ASSESSMENT 5 PART A PROJECT PROPOSAL - OVERALL ASSESSMENT WEIGHT 5/25

Performance - Scale
Criteria Aspects to be covered (weight)
85 -100 75 - 84 65 - 74 50 - 64 <49
Cover page complies with all requirements (1)
Well structured descriptions of each of the potential case projects that allows corss
referencing and comparison between projects (6)
A maximum of 5 highly relevant, specific, measurable, realistic, criteria that are clearly
enunciated (5)
Excellent rigour in the assessment of potential case project compliance with the criteria is
presented, based on credible sources and the final selcted project is identified and well
justified. (5)
Compliance with SOW
A Scope Statement that clearly identifies the expected outcome and the action, time & cost
requirements of the team project. (4)
A WBS for the final team project deliverables required for Assessment 5 Part B down to a work
package level. (4)

An initial schedule for the team project in the form of an AON diagram identifying
activity precedence and duration and showing sequencing of activities . (5)