You are on page 1of 83

DAFTAR ANALISA PEKERJAAN

XVI PEKERJAAN MEKANIKAL ELEKTRIKAL


HARGA BAHAN/UPAH JUMLAH XVI.1 1 Buah Lampu Gantung
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM Bahan
Rp Rp Rp Rp 1 Buah Lampu TL D 2 x 36 Watt Rp 185,000.00

I HARGA SATUAN PEKERJAAN PERSIAPAN Tenaga


0.15 OH Tukang Listrik Rp 85,000.00
I.1 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 1,803,669.65 2,030,239.94 0.015 OH Kepala Tukang Rp 90,000.00
A TENAGA 46,100.00 49,500.00
L.01 0.2 OH Pekerja 55,000.00 60,000.00 11,000.00 12,000.00 XVI.2 1 Buah Lampu SL 18 WATT
L.02 0.4 OH Tukang Kayu 80,000.00 85,000.00 32,000.00 34,000.00 Bahan
L.03 0.02 OH Kepala Tukang 75,000.00 85,000.00 1,500.00 1,700.00 1 Buah Lampu SL 18 WATT Rp 53,000.00
L.04 0.02 OH Mandor 80,000.00 90,000.00 1,600.00 1,800.00
B BAHAN 1,593,599.68 1,796,172.68 Tenaga
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 1,100,000.00 1,250,000.00 1,375,000.00 1,562,500.00 0.15 OH Tukang Listrik Rp 85,000.00
2.5 Kg Portalnd Semen 1,750.00 1,775.00 4,375.00 4,437.50 0.015 OH Kepala Tukang Rp 90,000.00
1.2 Lbr Seng Gelombang 3" - 5" 48,000.00 57,000.00 57,600.00 68,400.00
0.005 m3 Pasir Beton 250,000.00 270,000.00 1,250.00 1,350.00 XVI.3 1 Buah Lampu Baret + TL. Ring 32 W
0.009 m3 Koral Beton 520.00 575.00 4.68 5.18 Bahan
0.072 m3 Kayu 5/7X4m Kayu Kruing 2,050,000.00 2,100,000.00 147,600.00 151,200.00 1 Buah Lampu Baret + TL. Ring 32 W Rp 33,000.00
0.06 Kg Paku Biasa 2" - 5" 17,000.00 18,000.00 1,020.00 1,080.00
0.45 Kg Meni Besi 15,000.00 16,000.00 6,750.00 7,200.00 Tenaga
C PERALATAN 0.15 OH Tukang Listrik Rp 85,000.00
D Jumlah A + B + C 1,639,699.68 1,845,672.68 0.015 OH Kepala Tukang Rp 90,000.00
E Pekerja 10% 163,969.97 184,567.27
F Harga Satuan Pekerjaan (D+E) 1,803,669.65 2,030,239.94 XVI.4 1 Buah Lampu Pijar 40 W
Bahan
I.2 1 m' Pengukuran dan Pemasangan Bouwplank 84,359.00 93,236.00 1 Buah Lampu Pijar 40 W Rp 65,000.00
A Tenaga 14,650.00 15,800.00
L.01 0.1 OH Pekerja 55,000.00 60,000.00 5,500.00 6,000.00 Tenaga
L.02 0.1 OH Tukang Kayu 80,000.00 85,000.00 8,000.00 8,500.00 0.15 OH Tukang Listrik Rp 85,000.00
L.03 0.01 OH Kepala Tukang 75,000.00 85,000.00 750.00 850.00 0.015 OH Kepala Tukang Rp 90,000.00
L.04 0.005 OH Mandor 80,000.00 90,000.00 400.00 450.00
B Bahan 62,040.00 68,960.00 XVI.5 1 Buah TL 2 x 18W
0.012 m3 Kayu 5/7x 4m Kayu Kruing 2,050,000.00 2,100,000.00 24,600.00 25,200.00 Bahan
0.02 Kg Paku Biasa 2" - 5" 17,000.00 18,000.00 340.00 360.00 1 Buah TL 2 x 18W Rp 90,000.00
0.007 m3 Kayu Papan 3/20 Kruing 5,300,000.00 6,200,000.00 37,100.00 43,400.00
C PERALATAN Tenaga
D Jumlah A + B + C 76,690.00 84,760.00 0.15 OH Tukang Listrik Rp 85,000.00
E 0 10% 7,669.00 8,476.00 0.015 OH Kepala Tukang Rp 90,000.00
F Harga Satuan Pekerjaan (D+E) 84,359.00 93,236.00
XVI.6 1 Buah Lampu Exterior Sudut
I.3 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 2,557,277.80 2,823,151.38 Bahan
A Tenaga 376,500.00 405,000.00 Buah Lampu Exterior Sudut Rp 129,000.00
L.01 2 OH Pekerja 55,000.00 60,000.00 110,000.00 120,000.00 1
L.02 2 OH Tukang Kayu 80,000.00 85,000.00 160,000.00 170,000.00 Tenaga
L.02 1 OH Tukang Batu 80,000.00 85,000.00 80,000.00 85,000.00 0.15 OH Tukang Listrik Rp 85,000.00
L.03 0.3 OH Kepala Tukang 75,000.00 85,000.00 22,500.00 25,500.00 0.015 OH Kepala Tukang Rp 90,000.00
L.04 0.05 OH Mandor 80,000.00 90,000.00 4,000.00 4,500.00 XVI.7 1 Buah Saklar Tunggal
B Bahan 1,948,298.00 2,161,501.25 Bahan
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 1,100,000.00 1,250,000.00 1,375,000.00 1,562,500.00 1 Buah Saklar Tunggal Rp 15,000.00
0.18 m3 Kayu 2,050,000.00 2,100,000.00 369,000.00 378,000.00
0.85 Kg Paku Biasa 2" - 5" 17,000.00 18,000.00 14,450.00 15,300.00 Tenaga
1.1 Kg Besi Strip 13,700.00 14,200.00 15,070.00 15,620.00 0.15 OH Tukang Listrik Rp 85,000.00
35 Kg Portland Sement 1,750.00 1,775.00 61,250.00 62,125.00 0.015 OH Kepala Tukang Rp 90,000.00
0.15 m3 Pasir pasang 180,000.00 210,000.00 27,000.00 31,500.00
0.1 m3 Pasir Beton 250,000.00 270,000.00 25,000.00 27,000.00 XVI.8 1 Buah Saklar Ganda
0.15 m3 Koral Beton 520.00 575.00 78.00 86.25 Bahan
30 buah Batu bata Merah 520.00 575.00 15,600.00 17,250.00 1 Buah Saklar Tunggal Rp 15,000.00
0.25 Lbr Seng Plat 22,000.00 25,000.00 5,500.00 6,250.00
2 buah Jendela Naco 10,500.00 12,500.00 21,000.00 25,000.00 Tenaga
0.08 m2 Kaca Polos 60,000.00 64,000.00 4,800.00 5,120.00 0.15 OH Tukang Listrik Rp 85,000.00
0.15 buah Kunci Tanam 65,000.00 70,000.00 9,750.00 10,500.00 0.015 OH Kepala Tukang Rp 90,000.00
0.3 buah Engsel 4,000.00 4,500.00 1,200.00 1,350.00
0.06 Lbr Plywood 4 mm 60,000.00 65,000.00 3,600.00 3,900.00 XVI.9 1 Buah Stop Kontak
C PERALATAN Bahan
D Jumlah A + B + C 2,324,798.00 2,566,501.25 Buah Stop Kontak Rp 15,000.00
E 0 10% 232,479.80 256,650.13 1
F Harga Satuan Pekerjaan (D+E) 2,557,277.80 2,823,151.38 Tenaga
0.15 OH Tukang Listrik Rp 85,000.00
I.4 1 m2 Pembuatan Gudang Semen dan Peralatan 2,901,251.10 3,228,682.88 0.015 OH Kepala Tukang Rp 90,000.00
A Tenaga 234,000.00 251,500.00
L.01 1 OH Pekerja 55,000.00 60,000.00 55,000.00 60,000.00 XVII.1 1 Set Pompa Air 100 W
L.02 2 OH Tukang Kayu 80,000.00 85,000.00 160,000.00 170,000.00
L.03 0.2 OH Kepala Tukang 75,000.00 85,000.00 15,000.00 17,000.00
L.04 0.05 OH Mandor 80,000.00 90,000.00 4,000.00 4,500.00
B Bahan 2,403,501.00 2,683,666.25
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 1,100,000.00 1,250,000.00 1,870,000.00 2,125,000.00
0.21 m3 Kayu 2,050,000.00 2,100,000.00 430,500.00 441,000.00
0.3 Kg Paku Biasa 2" - 5" 17,000.00 18,000.00 5,100.00 5,400.00
10.5 Kg Portland Semen 1,750.00 1,775.00 18,375.00 18,637.50
0.03 m3 Pasir Beton 250,000.00 270,000.00 7,500.00 8,100.00
0.05 m3 Koral Beton 520.00 575.00 26.00 28.75
1.5 Lbr Seng Gelombang BJLS 32 48,000.00 57,000.00 72,000.00 85,500.00
C PERALATAN
D Jumlah A + B + C 2,637,501.00 2,935,166.25
E 0 10% 263,750.10 293,516.63
F Harga Satuan Pekerjaan (D+E) 2,901,251.10 3,228,682.88

I.5 1 m2 Membersihkan Lapangan dan Perataan 10,450.00 11,550.00


A Tenaga 9,500.00 10,500.00
L.01 0.1 OH Pekerja 55,000.00 60,000.00 5,500.00 6,000.00
L.04 0.05 OH Mandor 80,000.00 90,000.00 4,000.00 4,500.00
B Bahan
C PERALATAN
D Jumlah A + B + C 9,500.00 10,500.00
E 0 10% 950.00 1,050.00
F Harga Satuan Pekerjaan (D+E) 10,450.00 11,550.00

I.6 1 Ls Listrik Penerangan Proyek Rp 5,000,000.00

I.7 1 Ls Air Kerja & Air Minum Proyek Rp 5,000,000.00

I.8 1 Ls Papan Nama Proyek Rp 500,000.00

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. MINIMUM MAKSIMUM MINIMUM MAKSIMUM
URAIAN PEKERJAAN
Rp Rp Rp Rp
II HARGA SATUAN PEKERJAAN TANAH

II.1 1 m3 Menggali Tanah 47300 51562.5


A TENAGA 43000 46875
L.01 0.75 OH Pekerja 55000 60000 41250 45000
L.04 0.025 OH Mandor 70000 75000 1750 1875
B BAHAN
C PERALATAN
D Jumlah A + B + C 43000 46875
E Overhead & Profit (contah 10%) 4300 4687.5
F Harga Satuan Pekerjaan (D+E) 47300 51562.5

II.2 1 m3 Pengurugan Kembali 11,366.67 12,375.00

A TENAGA 31,000.00 33,750.00


L.01 0.50 OH Pekerja 55,000.00 60,000.00 27,500.00 30,000.00
L.04 0.050 OH Mandor 70,000.00 75,000.00 3,500.00 3,750.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 31,000.00 33,750.00
E Overhead & Profit (contah 1 10% 3,100.00 3,375.00
F Harga Satuan Pekerjaan (D+E) 34,100.00 37,125.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
III HARGA SATUAN PEKERJAAN PONDASI

III.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 707,058.00 786,126.00


A TENAGA 150,000.00 166,125.00
L.01 1.5 OH Pekerja 55,000.00 60,000.00 82,500.00 90,000.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 80,000.00 90,000.00 6,000.00 6,750.00
L.04 0.075 OH Mandor 70,000.00 75,000.00 5,250.00 5,625.00
B BAHAN 492,780.00 548,535.00
1.2 m3 Batu Belah 15/20 190,000.00 220,000.00 228,000.00 264,000.00
117 Kg Portland Sement 1,400.00 1,425.00 163,800.00 166,725.00
0.561 m3 Pasir Pasang 180,000.00 210,000.00 100,980.00 117,810.00
C PERALATAN
D Jumlah A + B + C 642,780.00 714,660.00
E Overhead & Profit (contoh 1 10% 64,278.00 71,466.00
F Harga Satuan Pekerjaan (D+E) 707,058.00 786,126.00

