before and after work.

C.T. to drill all holes required immediately and in future no gutters shall be installed if the fixing holes are not
90 08-Jan-24 RM11 gutters installed without drilled holes for the locking down plate 8-Jan-24 2.0 performed

Structural issues and NCR required to submit and close with documentation