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
IV HARGA SATUAN PEKERJAAN PASANGAN DINDING

VI.1 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6 189,596.00 208,375.75
A Tenaga 51,700.00 56,950.00
L.01 0.6 OH Pekerja 55000 60000 33,000.00 36,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 80,000.00 85,000.00 1,600.00 1,700.00
L.04 0.03 OH Mandor 70,000.00 75,000.00 2,100.00 2,250.00
B Bahan 120,660.00 132,482.50
140 Buah Bata Merah 520 575 72,800.00 80,500.00
18.5 Kg Portland Semen (PC) 1,400.00 1,425.00 25,900.00 26,362.50
0.122 m3 Pasir Pasang (PP) 180,000.00 210,000.00 21,960.00 25,620.00
C PERALATAN
D Jumlah A + B + C 172360 189432.5
E Overhead & Profit (contoh 1 0.1 17,236.00 18,943.25
F Harga Satuan Pekerjaan (D+E) 189,596.00 208,375.75

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. MINIMUM MAKSIMUM MINIMUM MAKSIMUM
URAIAN PEKERJAAN Rp Rp Rp Rp
V HARGA SATUAN PEKERJAAN PLESTERAN
V.1 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 61,728.48 67,704.56
A Tenaga 40,140.00 44,350.00
L.01 0.400 OH Pekerja 55,000.00 60,000.00 22,000.00 24,000.00
L.02 0.200 OH Tukang batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.020 OH Kepala Tukang 80,000.00 85,000.00 1,600.00 1,700.00
L.04 0.022 OH Mandor 70,000.00 75,000.00 1,540.00 1,650.00
B Bahan 15,976.80 17,199.60
6.912 Kg Portland Semen 1,400.00 1,425.00 9,676.80 9,849.60
0.035 m3 Pasir Pasang 180,000.00 210,000.00 6,300.00 7,350.00
C PERALATAN
D Jumlah A + B + C 56,116.80 61,549.60
E Overhead & Profit (contoh 1 10% 5,611.68 6,154.96
F Harga Satuan Pekerjaan (D+E) 61,728.48 67,704.56

V.2 1 m2 Pemasangan Acian 27,005.00 29,404.38

Tenaga 20,000.00 22,100.00


L.01 0.20 OH Pekerja 55,000.00 60,000.00 11,000.00 12,000.00
L.02 0.10 OH Tukang batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 80,000.00 85,000.00 800.00 850.00
L.04 0.010 OH Mandor 70,000.00 75,000.00 700.00 750.00
Bahan 4,550.00 4,631.25
3.25 Kg Portland Semen 1,400.00 1,425.00 4,550.00 4,631.25
C PERALATAN
D Jumlah A + B + C 24,550.00 26,731.25
E Overhead & Profit (contoh 1 10% 2,455.00 2,673.13
F Harga Satuan Pekerjaan (D+E) 27,005.00 29,404.38
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VI HARGA SATUAN PEKERJAAN K A Y U
VI.1 1 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III 11173800 12227325
Tenaga 1845000 2074500
L.01 6 OH Pekerja 55000 60000 330000 360000
L.02 18 OH Tukang Kayu 75000 85000 1350000 1530000
L.03 1.8 OH Kepala Tukang 80000 90000 144000 162000
L.04 0.3 OH Mandor 70000 75000 21000 22500
Bahan 8313000 9041250
1.2 m3 Kayu Klas II (Kamfer) , Balok 6900000 7500000 8280000 9000000
1.25 kg Paku Biasa 2" - 5 " 12000 17000 15000 21250
1 kg Lem Kayu 18000 20000 18000 20000
C PERALATAN
D Jumlah A + B + C 10158000 11115750
E Overhead & Profit (contoh 10%) 1015800 1111575
F Harga Satuan Pekerjaan (D+E) 11173800 12227325

VI.2 1 m2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II 673,640.00 724,625.00
A Tenaga 307,500.00 345,750.00
L.01 1.00 OH Pekerja 55,000.00 60,000.00 55,000.00 60,000.00
L.02 3.00 OH Tukang Kayu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.30 OH Kepala Tukang 80,000.00 90,000.00 24,000.00 27,000.00
L.04 0.05 OH Mandor 70,000.00 75,000.00 3,500.00 3,750.00
B Bahan 304,900.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.050 kg Lem Kayu 18,000.00 20,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 612,400.00 658,750.00
E Overhead & Profit (contoh 1 10% 61,240.00 65,875.00
F Harga Satuan Pekerjaan (D+E) 673,640.00 724,625.00

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VII HARGA SATUAN PEKERJAAN B E T O N


VII.1 1 m3 pekerjaan beton footplat (K250) 1,073,851.72 1,152,003.31
A Tenaga 119,425.00 130,980.00
L.01 1.650 OH Pekerja 55,000.00 60,000.00 90,750.00 99,000.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 80,000.00 85,000.00 2,240.00 2,380.00
L.04 0.083 OH Mandor 70,000.00 75,000.00 5,810.00 6,225.00
B Bahan 856,803.84 916,295.74
384 Kg Portland Semen 1,400.00 1,425.00 537,600.00 547,200.00
692 Kg Pasir Beton 178.57 200.00 123,571.43 138,400.00
1,039 Kg Kerikil (maksimum 30 mm) 185.19 218.52 192,407.41 227,040.74
215 ltr Air 15.00 17.00 3,225.00 3,655.00
C PERALATAN
D Jumlah A + B + C 976,228.84 1,047,275.74
E Overhead & Profit (contoh 1 10% 97,622.88 104,727.57
F Harga Satuan Pekerjaan (D+E) 1,073,851.72 1,152,003.31

VII.2 1 m3 Pekerjaan Sloof (K225) 1,056,639.92 1,134,868.78


A Tenaga 119,425.00 130,980.00
L.01 1.650 OH Pekerja 55,000.00 60,000.00 90,750.00 99,000.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 80,000.00 85,000.00 2,240.00 2,380.00
L.04 0.083 OH Mandor 70,000.00 75,000.00 5,810.00 6,225.00
B Bahan 841,156.75 900,718.89
371 Kg Portland Semen 1,400.00 1,425.00 519,400.00 528,675.00
698 Kg Pasir Beton 178.57 200.00 124,642.86 139,600.00
1,047 Kg Kerikil (maksimum 30 mm) 185.19 218.52 193,888.89 228,788.89
215 ltr air 15.00 17.00 3,225.00 3,655.00
C PERALATAN
D Jumlah A + B + C 960,581.75 1,031,698.89
E Overhead & Profit (contoh 1 10% 96,058.17 103,169.89
F Harga Satuan Pekerjaan (D+E) 1,056,639.92 1,134,868.78

VII.3 1 m3 Pekerjaan Balok (K250) 1,073,851.72 1,152,003.31


A Tenaga 119,425.00 130,980.00
L.01 1.650 OH Pekerja 55,000.00 60,000.00 90,750.00 99,000.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 80,000.00 85,000.00 2,240.00 2,380.00
L.04 0.083 OH Mandor 70,000.00 75,000.00 5,810.00 6,225.00
B Bahan 856,803.84 916,295.74
384 Kg Portland Semen 1,400.00 1,425.00 537,600.00 547,200.00
692 Kg Pasir Beton 178.57 200.00 123,571.43 138,400.00
1,039 Kg Kerikil (maksimum 30 mm) 185.19 218.52 192,407.41 227,040.74
215 ltr air 15.00 17.00 3,225.00 3,655.00
C PERALATAN
D Jumlah A + B + C 976,228.84 1,047,275.74
E Overhead & Profit (contoh 1 10% 97,622.88 104,727.57
F Harga Satuan Pekerjaan (D+E) 1,073,851.72 1,152,003.31

VII.4 1 m3 Pekerjaan Kolom (K250) 1,073,851.72 1,152,003.31


A Tenaga 119,425.00 130,980.00
L.01 1.650 OH Pekerja 55,000.00 60,000.00 90,750.00 99,000.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 80,000.00 85,000.00 2,240.00 2,380.00
L.04 0.083 OH Mandor 70,000.00 75,000.00 5,810.00 6,225.00
B Bahan 856,803.84 916,295.74
384 Kg Portland Semen 1,400.00 1,425.00 537,600.00 547,200.00
692 Kg Pasir Beton 178.57 200.00 123,571.43 138,400.00
1,039 Kg Kerikil (maksimum 30 mm) 185.19 218.52 192,407.41 227,040.74
215 ltr air 15.00 17.00 3,225.00 3,655.00
C PERALATAN
D Jumlah A + B + C 976,228.84 1,047,275.74
E Overhead & Profit (contoh 1 10% 97,622.88 104,727.57
F Harga Satuan Pekerjaan (D+E) 1,073,851.72 1,152,003.31

VII.5 1 m3 Pekerjaan Plat Laantai (K225) 1,056,639.92 1,134,868.78


A Tenaga 119,425.00 130,980.00
L.01 1.650 OH Pekerja 55,000.00 60,000.00 90,750.00 99,000.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 80,000.00 85,000.00 2,240.00 2,380.00
L.04 0.083 OH Mandor 70,000.00 75,000.00 5,810.00 6,225.00
B Bahan 841,156.75 900,718.89
371 Kg Portland Semen 1,400.00 1,425.00 519,400.00 528,675.00
698 Kg Pasir Beton 178.57 200.00 124,642.86 139,600.00
1,047 Kg Kerikil (maksimum 30 mm) 185.19 218.52 193,888.89 228,788.89
215 ltr air 15.00 17.00 3,225.00 3,655.00
C PERALATAN
D Jumlah A + B + C 960,581.75 1,031,698.89
E Overhead & Profit (contoh 1 10% 96,058.17 103,169.89
F Harga Satuan Pekerjaan (D+E) 1,056,639.92 1,134,868.78

VII.6 1 m3 Pekerjaan Tangga (K225) 1,056,639.92 1,134,868.78


A Tenaga 119,425.00 130,980.00
L.01 1.650 OH Pekerja 55,000.00 60,000.00 90,750.00 99,000.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 80,000.00 85,000.00 2,240.00 2,380.00
L.04 0.083 OH Mandor 70,000.00 75,000.00 5,810.00 6,225.00
B Bahan 841,156.75 900,718.89
371 Kg Portland Semen 1,400.00 1,425.00 519,400.00 528,675.00
698 Kg Pasir Beton 178.57 200.00 124,642.86 139,600.00
1,047 Kg Kerikil (maksimum 30 mm) 185.19 218.52 193,888.89 228,788.89
215 ltr air 15.00 17.00 3,225.00 3,655.00
C PERALATAN
D Jumlah A + B + C 960,581.75 1,031,698.89
E Overhead & Profit (contoh 1 10% 96,058.17 103,169.89
F Harga Satuan Pekerjaan (D+E) 1,056,639.92 1,134,868.78

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VIII HARGA SATUAN PEKERJAAN PEMBESIAN


VIII.1 10 Kg Pembesian dg Besi Polos atau Besi Ulir 146,973.04 152,916.88
A Tenaga 111.86 115.35
L.01 0.07 OH Pekerja 1,400.00 1,425.00 98.00 99.75
L.02 0.07 OH Tukang Besi 178.57 200.00 12.50 14.00
L.03 0.007 OH Kepala Tukang 185.19 218.52 1.30 1.53
L.04 0.004 OH Mandor 15.00 17.00 0.06 0.07
B Bahan 133,500.00 138,900.00
10.50 Kg Besi Beton (polos/ulir) 12,500.00 13,000.00 131,250.00 136,500.00
0.150 Kg Kawat Beton 15,000.00 16,000.00 2,250.00 2,400.00
C PERALATAN
D URAIAN PEKERJAAN 133,611.86 139,015.35
E 0 10% 13,361.19 13,901.53
F Harga Satuan Pekerjaan (D+E) 146,973.04 152,916.88

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX HARGA SATUAN PEKERJAAN BEKISTING


IX.1 1 m2 Memasang Bekisting untuk Pondasi 139,150.00 153,516.00
A Tenaga 52,000.00 57,460.00
L.01 0.52 OH Pekerja 55,000.00 60,000.00 28,600.00 31,200.00
L.02 0.26 OH Tukang Kayu 75,000.00 85,000.00 19,500.00 22,100.00
L.03 0.026 OH Kepala Tukang 80,000.00 85,000.00 2,080.00 2,210.00
L.04 0.026 OH Mandor 70,000.00 75,000.00 1,820.00 1,950.00
B Bahan 74,500.00 82,100.00
0.04 m3 Kayu Klas III (Terentang) 1,750,000.00 1,900,000.00 70,000.00 76,000.00
0.3 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 3,600.00 5,100.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 126,500.00 139,560.00
E Overhead & Profit (contoh 1 10% 12,650.00 13,956.00
F Harga Satuan Pekerjaan (D+E) 139,150.00 153,516.00

IX.2 1 m2 Memasang Bekisting untuk Sloof 148,775.00 163,966.00


A Tenaga 52,000.00 57,460.00
L.01 0.52 OH Pekerja 55,000.00 60,000.00 28,600.00 31,200.00
L.02 0.26 OH Tukang Kayu 75,000.00 85,000.00 19,500.00 22,100.00
L.03 0.026 OH Kepala Tukang 80,000.00 85,000.00 2,080.00 2,210.00
L.04 0.026 OH Mandor 70,000.00 75,000.00 1,820.00 1,950.00
B Bahan 83,250.00 91,600.00
0.045 m3 Kayu Klas III (Terentang) 1,750,000.00 1,900,000.00 78,750.00 85,500.00
0.3 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 3,600.00 5,100.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 135,250.00 149,060.00
E Overhead & Profit (contoh 1 10% 13,525.00 14,906.00
F Harga Satuan Pekerjaan (D+E) 148,775.00 163,966.00

IX.3 1 m2 Memasang Bekisting untuk Kolom 356,510.00 400,378.00


A Tenaga 66,000.00 72,930.00
L.01 0.66 OH Pekerja 55,000.00 60,000.00 36,300.00 39,600.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 80,000.00 85,000.00 2,640.00 2,805.00
L.04 0.033 OH Mandor 70,000.00 75,000.00 2,310.00 2,475.00
B Bahan 258,100.00 291,050.00
0.04 m3 Kayu Klas III (Terentang) 1,750,000.00 1,900,000.00 70,000.00 76,000.00
0.4 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 4,800.00 6,800.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 5,000,000.00 5,800,000.00 75,000.00 87,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 135,000.00 38,500.00 47,250.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 34,000.00 36,000.00 68,000.00 72,000.00
C PERALATAN
D Jumlah A + B + C 324,100.00 363,980.00
E Overhead & Profit (contoh 1 10% 32,410.00 36,398.00
F Harga Satuan Pekerjaan (D+E) 356,510.00 400,378.00

IX.4 1 m2 Memasang Bekisting untuk Balok 373,010.00 419,518.00


A Tenaga 66,000.00 72,930.00
L.01 0.66 OH Pekerja 55,000.00 60,000.00 36,300.00 39,600.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 80,000.00 85,000.00 2,640.00 2,805.00
L.04 0.033 OH Mandor 70,000.00 75,000.00 2,310.00 2,475.00
B Bahan 273,100.00 308,450.00
0.04 m3 Kayu Klas III (Terentang) 1,750,000.00 1,900,000.00 70,000.00 76,000.00
0.4 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 4,800.00 6,800.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 5,000,000.00 5,800,000.00 90,000.00 104,400.00
0.35 Lbr Plywood tebal 9mm 110,000.00 135,000.00 38,500.00 47,250.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 34,000.00 36,000.00 68,000.00 72,000.00
C PERALATAN
D Jumlah A + B + C 339,100.00 381,380.00
E Overhead & Profit (contoh 1 10% 33,910.00 38,138.00
F Harga Satuan Pekerjaan (D+E) 373,010.00 419,518.00

IX.5 1 m2 Memasang Bekisting untuk Lantai 506,110.00 558,778.00


A Tenaga 66,000.00 72,930.00
L.01 0.66 OH Pekerja 55,000.00 60,000.00 36,300.00 39,600.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 80,000.00 85,000.00 2,640.00 2,805.00
L.04 0.033 OH Mandor 70,000.00 75,000.00 2,310.00 2,475.00
B Bahan 394,100.00 435,050.00
0.04 m3 Kayu Klas III (Terentang) 1,750,000.00 1,900,000.00 70,000.00 76,000.00
0.4 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 4,800.00 6,800.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 5,000,000.00 5,800,000.00 75,000.00 87,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 135,000.00 38,500.00 47,250.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 34,000.00 36,000.00 204,000.00 216,000.00
C PERALATAN
D Jumlah A + B + C 460,100.00 507,980.00
E Overhead & Profit (contoh 1 10% 46,010.00 50,798.00
F Harga Satuan Pekerjaan (D+E) 506,110.00 558,778.00

IX.6 1 m2 Memasang Bekisting untuk Tangga 336,765.00 378,928.00


A Tenaga 66,000.00 72,930.00
L.01 0.66 OH Pekerja 55,000.00 60,000.00 36,300.00 39,600.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 80,000.00 85,000.00 2,640.00 2,805.00
L.04 0.033 OH Mandor 70,000.00 75,000.00 2,310.00 2,475.00
B Bahan 240,150.00 271,550.00
0.03 m3 Kayu Klas III (Terentang) 1,750,000.00 1,900,000.00 52,500.00 57,000.00
0.4 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 4,800.00 6,800.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 5,000,000.00 5,800,000.00 75,000.00 87,000.00
0.35 Lbr Plywood tebal 9mm 110,000.00 135,000.00 38,500.00 47,250.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 34,000.00 36,000.00 68,000.00 72,000.00
C PERALATAN
D Jumlah A + B + C 306,150.00 344,480.00
E Overhead & Profit (contoh 1 10% 30,615.00 34,448.00
F Harga Satuan Pekerjaan (D+E) 336,765.00 378,928.00

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

X HARGA SATUAN PEKERJAAN PENUTUP ATAP


X.1 1 m2 Pemasangan Atap Genteng Beton 94,996.00 109,626.00
A Tenaga 20,000.00 22,150.00
L.01 0.2 OH Pekerja 55,000.00 60,000.00 11,000.00 12,000.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 80,000.00 90,000.00 800.00 900.00
L.04 0.01 OH Mandor 70,000.00 75,000.00 700.00 750.00
B Bahan 66,360.00 77,510.00
11 Lbr Genteng Beton Standrad 6,000.00 7,000.00 66,000.00 77,000.00
0.03 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 360.00 510.00
C PERALATAN
D Jumlah A + B + C 86,360.00 99,660.00
E Overhead & Profit (contoh 1 10% 8,636.00 9,966.00
F Harga Satuan Pekerjaan (D+E) 94,996.00 109,626.00

X.2 1 m' Pemasangan Nok Genteng Beton 100,353.00 112,486.00


A Tenaga 40,000.00 44,300.00
L.01 0.4 OH Pekerja 55,000.00 60,000.00 22,000.00 24,000.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 80,000.00 90,000.00 1,600.00 1,800.00
L.04 0.02 OH Mandor 70,000.00 75,000.00 1,400.00 1,500.00
B Bahan 51,230.00 57,960.00
3.5 Buah Nok Genteng Beton 8,500.00 10,000.00 29,750.00 35,000.00
0.05 Kg Paku Biasa 2" - 5" 12,000.00 17,000.00 600.00 850.00
10.8 Kg Portland Semen 1,400.00 1,425.00 15,120.00 15,390.00
0.032 m3 Pasir Pasang 180,000.00 210,000.00 5,760.00 6,720.00
C PERALATAN
D Jumlah A + B + C 91,230.00 102,260.00
E Overhead & Profit (contoh 1 10% 9,123.00 10,226.00
F Harga Satuan Pekerjaan (D+E) 100,353.00 112,486.00

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XI HARGA SATUAN PEKERJAAN LANGIT-LANGIT


XI.1 1 m2 Memasang Langit-langit Gypsum Board, Uk (120x240) tebal 9 mm 37,639.80 40,084.00
A Tenaga 10,000.00 11,075.00
L.01 0.1 OH Pekerja 55,000.00 60,000.00 5,500.00 6,000.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 80,000.00 90,000.00 400.00 450.00
L.04 0.005 OH Mandor 70,000.00 75,000.00 350.00 375.00
B Bahan 24,218.00 25,365.00
0.364 Lbr Gypsum Board 62,000.00 65,000.00 22,568.00 23,660.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 34,218.00 36,440.00
E Overhead & Profit (contoh 1 10% 3,421.80 3,644.00
F Harga Satuan Pekerjaan (D+E) 37,639.80 40,084.00

XI.2 1 m2 Pemasangan List Gypsum 37,639.80 40,084.00


A Tenaga 10,000.00 11,075.00
L.01 0.1 OH Pekerja 55,000.00 60,000.00 5,500.00 6,000.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 80,000.00 90,000.00 400.00 450.00
L.04 0.005 OH Mandor 70,000.00 75,000.00 350.00 375.00
B Bahan 24,218.00 25,365.00
1.000 Lbr List Profil Gypsum 11,000.00 13,000.00 22,568.00 23,660.00
0.65 Kg compon 4,000.00 5,000.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 34,218.00 36,440.00
E Overhead & Profit (contoh 1 10% 3,421.80 3,644.00
F Harga Satuan Pekerjaan (D+E) 37,639.80 40,084.00

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XII HARGA SATUAN PEKERJAAN SANITASI


XII.1 1 Unit Memasang Closet Duduk / Mono Blok 1,585,408.00 2,082,949.00
A Tenaga 275,280.00 303,590.00
L.01 3.3 OH Pekerja 55,000.00 60,000.00 181,500.00 198,000.00
L.02 1.1 OH Tukang Batu 75,000.00 85,000.00 82,500.00 93,500.00
L.03 0.001 OH Kepala Tukang 80,000.00 90,000.00 80.00 90.00
L.04 0.16 OH Mandor 70,000.00 75,000.00 11,200.00 12,000.00
Buah Bahan 1,166,000.00 1,590,000.00
1 Buah Kloset Duduk / Monoblok 1,100,000.00 1,500,000.00 1,100,000.00 1,500,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,100,000.00 1,500,000.00 66,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,441,280.00 1,893,590.00
E Overhead & Profit (contoh 1 10% 144,128.00 189,359.00
F Harga Satuan Pekerjaan (D+E) 1,585,408.00 2,082,949.00

XII.2 1 Unit Memasang Wastafel 509,932.50 771,072.50


A Tenaga 95,875.00 105,325.00
L.01 1.2 OH Pekerja 55,000.00 60,000.00 66,000.00 72,000.00
L.02 0.145 OH Tukang Batu 75,000.00 85,000.00 10,875.00 12,325.00
L.03 0.15 OH Kepala Tukang 80,000.00 90,000.00 12,000.00 13,500.00
L.04 0.1 OH Mandor 70,000.00 75,000.00 7,000.00 7,500.00
B Bahan 367,700.00 595,650.00
1 Buah Wastafel 275,000.00 450,000.00 275,000.00 450,000.00
0.3 - Perlengkapan 30% Harga Wastafel 275,000.00 450,000.00 82,500.00 135,000.00
6 Kg Portland Semen 1,400.00 1,425.00 8,400.00 8,550.00
0.01 m3 Pasir Pasang 180,000.00 210,000.00 1,800.00 2,100.00
C PERALATAN
D Jumlah A + B + C 463,575.00 700,975.00
E Overhead & Profit (contoh 1 10% 46,357.50 70,097.50
F Harga Satuan Pekerjaan (D+E) 509,932.50 771,072.50
XII.3 1 Unit Memasang Urinoir 671,220.00 725,615.00
A Tenaga 145,000.00 161,500.00
L.01 1.0 OH Pekerja 55,000.00 60,000.00 55,000.00 60,000.00
L.02 1.000 OH Tukang Batu 75,000.00 85,000.00 75,000.00 85,000.00
L.03 0.10 OH Kepala Tukang 80,000.00 90,000.00 8,000.00 9,000.00
L.04 0.1 OH Mandor 70,000.00 75,000.00 7,000.00 7,500.00
B Bahan 465,200.00 498,150.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350000 375000 105000 112500
6 Kg Portland Semen 1400 1425 8,400.00 8,550.00
0.01 m3 Pasir Pasang 180000 210000 1,800.00 2,100.00
C PERALATAN
D Jumlah A + B + C 610200 659650
E Overhead & Profit (contoh 10%) 61020 65965
F Harga Satuan Pekerjaan (D+E) 671220 725615

XII.4 1 buah Pemasangan Floor Drain 81,895.00 88,412.50


A Tenaga 9,200.00 10,375.00
L.01 0.010 OH Pekerja 55,000.00 60,000.00 550.00 600.00
L.02 0.100 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 80,000.00 90,000.00 800.00 900.00
L.04 0.005 OH Mandor 70,000.00 75,000.00 350.00 375.00
B Bahan 65,250.00 70,000.00
1 bh Floor Drain 65,250.00 70,000.00 65,250.00 70,000.00

C PERALATAN
D Jumlah A + B + C 74,450.00 80,375.00
E Overhead & Profit (contoh 1 10% 7,445.00 8,037.50
F Harga Satuan Pekerjaan (D+E) 81,895.00 88,412.50

XII.5 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 21,450.00 22,811.25


A Tenaga 7,100.00 7,950.00
L.01 0.036 OH Pekerja 55,000.00 60,000.00 1,980.00 2,160.00
L.02 0.060 OH Tukang Batu 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.002 OH Mandor 70,000.00 75,000.00 140.00 150.00
B Bahan 12,400.00 12,787.50
1 m' Pipa PVC Ø ¾" 8,000.00 8,250.00 9,600.00 9,900.00
0 Ls Perlengkapan 35% x pipa 8,000.00 8,250.00 2,800.00 2,887.50
C PERALATAN
D Jumlah A + B + C 19,500.00 20,737.50
E Overhead & Profit (contoh 1 10% 1,950.00 2,073.75
F Harga Satuan Pekerjaan (D+E) 21,450.00 22,811.25

XII,6 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 40,415.83 44,375.83


A Tenaga 10,650.00 11,925.00
L.01 0.054 OH Pekerja 55,000.00 60,000.00 2,970.00 3,240.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 80,000.00 90,000.00 720.00 810.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 26,091.67 28,416.67
1.20 m' Pipa PVC Ø 2" 16,833.33 18,333.33 20,200.00 22,000.00
0.35 Ls Perlengkapan 35% x pipa 16,833.33 18,333.33 5,891.67 6,416.67
C PERALATAN
D Jumlah A + B + C 36,741.67 40,341.67
E Overhead & Profit (contoh 1 10% 3,674.17 4,034.17
F Harga Satuan Pekerjaan (D+E) 40,415.83 44,375.83

XII.7 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 72,946.50 77,036.67


A Tenaga 15,940.00 17,850.00
L.01 0.081 OH Pekerja 55,000.00 60,000.00 4,455.00 4,860.00
L.02 0.135 OH Tukang Batu 75,000.00 85,000.00 10,125.00 11,475.00
L.03 0.014 OH Kepala Tukang 80,000.00 90,000.00 1,080.00 1,215.00
L.04 0.004 OH Mandor 70,000.00 75,000.00 280.00 300.00
B Bahan 50,375.00 52,183.33
1.20 m' Pipa PVC Ø 3" 32,500.00 33,666.67 39,000.00 40,400.00
0.35 Ls Perlengkapan 35% x pipa 32,500.00 33,666.67 11,375.00 11,783.33
C PERALATAN
D Jumlah A + B + C 66,315.00 70,033.33
E Overhead & Profit (contoh 1 10% 6,631.50 7,003.33
F Harga Satuan Pekerjaan (D+E) 72,946.50 77,036.67

XII.8 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 54,020.31 80,943.78


A Tenaga 34,100.00 38,575.00
L.01 0.010 OH Pekerja 55,000.00 60,000.00 550.00 600.00
L.02 0.400 OH Tukang Batu 75,000.00 85,000.00 30,000.00 34,000.00
L.03 0.0400 OH Kepala Tukang 80,000.00 90,000.00 3,200.00 3,600.00
L.04 0.005 OH Mandor 70,000.00 75,000.00 350.00 375.00
B Bahan 15,009.38 35,010.25
1.00 bh Kran Air 15,000.00 35,000.00 15,000.00 35,000.00
0.00 bh Sealtape 3,750.00 4,100.00 9.38 10.25
C PERALATAN
D Jumlah A + B + C 49,109.38 73,585.25
E Overhead & Profit (contoh 1 10% 4,910.94 7,358.53
F Harga Satuan Pekerjaan (D+E) 54,020.31 80,943.78

XII.9 1 SET TANDON AIR 2,500,000.00

XII.10 1 SET Saptitanck kapasitas 5m3 15,250,000.00

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XIII HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


XIII.1 1 Kg Pemasangan Besi Profil ┘└ 70.70.7 27,736.50 30,087.75
A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.2 1 Kg Pemasangan Besi Profil ┘└ 60.60.6 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.3 1 Kg Pemasangan Besi Profil ┘└ 50.50.5 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.4 1 Kg Pemasangan Besi Profil ┘└ 40.40.4 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.5 1 Kg Pekerjaan Gording baja 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.6 1 Kg Pekerjaan Track Stang 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.7 1 Kg Pekerjaan Baja Tarik Angin 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.8 1 Kg Memasang Railing tangga stainless steel 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.9 1 Kg Memasang reng baja ringan 50.50.2,3 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.10 1 Kg Memasang usuk baja ringan 125.100.20.2,3 27,736.50 30,087.75


A Tenaga 8,490.00 9,465.00
L.01 0.06 OH Pekerja 55,000.00 60,000.00 3,300.00 3,600.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 16,725.00 17,887.50
1.15 Kg Besi Profil 13,500.00 14,250.00 15,525.00 16,387.50
0.06 Kg Meni Besi 20,000.00 25,000.00 1,200.00 1,500.00
C PERALATAN
D Jumlah A + B + C 25,215.00 27,352.50
E Overhead & Profit (contoh 1 10% 2,521.50 2,735.25
F Harga Satuan Pekerjaan (D+E) 27,736.50 30,087.75

XIII.11 1 m' Pemasangan Kusen Pintu Allumunium 108,439.10 116,027.45


A Tenaga 6,081.00 6,779.50
L.01 0.043 OH Pekerja 55,000.00 60,000.00 2,365.00 2,580.00
L.02 0.043 OH Tukang Besi 75,000.00 85,000.00 3,225.00 3,655.00
L.03 0.0043 OH Kepala Tukang 80,000.00 90,000.00 344.00 387.00
L.04 0.0021 OH Mandor 70,000.00 75,000.00 147.00 157.50
B Bahan 92,500.00 98,700.00
1.1 m' Profil Allumunium 80,000.00 85,000.00 88,000.00 93,500.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 98,581.00 105,479.50
E Overhead & Profit (contoh 1 10% 9,858.10 10,547.95
F Harga Satuan Pekerjaan (D+E) 108,439.10 116,027.45

XIII.12 1 m' Pemasangan Pipa Galvanis Ø 4" 259,468.00 271,502.00


A Tenaga 26,630.00 29,820.00
L.01 0.14 OH Pekerja 55,000.00 60,000.00 7,425.00 8,100.00
L.02 0.23 OH Tukang Batu 75,000.00 85,000.00 16,875.00 19,125.00
L.03 0.023 OH Kepala Tukang 80,000.00 90,000.00 1,840.00 2,070.00
L.04 0.007 OH Mandor 70,000.00 75,000.00 490.00 525.00
B Bahan 209,250.00 217,000.00
1.20 m' Pipa Galvanis Ø 4" 135,000.00 140,000.00 162,000.00 168,000.00
0.35 Ls Perlengkapan 35% x pipa 135,000.00 140,000.00 47,250.00 49,000.00
C PERALATAN
D Jumlah A + B + C 235,880.00 246,820.00
E Overhead & Profit (contoh 1 10% 23,588.00 24,682.00
F Harga Satuan Pekerjaan (D+E) 259,468.00 271,502.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XIV HARGA SATUAN PEKERJAAN KUNCI dan KACA


XIV.1 1 Buah Pemasangan Kunci Tanam Biasa 197,120.00 219,312.50
A Tenaga 39,200.00 44,375.00
L.01 0.01 OH Pekerja 55,000.00 60,000.00 550.00 600.00
L.02 0.5 OH Tukang Kayu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.01 OH Kepala Tukang 80,000.00 90,000.00 800.00 900.00
L.04 0.005 OH Mandor 70,000.00 75,000.00 350.00 375.00
B Bahan 140,000.00 155,000.00
1 Buah Kunci Tanam Biasa 140,000.00 155,000.00 140,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 179,200.00 199,375.00
E Overhead & Profit (contoh 1 10% 17,920.00 19,937.50
F Harga Satuan Pekerjaan (D+E) 197,120.00 219,312.50

XIV.2 1 Buah Pemasangan Engsel Pintu dan Jendela 28,798.00 31,968.75


A Tenaga 13,800.00 15,562.50
L.01 0.02 OH Pekerja 55,000.00 60,000.00 825.00 900.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.02 OH Kepala Tukang 80,000.00 90,000.00 1,200.00 1,350.00
L.04 0.008 OH Mandor 70,000.00 75,000.00 525.00 562.50
B Bahan 10,000.00 13,500.00
1 Buah Engsel pintu 6,000.00 9,000.00 6,000.00 9,000.00
1 buah Engsel Jendela 4,000.00 4,500.00 4,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 28,798.00 31,968.75
E Overhead & Profit (contoh 1 10% 2,879.80 3,196.88
F Harga Satuan Pekerjaan (D+E) 31,677.80 35,165.63

XIV.3 1 Buah Pemasangan Kait Angin 20,718.50 36,410.00


A Tenaga 13,835.00 15,600.00
L.01 0.02 OH Pekerja 55,000.00 60,000.00 825.00 900.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.02 OH Kepala Tukang 80,000.00 90,000.00 1,200.00 1,350.00
L.04 0.008 OH Mandor 70,000.00 75,000.00 560.00 600.00
B Bahan 5,000.00 17,500.00
1 Buah Kait Angin 5,000.00 17,500.00 5,000.00 17,500.00
C PERALATAN
D Jumlah A + B + C 18,835.00 33,100.00
E Overhead & Profit (contoh 1 10% 1,883.50 3,310.00
F Harga Satuan Pekerjaan (D+E) 20,718.50 36,410.00

XIV.4 1 m2 Pemasangan Kaca tebal 5 mm 99,360.25 107,311.88


A Tenaga 13,327.50 15,056.25
L.01 0.015 OH Pekerja 55,000.00 60,000.00 825.00 900.00
L.02 0.15 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 80,000.00 90,000.00 1,200.00 1,350.00
L.04 0.001 OH Mandor 70,000.00 75,000.00 52.50 56.25
B Bahan 77,000.00 82,500.00
1 m2 Kaca tebal 5mm 70,000.00 75,000.00 77,000.00 82,500.00
C PERALATAN
D Jumlah A + B + C 90,327.50 97,556.25
E Overhead & Profit (contoh 1 10% 9,032.75 9,755.63
F Harga Satuan Pekerjaan (D+E) 99,360.25 107,311.88

XIV.5 1 Buah Pemasangan Grendel 25,118.50 29,260.00


A Tenaga 13,835.00 15,600.00
L.01 0.02 OH Pekerja 55,000.00 60,000.00 825.00 900.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.02 OH Kepala Tukang 80,000.00 90,000.00 1,200.00 1,350.00
L.04 0.008 OH Mandor 70,000.00 75,000.00 560.00 600.00
B Bahan 9,000.00 11,000.00
1 Buah Grendel 9,000.00 11,000.00 9,000.00 11,000.00
C PERALATAN
D Jumlah A + B + C 22,835.00 26,600.00
E Overhead & Profit (contoh 1 10% 2,283.50 2,660.00
F Harga Satuan Pekerjaan (D+E) 25,118.50 29,260.00

XIV.6 1 m2 Pemasangan Kaca Cermin tebal 5 mm 286,910.25 349,311.88


A Tenaga 13,327.50 15,056.25
L.01 0.015 OH Pekerja 55,000.00 60,000.00 825.00 900.00
L.02 0.15 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 80,000.00 90,000.00 1,200.00 1,350.00
L.04 0.001 OH Mandor 70,000.00 75,000.00 52.50 56.25
B Bahan 247,500.00 302,500.00
1 m2 Kaca Cermin 225,000.00 275,000.00 247,500.00 302,500.00
C PERALATAN
D Jumlah A + B + C 260,827.50 317,556.25
E Overhead & Profit (contoh 1 10% 26,082.75 31,755.63
F Harga Satuan Pekerjaan (D+E) 286,910.25 349,311.88

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XV HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


XV.1 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 333,294.50 573,248.50
A Tenaga 25,075.00 27,770.00
L.01 0.250 OH Pekerja 55,000.00 60,000.00 13,750.00 15,000.00
L.02 0.125 OH Tukang Batu 75,000.00 85,000.00 9,375.00 10,625.00
L.03 0.013 OH Kepala Tukang 80,000.00 90,000.00 1,040.00 1,170.00
L.04 0.013 OH Mandor 70,000.00 75,000.00 910.00 975.00
B Bahan 277,920.00 493,365.00
6.63 Buah Ubin Granito 40x40 cm 0.4 36,666.67 68,333.33 243,100.00 453,050.00
9.8 Kg Portland Semen 0.16 1,400.00 1,425.00 13,720.00 13,965.00
1.300 Kg Semen warna 6.25 10,000.00 13,000.00 13,000.00 16,900.00
0.045 m3 Pasir Pasang 180,000.00 210,000.00 8,100.00 9,450.00
C PERALATAN
D Jumlah A + B + C 302,995.00 521,135.00
E Overhead & Profit (contoh 1 10% 30,299.50 52,113.50
F Harga Satuan Pekerjaan (D+E) 333,294.50 573,248.50

XV.2 1 m2 Kramik Uk. 30 x 30 cm 122,825.00 133,796.50


A Tenaga 26,000.00 28,795.00
L.01 0.26 OH Pekerja 55,000.00 60,000.00 14,300.00 15,600.00
L.02 0.130 OH Tukang Batu 75,000.00 85,000.00 9,750.00 11,050.00
L.03 0.013 OH Kepala Tukang 80,000.00 90,000.00 1,040.00 1,170.00
L.04 0.013 OH Mandor 70,000.00 75,000.00 910.00 975.00
B Bahan 85,659.09 92,838.18
11.87 Buah Keramik 30x30 cm 4,090.91 4,181.82 48,559.09 49,638.18
10.0 Kg Portland Semen 1,400.00 1,425.00 14,000.00 14,250.00
1.50 Kg Semen warna 10,000 13,000 15,000.00 19,500.00
0.0450 m3 Pasir Pasang 180,000.00 210,000.00 8,100.00 9,450.00
C PERALATAN
D Jumlah A + B + C 111,659.09 121,633.18
E Overhead & Profit (contoh 1 10% 11,165.91 12,163.32
F Harga Satuan Pekerjaan (D+E) 122,825.00 133,796.50

XV.3 1 m2 Pemasangan Dinding Keramik 20x20 cm, 194,194.00 220,250.25


A Tenaga 90,000.00 99,675.00
L.01 0.9 OH Pekerja 55,000.00 60,000.00 49,500.00 54,000.00
L.02 0.45 OH Tukang Batu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 80,000.00 90,000.00 3,600.00 4,050.00
L.04 0.045 OH Mandor 70,000.00 75,000.00 3,150.00 3,375.00
B Bahan 86,540.00 100,552.50
26.5 Buah Keramik 1,920.00 2,200.00 50,880.00 58,300.00
9.3 Kg Portland Semen 1,400.00 1,425.00 13,020.00 13,252.50
0.018 m3 Pasir Pasang 180,000.00 210,000.00 3,240.00 3,780.00
1.94 Kg Semen Warna 10,000.00 13,000.00 19,400.00 25,220.00
C PERALATAN
D Jumlah A + B + C 176,540.00 200,227.50
E Overhead & Profit (contoh 1 10% 17,654.00 20,022.75
F Harga Satuan Pekerjaan (D+E) 194,194.00 220,250.25

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XVIII HARGA SATUAN PEKERJAAN PENGECATAN


XVIII.1 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 35,953.50 41,629.50
A Tenaga 5,215.00 5,730.00
L.01 0.070 OH Pekerja 55,000.00 60,000.00 3,850.00 4,200.00
L.02 0.009 OH Tukang Cat 75,000.00 85,000.00 675.00 765.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 480.00 540.00
L.04 0.003 OH Mandor 70,000.00 75,000.00 210.00 225.00
B Bahan 27,470.00 32,115.00
0.2000 kg Cat Menie 20,000.00 27,000.00 4,000.00 5,400.00
0.1500 kg Plamuur 20,000.00 27,500.00 3,000.00 4,125.00
0.1700 kg Cat Dasar 34,000.00 36,500.00 5,780.00 6,205.00
0.2600 kg Cat Penutup 52,000.00 58,000.00 13,520.00 15,080.00
0.0100 bh Kuas 7,500.00 9,500.00 75.00 95.00
0.0300 kg Pengencer 16,500.00 17,000.00 495.00 510.00
0.2000 lbr Amplas 3,000.00 3,500.00 600.00 700.00
C PERALATAN
D Jumlah A + B + C 32,685.00 37,845.00
E Overhead & Profit (contoh 1 10% 3,268.50 3,784.50
F Harga Satuan Pekerjaan (D+E) 35,953.50 41,629.50

XVIII.2 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 16,586.90 19,257.70
2 lap. Cat Penutup)
A Tenaga 6,539.00 7,347.00
L.01 0.020 OH Pekerja 55,000.00 60,000.00 1,100.00 1,200.00
L.02 0.063 OH Tukang Cat 75,000.00 85,000.00 4,725.00 5,355.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 504.00 567.00
L.04 0.003 OH Mandor 70000 75000 210.00 225.00
B Bahan 8,540.00 10,160.00
0.1000 Kg Plamir 24,000.00 32,000.00 2,400.00 3,200.00
0.1000 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.2600 Kg Cat Penutup 2 kali 19,000.00 21,000.00 4,940.00 5,460.00
C PERALATAN
D Jumlah A + B + C 15,079.00 17,507.00
E Overhead & Profit (contoh 10%) 0.1 1,507.90 1,750.70
F Harga Satuan Pekerjaan (D+E) 16586.9 19257.7

XVIII.3 1 m2 Pengecatan Plafond dan List Plafond 16,586.90 19,257.70


2 lap. Cat Penutup)
A Tenaga 6,539.00 7,347.00
L.01 0.020 OH Pekerja 55,000.00 60,000.00 1,100.00 1,200.00
L.02 0.063 OH Tukang Cat 75,000.00 85,000.00 4,725.00 5,355.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 504.00 567.00
L.04 0.003 OH Mandor 70000 75000 210.00 225.00
B Bahan 8,540.00 10,160.00
0.1000 Kg Plamir 24,000.00 32,000.00 2,400.00 3,200.00
0.1000 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.2600 Kg Cat Penutup 2 kali 19,000.00 21,000.00 4,940.00 5,460.00
C PERALATAN
D Jumlah A + B + C 15,079.00 17,507.00
E Overhead & Profit (contoh 10%) 0.1 1,507.90 1,750.70
F Harga Satuan Pekerjaan (D+E) 16586.9 19257.7
Rp 199,100.00
Rp 185,000.00
Rp 185,000.00

Rp 14,100.00
Rp 12,750.00
Rp 1,350.00

Rp 67,100.00
Rp 53,000.00
Rp 53,000.00

Rp 14,100.00
Rp 12,750.00
Rp 1,350.00

Rp 47,100.00
Rp 33,000.00
Rp 33,000.00

Rp 14,100.00
Rp 12,750.00
Rp 1,350.00

Rp 79,100.00
Rp 65,000.00
Rp 65,000.00

Rp 14,100.00
Rp 12,750.00
Rp 1,350.00

Rp 104,100.00
Rp 90,000.00
Rp 90,000.00

Rp 14,100.00
Rp 12,750.00
Rp 1,350.00

Rp 131,625.00
Rp 129,000.00
Rp 129,000.00

Rp 2,625.00
Rp 1,275.00
Rp 1,350.00
Rp 29,100.00
Rp 15,000.00
Rp 15,000.00

Rp 14,100.00
Rp 12,750.00
Rp 1,350.00

Rp 29,100.00
Rp 15,000.00
Rp 15,000.00

Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 17,625.00
Rp 15,000.00
Rp 15,000.00

Rp 2,625.00
Rp 1,275.00
Rp 1,350.00

Rp 1,050,000.00
RENCANA ANGGARAN BIAYA
PEKERJAAN RUMAH TINGGAL 2 LANTAI
SEMARANG
TAHUN ANGGARAN 2016

Vol Sat Harga Satuan Harga X. Pekerjaan Penutup Atap dan Langit - Langit
No Jenis Pekerjaan
Pek. Pek. Pekerjaan Pekerjaan 1 Pemasangan Atap Genteng Beton 231.875 m2 Rp 109,626.00 Rp 25,419,528.75
I. Pekerjaan Persiapan 2 Pemasangan Nok Genteng Beton 64.39 m2 Rp 112,486.00 Rp 7,242,973.54
1 Permbersihan Lahan 296.525 m2 Rp 11,550.00 Rp 3,424,863.75 3 Pekerjaan Plafond Gypsum Board 340.640 m2 Rp 40,084.00 Rp 13,654,213.76
2 Pembuatan Direksi Keet 32 m2 Rp 2,823,151.38 Rp 90,340,844.00 4 Pekerjaan List Gypsum 266.300 m2 Rp 40,084.00 Rp 10,674,369.20
3 Pembuatan Pagar Keliling 69.9 m Rp 2,030,239.94 Rp 141,913,771.98 JUMLAH Rp 56,991,085.25
4 Gudang Bahan/Peralatan 9 m2 Rp 3,228,682.88 Rp 29,058,145.88
5 Pemasangan Bouwplank 61.5 m Rp 93,236.00 Rp 5,734,014.00 XIV. Pekerjaan penggantung kunci dan Kaca
5 Listrik Penerangan Proyek 1 ls Rp 5,000,000.00 Rp 5,000,000.00 1 Kunci Tanam Biasa 12 buah Rp 219,312.50 Rp 2,631,750.00
6 Air Kerja & Air Minum Proyek 1 ls Rp 5,000,000.00 Rp 5,000,000.00 2 Engsel Pintu dan jendela 80 buah Rp 31,968.75 Rp 2,557,500.00
7 Papan Nama Proyek 1 ls Rp 500,000.00 Rp 500,000.00 3 Engsel Kait Angin 89 buah Rp 36,410.00 Rp 3,240,490.00
JUMLAH Rp 280,971,639.61 4 Pemasangan Grendel 48 buah Rp 29,260.00 Rp 1,404,480.00
5 Pekerjaan Kaca 5 mm 13.416 m2 Rp 107,311.88 Rp 1,439,696.12
II. Pekerjaan Tanah 6 Pekerjaan cermin 5 mm 2 buah Rp 349,311.88 Rp 698,623.75
1 Pekerjaan Galian Tanah 111.94 m3 Rp 51,562.50 Rp 5,771,906.25 JUMLAH Rp 11,273,916.12
2 Pekerjaan Urugan Tanah Kembali 32.755 m3 Rp 12,375.00 Rp 405,343.13
JUMLAH Rp 6,177,249.38
XVI. Pekerjaan Elektrikal Mekanikal
III. Pekerjaan Pondasi 1 lampu gantung 16 buah Rp 185,000.00 Rp 2,960,000.00
1 Pasangan Pondasi Batu Kali 1Pc : 6 Pp 65.205 m3 Rp 786,126.00 Rp 51,259,345.83 2 Lampu SL 18 watt 9 buah Rp 53,000.00 Rp 477,000.00
JUMLAH Rp 51,259,345.83 3 Lampu Baret + TL. Ring 32 W 20 buah Rp 33,000.00 Rp 660,000.00
4 Lampu Pijar 40 W 11 buah Rp 65,000.00 Rp 715,000.00
VII Pekerjaan Beton 5 TL 2 x 18W 8 buah Rp 90,000.00 Rp 720,000.00
1 Pekerjaan Footplat 0.75 m3 Rp 1,152,003.31 Rp 864,002.49 6 Lampu Exterior Sudut 19 buah Rp 129,000.00 Rp 2,451,000.00
2 Pekerjaan Sloof 5.433 m3 Rp 1,134,868.78 Rp 6,165,742.07 7 Saklar Tunggal 11 buah Rp 15,000.00 Rp 165,000.00
3 Pekerjaan Kolom 14.67 m3 Rp 1,152,003.31 Rp 16,899,888.63 8 Saklar Ganda 8 buah Rp 21,000.00 Rp 168,000.00
4 Pekerjaan Balok 14.258 m3 Rp 1,152,003.31 Rp 16,425,263.26 9 Stop Kontak 19 buah Rp 15,000.00 Rp 285,000.00
5 Plat Lantai 34.503 m3 Rp 1,134,868.78 Rp 39,156,377.44 JUMLAH Rp 8,601,000.00
6 Pekerjaan Tangga 4.388 m3 Rp 1,134,868.78 Rp 4,979,804.20
JUMLAH Rp 83,627,075.60 XVII. Pekerjaan Mesin
1 Pompa Air 100 W 1 buah Rp 1,050,000.00 Rp 1,050,000.00
VIII Pekerjaan Pembesian JUMLAH Rp 1,050,000.00
1 Pembesian Footplat 43.6906 kg Rp 152,916.88 Rp 6,681,030.34
2 Pembesian Sloof 140.2115 kg Rp 152,916.88 Rp 21,440,705.46 XII. Pekerjaan Sanitair
3 Pembesian Kolom 232.9957 kg Rp 152,916.88 Rp 35,628,976.05 1 Pasangan Closet Duduk 4 buah Rp 2,082,949.00 Rp 8,331,796.00
4 Pembesian Balok 179.63 kg Rp 152,916.88 Rp 27,468,459.58 2 Pasangan Westafel Meja 2 buah Rp 771,072.50 Rp 1,542,145.00
5 Pembesian Lantai 15.1267 kg Rp 152,916.88 Rp 2,313,127.80 3 Urinoir 1 unit Rp 725,615.00 Rp 725,615.00
6 Pembesian Tangga 12.9365 kg Rp 152,916.88 Rp 1,978,209.25 4 kran air biasa 9 buah Rp 80,943.78 Rp 728,493.98
JUMLAH Rp 95,510,508.49 6 Pasangan Floor Drain 8 buah Rp 88,412.50 Rp 707,300.00
7 Pipa PVC 3/4" 74.05 m' Rp 22,811.25 Rp 1,689,173.06
IX. Pekerjaan Bekisting 8 Pipa PVC 2" 30.5 m' Rp 44,375.83 Rp 1,353,462.92
1 Bekisting Footplat 4.8 m² Rp 153,516.00 Rp 736,876.80 9 Pipa PVC 3" 28.75 m' Rp 77,036.67 Rp 2,214,804.17
2 Bekisting Sloof 18.113 m² Rp 163,966.00 Rp 2,969,916.16 10 Tandon Air 1 buah Rp 2,500,000.00 Rp 2,500,000.00
3 Bekisting Kolom 31.776 m² Rp 400,378.00 Rp 12,722,411.33 11 Septictank kapasitas 5 m3 1 buah Rp 15,250,000.00 Rp 15,250,000.00
4 Bekisting Balok 17.305 m² Rp 419,518.00 Rp 7,259,758.99 JUMLAH Rp 35,042,790.12
5 Bekisting Lantai 23.8025 m² Rp 558,778.00 Rp 13,300,313.35
6 Bekisting Tangga 1.5859 m² Rp 378,928.00 Rp 600,941.92 XVIII. Pekerjaan Finisihing
JUMLAH Rp 36,989,276.62 1 Pengecatan Tembok 459.245 m2 Rp 19,257.70 Rp 8,844,002.44
2 Pengecatan Plafond 340.64 m2 Rp 19,257.70 Rp 6,559,942.93
JUMLAH Rp 15,403,945.36

IV-V Pekerjaan Pasangan


1 Pas.Dinding bata merah 459.425 m2 Rp 208,375.75 Rp 95,733,028.94
2 Plesteran 1Pc : 5Pp 918 m2 Rp 67,704.56 Rp 62,185,961
3 Acian 918 m2 Rp 22,100.00 Rp 20,298,629.00
JUMLAH Rp 178,217,619.26

XV. Pekerjaan Penutup Lantai


1 Keramik Tile 40 x 40 polished 312.375 m2 Rp 573,248.50 Rp 179,068,500.19
2 Keramik Tile 30 x 30 polished 12 m2 Rp 133,796.50 Rp 1,605,558.00
3 Keramik kamar mandi 20 x 20 58.857 m2 Rp 220,250.25 Rp 12,963,268.96
JUMLAH Rp 193,637,327.15

VI. Pekerjaan Kayu


1 Pekerjaan Kusen Pintu dan Jendela 1.53 m3 Rp 12,227,325.00 Rp 18,707,807.25
2 Pekerjaan Daun Pintu 16.26 m2 Rp 724,625.00 Rp 11,782,402.50
JUMLAH Rp 30,490,209.75

XIII Pekerjaan Baja dan Alumunium


1 Pekerjaan kuda-kuda baja profil ┘└ 70.70.7 299.997 kg Rp 30,087.75 Rp 9,026,234.74
2 Pekerjaan kuda-kuda baja profil ┘└ 60.60.6 198.643 kg Rp 30,087.75 Rp 5,976,720.92
3 Pekerjaan kuda-kuda baja profil ┘└ 50.50.5 53.911 kg Rp 30,087.75 Rp 1,622,060.69
4 Pekerjaan kuda-kuda baja profil ┘└ 40.40.4 84.7 kg Rp 30,087.75 Rp 2,548,432.43
5 Pekerjaan baja gording atap 944.64 kg Rp 30,087.75 Rp 28,422,092.16
6 Pekerjaan baja track stang 1.425 kg Rp 30,087.75 Rp 42,875.04
7 Pipa galvanis Ø4” tp 5 mm’ 203.28 kg Rp 271,502.00 Rp 55,190,926.56
8 Usuk Baja Ringan C 75/100 2204.16 kg Rp 30,087.75 Rp 66,318,215.04
9 Reng Baja Ringan C 75/100 3660.48 kg Rp 30,087.75 Rp 110,135,607.12
10 Pekerjaan Kusen dan Daun pintu Alumunium 23.72 m2 Rp 116,027.45 Rp 2,752,171.11
JUMLAH Rp 279,283,164.70
MAN POWER

NO URAIAN PEKERJAAN KODE SATUAN VOLUME


Pekerja K. Tukang

I PEKERJAAN PERSIAPAN
1 Permbersihan Lahan 6.8 m2 296.525 30
2 Pembuatan Direksi Keet 6.5 m2
32.000 64 10
3 Pembuatan Pagar Keliling 6.4 m2
69.900 14 1
TOTAL MAN POWER 108 11

II PEKERJAAN TANAH
1 Pekerjaan Galian Tanah 6.1 m3 111.940 84
2 Pekerjaan Urugan Tanah Kembali - m3
32.755 16

TOTAL MAN POWER 100 0

III PEKERJAAN PONDASI


1 Pasangan Pondasi Batu Kali 1Pc : 6 Pp 6.9 m3 65.205 98 5

TOTAL MAN POWER 98 5

IV PEKERJAAN DINDING
1 Pas.Dinding bata merah 6.13 m2 459.43 276 9
TOTAL MAN POWER 276 9

V PEKERJAAN PLESTERAN
1 Plesteran 1Pc : 5Pp 6.3 m2 918.490 367 18
2 Acian 6.27 m2 918.490 184 9
TOTAL MAN POWER 551 28

VI PEKERJAAN KUSEN
1 Pekerjaan Kusen Pintu dan Jendela 6.5 m2 1.530 9 3
2 Pekerjaan Daun Pintu 6.12 m2 16.260 16 5

TOTAL MAN POWER 25 8

VII PEKERJAAN BETON


1 Pekerjaan Footplat 6.4 m3 0.750 1 0
2 Pekerjaan Sloof 6.29 m3
5.433 9 0
3 Pekerjaan Kolom 6.33 m3 14.670 24 0
4 Pekerjaan Balok 6.33 m3 14.258 24 0
5 Plat Lantai 6.3 m3 34.503 57 1
6 Pekerjaan Tangga 6.31 m3 4.388 1 0
TOTAL MAN POWER 115 1

VIII PEKERJAAN PEMBESIAN


1 Pembesian Footplat 6.4 kg 43.6906 3 0
2 Pembesian Sloof 6.29 kg 140.212 10 1
3 Pembesian Kolom 6.33 kg 232.996 16 2
4 Pembesian Balok 6.33 kg 179.630 13 1
5 Pembesian Lantai 6.3 kg 15.127 1 0
6 Pembesian Tangga 6.31 kg 12.937 1 0

TOTAL MAN POWER 44 4

IX PEKERJAAN BEKISTING
1 Bekisting Footplat 6.4 m² 4.800 2 0
2 Bekisting Sloof 6.29 m² 18.113 9 0
3 Bekisting Kolom 6.33 m² 31.776 21 1
4 Bekisting Balok 6.33 m² 17.305 11 1
5 Bekisting Lantai 6.3 m² 23.803 16 1
6 Bekisting Tangga 6.31 m² 1.586 1 0
TOTAL MAN POWER 61 3

X PEKERJAAN PENUTUP ATAP


1 Pemasangan Atap Genteng Beton 6.4 m2 231.875 46 2
2 nok genteng beton 6.4 m2
64.390 26 1
TOTAL MAN POWER 72 3
XI PEKERJAAN LANGIT - LANGIT
1 Pekerjaan Plafond Gypsum Board 6.7 m2 340.640 34 2
2 Pekerjaan List Gypsum 6.7 m2
266.300 27 1

TOTAL MAN POWER 61 3

XII PEKERJAAN SANITASI


1 Pasangan Closet Duduk 6.36 bh 4.000 13 0
2 Pasangan Westafel Meja 6.1 bh 2.000 2 0
3 Urinoir 6.2 bh 1.000 1 0
4 kran air biasa 6.33 bh 9.000 0 0
5 Pasangan Floor Drain 6.33 bh 8.000 0 0
6 Pipa PVC 3/4" 6.35 bh 74.050 3 0
7 Pipa PVC 2" 6.35 bh 30.500 2 0
8 Pipa PVC 3" 6.35 bh 28.750 2 0
9 Tandon Air 6.35 bh 1.000 1 1
10 Septictank kapasitas 5 m3 6.25 m1 1.000 1 1

TOTAL MAN POWER 25 2

XIII PEKERJAAN BESI & ALUMINIUM


Pekerjaan kuda-kuda baja profil ┘└ 70.70.7 6.11 kg 299.997 18 2
1 Pekerjaan kuda-kuda baja profil ┘└ 60.60.6 6.13 kg 53.911 3 0
2 Pekerjaan kuda-kuda baja profil ┘└ 50.50.5 6.13 kg 84.700 5 1
3 Pekerjaan kuda-kuda baja profil ┘└ 40.40.4 6.13 kg 84.700 5 1
4 Pekerjaan baja gording atap 6.11 kg 944.640 57 6
5 Pekerjaan baja track stang 6.12 kg 1.425 0 0
6 Pipa galvanis Ø4” tp 5 mm’ 6.12 kg 203.280 27 5
7 Pekerjaan Kusen dan Daun pintu Alumunium 23.72 kg 23.720 1 0
TOTAL MAN POWER 117 14

XIV PEKERJAAN KUNCI & KACA


Kunci Tanam Biasa 6.17 bh 12.000 0 0
1 Engsel Pintu dan jendela 6.17 bh 80.000 1 1
2 Engsel Kait Angin 6.5 bh 89.000 1 1
3 Pemasangan Grendel 6.11 bh 48.000 1 1
4 Pekerjaan Kaca 5 mm 6.9 m2 13.416 0 0
5 Pekerjaan cermin 5 mm 6.9 bh 2.000 0 0
TOTAL MAN POWER 3 3

XV PEKERJAAN PENUTUP LANTAI


Keramik Tile 40 x 40 polished 6.9 m2 312.375 78 4
1 Keramik Tile 30 x 30 polished 6.9 m 2
12.000 3 0
2 Keramik kamar mandi 20 x 20 6.9 m 2
58.857 53 3
3
TOTAL MAN POWER 134 7

XVI MEKANIKAL ELEKTRIKAL


1 lampu gantung 6.8 buah 16 0
2 Lampu SL 18 watt 6.8 buah 9 0
3 Lampu Baret + TL. Ring 32 W 6.8 buah 20 0
4 Lampu Pijar 40 W 6.8 buah 11 0
5 TL 2 x 18W 6.8 buah 8 0
6 Lampu Exterior Sudut 6.8 buah 19 0
7 Saklar Tunggal 6.8 buah 11 0
8 Saklar Ganda 6.8 buah 8 0
9 Stop Kontak 6.8 buah 19 0
TOTAL MAN POWER 0 0

XVII PEKERJAAN PENGECATAN


Pengecatan Tembok 6.14 m2 459.245 9 3
1 Pengecatan Plafond 6.1 m 2
340.640 7 2
2
TOTAL MAN POWER 16 5
Jumlah Tenaga Kerja
T. Kayu T. Besi T. Batu T. Ledeng T. Cat Mandor T.listrik

15
64 32 2
28 1
92 0 32 0 0 18 0

3
2

0 0 0 0 0 4 0

49 5

0 0 49 0 0 5 0

92 14
0 0 92 0 0 14 0

184 20
92 9
0 0 276 0 0 29 0

28 0
49 1

76 0 0 0 0 1 0

0 0
1 0
4 1
4 1
9 3
0 0
19 0 0 0 0 5 0

3 0
10 1
16 1
13 1
1 0
1 0

0 44 0 0 0 3 0

1 0
5 0
10 1
6 1
8 1
1 0
31 0 0 0 0 3 0

23 2
13 1
36 0 0 0 0 3 0
17 2
13 1

30 0 0 0 0 3 0

4 1
0 0
1 0
4 0
1 0
4 0
3 0
4 0
1 1
1 1

0 0 9 14 0 3 0

18 1
3 0
5 0
5 0
57 3
0 0
12 1
1 0
0 101 0 0 0 5 0

6 0
12 1
13 1
7 0
2 0
0 0
41 0 0 0 0 2 0

39 4
2 0
26 3

0 0 67 0 0 7 0

2
1
3
2
1
3
2
1
3
0 0 0 0 0 0 18

29 1
21 1

0 0 0 0 50 2 0
2
4.12 2.62
1.5

0.6 19.8 64.944 129.8116


10.8644 33 108.24
3.296119 6 19.77671 3.28 64.86762

18.876 2 37.752
0 0 0
0 0 0
0 0 0
37.752

0.786 5.47 6.256


REKAPITULASI ANGGARAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH TINGGAL LT 2
SEMARANG
TAHUN ANGGARAN 2016
No Uraian Pekerjaan Biaya
I Pekerjaan Persiapan Rp 280,971,639.61
II Pekerjaan Tanah Rp 6,177,249.38
III Pekerjaan Pondasi Rp 51,259,345.83
IV Pekerjaan Beton Rp 83,627,075.60
V Pekerjaan Pembesian Rp 95,510,508.49
VI Pekerjaan Bekisting Rp 36,989,276.62
VII Pekerjaan Dinding Rp 178,217,619.26
VIII Pekerjaan Penutup Lantai Rp 193,637,327.15
IX Pekerjaan Kusen Rp 30,490,209.75
X Pekerjaan Baja Rp 279,283,164.70
XI Pekerjaan Penutup Atap Rp 56,991,085.25
XII Pekerjaan Penggantung Kunci dan Kaca Rp 11,273,916.12
XIII Pekerjaan Mekanikal Elektrikal Rp 8,601,000.00
XIV Pekerjaan Mesin Rp 1,050,000.00
XV Pekerjaan Sanitasi Rp 35,042,790.12
XVI Pekerjaan Finisihing Rp 15,403,945.36
JUMLAH BIAYA Rp 1,364,526,153.23
JASA PEMBORONG 10 % Rp 136,452,615.32
JUMLAH Rp 1,500,978,768.55
PPN 10% Rp 150,097,876.86
TOTAL Rp 1,651,076,645.41
PEMBULATAN

TERBILANG :
REKAP MAN POWER

Jumlah Tenaga Kerja Jumlah Total Tenaga Kerja


No Item Pekerjaan
Pekerja K.Tukang T. Kayu T. Besi T. Batu T. Ledeng T. Cat Mandor T.Listrik Per-Item Pekerjaan
1 PEKERJAAN PERSIAPAN 108 11 92 0 32 0 0 18 0 260
2 PEKERJAAN TANAH 100 0 0 0 0 0 0 4 0 105
3 PEKERJAAN PONDASI 98 5 0 0 49 0 0 5 0 156
4 PEKERJAAN DINDING 276 9 0 0 92 0 0 14 0 391
5 PEKERJAAN PLESTERAN 551 28 0 0 276 0 0 29 0 884
6 PEKERJAAN KUSEN 25 8 76 0 0 0 0 1 0 111
7 PEKERJAAN BETON 115 1 0 0 19 0 0 5 0 140
8 PEKERJAAN PEMBESIAN 44 4 0 0 0 0 0 3 0 89
9 PEKERJAAN BEKISTING 61 4 44 0 0 0 0 3 0 112
10 PEKERJAAN PENUTUP ATAP 72 3 36 0 0 0 0 3 0 114
11 PEKERJAAN LANGIT - LANGIT 61 3 30 0 0 0 0 3 0 97
12 PEKERJAAN SANITASI 25 2 0 0 9 14 0 3 0 54
13 PEKERJAAN BESI & ALUMINIUM 117 14 0 101 0 0 0 5 0 237
14 PEKERJAAN KUNCI & KACA 3 3 41 0 0 0 0 2 0 49
15 PEKERJAAN PENUTUP LANTAI 134 7 0 0 67 0 0 7 0 215
16 MEKANIKAL ELEKTRIKAL 0 0 0 0 0 0 0 0 18 19
17 PEKERJAAN PENGECATAN 16 5 0 0 0 0 50 2 0 74
KURVA S dan BARCHART

Proyek : PEMBANGUNAN RUMAH LANTAI 2

Lokasi : SEMARANG

Tahun Anggaran : 2015

Agustus september Oktober Chart Title


November Desember Januari

no Uraian pekerjaan Jumlah harga Bobot(%) MP 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Keterangan

15 s/d 21 22 s/d 28 29 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 1 2 s/d 8 9 s/d 15 16 s/d 22 23 s/d 29 30 s/d 5 6 s/d 12 13 s/d 19 20 s/d 26 27 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 31 1 s/d 7 8 s/d 14 15 s/d 21 22 s/d 28

1 Pekerjaan Persiapan Rp 280,971,639.606 20.591 260 0.858

2 Pekerjaan Tanah Rp 6,177,249.375 0.453 105 0.091 0.091 0.091 0.091 0.091 Kalender : 168 hari

3 Pekerjaan Pondasi Rp 51,259,345.830 3.757 156 1.252 1.252 1.252

4 Pekerjaan Beton Rp 83,627,075.597 6.129 140 0.766 0.766 0.766 0.766 0.766 0.766 0.766 0.766 Masa Pemeliharaan : 60 hari

Rp 95,510,508.490
5 Pekerjaan Pembesian 7.000 89 0.875 0.875 0.875 0.875 0.875 0.875 0.875 0.875

Rp 36,989,276.621
6 Pekerjaan Bekisting 2.711 112 0.339 0.339 0.339 0.339 0.339 0.339 0.339 0.339

7 Pekerjaan Dinding Rp 178,217,619.258 13.061 391 1.633 1.633 1.633 1.633 1.633 1.633 1.633 1.633

8 Pekerjaan Penutup Lantai Rp 193,637,327.152 14.191 215 2.365 2.365 2.365 2.365 2.365 2.365

9 Pekerjaan Kusen Rp 30,490,209.750 2.234 111 0.745 0.745 0.745

10 Pekerjaan Baja Rp 279,283,164.699 20.467 237 6.822 6.822 6.822 Kegiatan Kritis

11 Pekerjaan Penutup Atap Rp 56,991,085.250 4.177 114 1.392 1.392 1.392

12 Pekerjaan Penggantung Kunci dan Kaca Rp 11,273,916.115 0.826 49 0.207 0.207 0.207 0.207

13 Pekerjaan Mekanikal Elektrikal Rp 8,601,000.000 0.630 19 0.315 0.315

14 Pekerjaan Mesin Rp 1,050,000.000 0.077 0 0.019 0.019 0.019 0.019

15 Pekerjaan Sanitasi Rp 35,042,790.121 2.568 54 0.428 0.428 0.428 0.428 0.428 0.428

16 Pekerjaan Finisihing Rp 15,403,945.365 1.129 74 0.376 0.376 0.376

Jumlah Rp 1,364,526,153.229 100.000

0 5 10 15 20 25

Rencana minggu ini 0.858 0.091 0.110 0.110 0.110 0.110 1.252 1.252 3.617 5.090 5.090 6.722 12.800 12.800
Row 29 10.863 5.433 5.433 3.453 2.267 1.011 0.583 0.898 0.315 0.000

Komulatif minggu ini 0.858 0.949 1.058 1.168 1.278 1.388 2.640 3.892 7.509 12.599 17.689 24.411 37.211 50.012 60.875 66.307 71.740 75.193 77.460 78.471 79.054 79.952 80.267 80.267

Man Power 10.851 31.804 31.804 31.804 31.804 31.804 63.015 63.015 98.849 101.052 101.052 149.866 191.844 191.844 164.988 124.187 124.187 106.708 80.800 56.596 47.618 56.880 20.113 10.851

Realisasi minggu ini

Komulatif minggu ini

Mengetahui Disetujui Pati, Desember 2013


Pimpinan Proyek Konsultan Pengawas Dibuat oleh
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

260 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851
105 20.954 20.954 20.954 20.954 20.954
156 52.164 52.164 52.164
140 17.479 17.479 17.479 17.479 17.479 17.479 17.479 17.479
391 48.814 48.814 48.814 48.814 48.814 48.814 48.814 48.814
215 35.835 35.835 35.835 35.835 35.835 35.835
111 36.888 36.888 36.888
237 78.866 78.866 78.866
114 38.066 38.066 38.066
49 12.157 12.157 12.157 12.157
19 9.263 9.263
0 0.000 0.000 0.000 0.000
54 8.978 8.978 8.978 8.978 8.978 8.978
74 24.610 24.610 24.610
0.000 0.000
0.000 0.000 0.000 0.000

10.851 31.804 31.804 31.804 31.804 31.804 63.015 63.015 98.849 101.052 101.052 149.866 191.844 191.844 164.988 124.187 124.187 106.708 80.800 56.596 47.618 56.880 20.113 10.851

12.00

MAN POWER

J 10.00
U
M
L
A
H
8.00
T
E
N
A
G
A 6.00

K
E
R
J
A 4.00

2.00

0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

MINGGU
TIME SCHEDULE

Proyek : PEMBANGUNAN RUMAH TINGGAL LT 2

Lokasi : SEMARANG

Tahun Anggaran : 2015

no Uraian pekerjaan Jumlah harga Bobot(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 keterangan

15 s/d 21 22 s/d 28 29 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 1 2 s/d 8 9 s/d 15 16 s/d 22 23 s/d 29 30 s/d 5 6 s/d 12 13 s/d 19 20 s/d 26 27 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 31 1 s/d 7 8 s/d 21

1 Pekerjaan Persiapan Rp 280,971,639.61 17.093 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 Jangka Waktu

2 Pekerjaan Tanah Rp 6,177,249.38 0.376 0.13 0.13 0.13 Pelaksanaan

3 Pekerjaan Pondasi Rp 51,259,345.83 3.118 1.56 1.56 154 hari

4 Pekerjaan Beton Lantai 1 Rp 41,813,537.80 2.544 0.85 0.85 0.85 Kalender

5 Pekerjaan Beton lantai 2 Rp 41,813,537.80 2.544 0.85 0.85 0.85

Rp 95,510,508.49 5.810
6Pekerjaan Pembesian 1.937 1.937 1.937 1.937 1.937 1.937
Rp 36,989,276.62 2.250
7Pekerjaan Bekisting 0.750 0.750 0.750 0.750 0.750 0.750
8 Pekerjaan Dinding Rp 178,217,619.26 10.842 3.61 3.61 3.61

9 Pekerjaan Baja Rp 279,283,164.70 16.990 5.66 5.66 5.66

10 Pekerjaan Penutup Lantai Rp 193,637,327.15 11.780 2.94 2.94 2.94 2.94

11 Pekerjaan Kusen Rp 30,490,209.75 1.855 0.46 0.46 0.46 0.46

12 Pekerjaan Baja Rp 279,283,164.70 16.990 8.49 8.49

13 Pekerjaan Penutup Atap Rp 56,991,085.25 3.467 1.73 1.73

14 Pekerjaan Penggantung Kunci dan Kaca Rp 11,273,916.12 0.686 0.34 0.34

16 Pekerjaan Mekanikal Elektrikal Rp 8,601,000.00 0.523 0.13 0.13 0.13 0.13 Jangka Waktu

17 Pekerjaan Sanitasi Rp 35,042,790.12 2.132 1.07 1.07 Pemeliharaan

18 Pekerjaan Finisihing Rp 15,403,945.36 0.937 0.31 0.31 0.31 120

19 Pekerjaan Mesin Rp 1,050,000.00 0.064 0.03 0.03 Hari Kalender

JUMLAH
Rp 1,643,809,317.928 100.000
Rencana minggu ini 0.78 0.90 0.90 0.90 2.34 2.34 4.31 4.31 4.31 4.31 7.26 7.39 13.47 13.47 11.71 10.80 9.74 2.97 2.51 1.09 1.09 1.09

Komulatif minggu ini 0.78 1.68 2.58 3.48 5.82 8.16 12.47 16.78 21.09 25.40 32.66 40.05 53.52 66.99 78.71 89.51 99.24 102.22 104.73 105.82 106.91 100.00

Mengetahui Disetujui Pati, Desember 2013


Pimpinan Proyek Konsultan Pengawas Dibuat oleh

Sumardi,ST Ir.Suharyono,MM PT. Surya Unggul Nusa


TIME SCHEDULE

Proyek : PEMBANGUNAN GEDUNG KANTOR DISPERTANAK

Lokasi : KABUPATEN PATI

Tahun Anggaran : 2013

no Uraian pekerjaan Jumlah harga Bobot(%) MP 1 2 3 4 5 6 7 8 9 10 11

15 s/d 21 22 s/d 28 29 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 1 2 s/d 8 9 s/d 15 16 s/d 22 23 s/d 29

1 Pekerjaan Persiapan Rp 280,971,639.606 17.427 260 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79
2 Pekerjaan Tanah Rp 6,177,249.375 0.383 105 0.13 0.13 0.13
3 Pekerjaan Pondasi Rp 51,259,345.830 3.179 156 1.59 1.59
4 Pekerjaan Beton Lantai 1 Rp 41,813,537.799 2.594 70 0.86 0.86 0.86
5 Pekerjaan Beton lantai 2 Rp 41,813,537.799 2.594 70 0.86 0.86
6pekerjaan Pembesian Rp 95,510,508.490 5.924 89 0.987 0.987 0.987 0.987 0.987
7Pekerjaan Bekisting Rp 36,989,276.621 2.294 112 0.382 0.382 0.382 0.382 0.382
8 Pekerjaan Dinding Rp 178,217,619.258 11.054 391
9 Pekerjaan Baja Rp 279,283,164.699 17.323 884
10 Pekerjaan Penutup Lantai Rp 193,637,327.152 12.010 215 3.00 3.00
11 Pekerjaan Kusen Rp 30,490,209.750 1.891 111
12 Pekerjaan Baja Rp 279,283,164.699 17.323 237
13 Pekerjaan Penutup Atap Rp 25,419,528.750 1.577 114
14 Pekerjaan Penggantung Kunci dan Kaca Rp 11,273,916.115 0.699 49
15 0 Rp - 0.000 97
16 Pekerjaan Mekanikal Elektrikal Rp 8,601,000.000 0.533 19 0.13 0.13 0.13
17 Pekerjaan Sanitasi Rp 35,042,790.121 2.174 54
18 Pekerjaan Finisihing Rp 15,403,945.365 0.955 74
20 Pekerjaan Mesin Rp 1,050,000.000 0.065
JUMLAH Rp 1,612,237,761.428 100.000
Rencana minggu ini 0.79 0.92 0.92 0.92 2.38 2.38 3.03 3.03 3.16 6.16 6.16
Komulatif minggu ini 0.79 1.71 2.63 3.55 5.93 8.32 11.34 14.37 17.53 23.69 29.85
Man Power 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Realisasi minggu ini
Komulatif minggu ini

Mengetahui Disetujui
DULE

Keterangan

12 13 14 15 16 17 18 19 20 21 22

30 s/d 5 6 s/d 12 13 s/d 19 20 s/d 26 27 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 31 1 s/d 7

0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79

Kalender : 154 hari

0.86
0.987
0.382
3.68 3.68 3.68
5.77 5.77 5.77
3.00 3.00 Kegiatan Kritis
0.47 0.47 0.47 0.47
8.66 8.66
0.79 0.79
0.23 0.23 0.23
0.00 0.00
0.13
1.09 1.09
0.32 0.32 0.32
0.03 0.03

6.40 13.49 10.48 10.25 11.01 11.01 2.05 2.05 1.11 1.11 1.11
36.25 49.74 60.22 70.47 81.48 92.50 94.55 96.60 97.71 98.82 99.93
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000

Semarang, Januari 2015


Pekerjaan Persiapan 7 Pekerjaan Tanah
START

154 21

0 0 0 154 7 28
keterangan Pekerjaan LT

Jalur Kritis Durasi

ESD EFD

Jalur Non KRITIS

ESD = Aawal Mula Pekerjaan

EFD = Akhir Dari Pekerjaan

LT = Lead Time

Durasi = Lamanya Pekerjaan


pek,langit langit 42

14

Pek. ME 21 77 91 Pekerjaan Sanitasi 4

28 14

56 84 21 Pek. Kunci dan Kaca 42 119 147

21

77 98 Pekerjaan Mesin 8

14 14

70 84

21 Pekerjaan Pondasi 14 Pekerjaan Beton 21 Pek. Penutup Lantai 14 pek kusen 42 Pekerjaan Finising
FINISH

14 42 28 21 21

28 42 42 84 14 42 28 49 42 Pekerjaan Lain-lain 7 147 168 168 168

42 14
70 84

Pekerjaan dinding 21 Pekerjaan Baja 14 Pek. Penutup Atap 14

21 14 14

84 105 105 119 133 147

LT Pekerjaan 14 pek,langit langit 14

Durasi 14

ESD EFD 119 133


NETWORK PLANNING
Pek. ME 14

42

56 98

14

Pekerjaan Finishing
Pekerjaan Persiapan 7 Pekerjaan Tanah 21 Pekerjaan Pondasi 14 Pekerjaan Beton LT 1 21 Pekerjaan lantai 14 Pek. Kunci dan kaca 42 Pek. Sanitasi 14
START FINISH
21
154 21 14 21 42 14 14

0 0 0 154 7 28 28 42 42 63 63 105 77 91 119 133 133 154 154 154

21 14
pek plesteran 0 Pekerjaan Lain-lain

21 14

84 105 119 133

0 0 14 14
Pekerjaan Beton Lt 2 21 pekerjaan dinding 14 pek baja 21 pek,penutup atap Pekerjaan Mesin
keterangan
Pekerjaan LT Pekerjaan 21 21 14 21 14

Jalur Kritis Durasi Durasi 63 84 84 105 98 112 119 140 0 119 133

ESD EFD ESD EFD 0


Jalur Non KRITIS

ESD = Aawal Mula Pekerjaan Pekerjaan kusen 0


EFD = Akhir Dari Pekerjaan 42

LT = Lead Time 98 140

Durasi = Lamanya Pekerjaan


0 0
0 - 7
Pek.Persiapan
start
7

0 - 7

ESD - EFD

KEGIATAN

DURASI

LSD - LFD
FF TF

0 0

0 0 0 - 7
Pek.Persiapan 7
start
7

0 - 7

FF TF

ESD - EFD
KEGIATAN
DURASI

LSD - LFD

Jalur Kritis
7 - 28 28
7 Pek.Tanah Pek.Pondasi
21 14

7 - 28 28
FF TF FF TF

0 0 0 0

7 - 28 28 - 42
Pek.Tanah Pek.Pondasi
21 14

7 - 28 28 - 42

FF = Free Float

TF = Total Float
ESD = Earliest Start Date
EFD= Earliest Finish date

LSD = Latest Start Date

LFD= Latest Finish Date


- 42 42 - 63
Pek.Pondasi Pek.Beton Lt 1
14 21
- 42 42 - 63
FF TF FF

0 0 0

42 - 56 56
Pek.Pembesian Pek.Bekisting
14 14

49 - 63 70
63 - 91

Pek.Penutup Lantai

28

77 - 105

84 - 98

Pek.penggantung kunci

14

105 - 119

63 - 84 84 - 105
Pek.Beton Lt 2 Pek.Dinding
21 21

63 - 84 84 - 105

84 - 105
Pek.Plesteran

21

98 - 119

63 - 91 91 - 105
Pek.ME Pek.Sanitasi
28 14
77 - 105 105 - 119
TF FF TF

0 0 0

- 70 42 - 63
Pek.Bekisting Pek.Beton Lt 1
14 21
- 84 42 - 63
91 - 119

Pek.Kusen

28

105 - 133

98

` Pek.Mesin

14

119

105 - 119 119


Pek.Baja Pek.Penutup ata
14 14

105 - 119 119

105 - 119
Pek.Langit langit

14

119 - 133

105 - 119
Pek.Lain - lain
14
119 - 133

NETWORK PLANNING
PRECEDENCE DIAGRAM

FF TF

14 14

63 - 91
Pek.Penutup Lantai
28

77 - 105
FF TF FF TF

0 0 0 0

63 - 84 84 - 105
Pek.Beton Lt 2 Pek.Dinding
21 21

63 - 84 84 - 105

FF TF FF TF

14 14 14 14
63 - 91 91 - 105
Pek.ME Pek.Sanitasi
28 14

77 - 105 105 - 119


- 112

Pek.Mesin

14

- 133

- 133 133 - 154


Pek.Penutup atap Pek.Finishing
14 21
- 133 133 - 154
FF TF

14 14

91 - 119
Pek.Kusen
28

105 - 133

FF TF FF TF

21 21 21 21

84 - 98 98 - 112
Pek.penggantung kunci Pek.Mesin
14 14

105 - 119 119 - 133

FF TF

0 0

105 - 119
Pek.Baja
14

105 - 119

FF TF FF TF

0 0 0 0

84 - 105 105 - 119


Pek.Plesteran Pek.Langit langit

21 14

98 - 119 119 - 133

FF TF

14 14
105 - 119
Pek.Lain - lain
14

119 - 133
154 - 154
FINISH

154 - 154
FF TF FF TF

0 0 0 0

119 - 133 133 - 154


Pek.Penutup atap Pek.Finishing
14 21

119 - 133 133 - 154


FF TF

0 0

154 - 154
FINISH

154 - 154
Pek.Persiapan
0 0 0 7
start 0
7

ESD - EFD

KEGIATAN
DURASI

LSD - LFD
Pek.Tanah Pek.Pondasi
7 28 28
21 14

56 - 77 77 -
ek.Pondasi Pek.Beton Lt 1
42 42 63
21

91 91 - 112
63 91
28

98 - 126 Pek.penggantung kunci


84 98
14

140 - 154
Pek.Beton Lt 2 Pek.Dinding
63 84 84 105
21 21

112 - 133 133 - 154

Pek.Plesteran
84 105
21

119 - 140

Pek.ME Pek.Sanitasi
63 91 91 105
28 14

112 - 140 140 - 154


91 119
28

126 - 154 Pek.Mesin


98
` 14

154 -
Pek.Baja Pek.Penutup atap
105 105 105
14 14

154 - 154 154 -


Pek.Langit langit
105 119
14

140 - 154

Pek.Lain - lain
105 105
14

154 - 154
Pek.Mesin
98

154
Penutup atap Pek.Finishing FINISH
105 105 105 105
21

154 154 - 154 154


FINISH
105

- 154
Vol Sat
No Jenis Pekerjaan
Pek. Pek.
I. Pekerjaan Persiapan
1 Permbersihan Lahan 296.525 m2
2 Pembuatan Direksi Keet 32 m2
3 Pembuatan Pagar Keliling 69.9 m
4 Gudang Bahan/Peralatan 9 m2
5 Pemasangan Bouwplank 61.5 m
5 Listrik Penerangan Proyek 1 ls
6 Air Kerja & Air Minum Proyek 1 ls
7 Papan Nama Proyek 1 ls
II. Pekerjaan Tanah
1 Pekerjaan Galian Tanah 111.94 m3
2 Pekerjaan Urugan Tanah Kembali 32.755 m3
III. Pekerjaan Pondasi
1 Pasangan Pondasi Batu Kali 1Pc : 6 Pp 65.205 m3
IV-V Pekerjaan Pasangan
1 Pas.Dinding bata merah 459.425 m2
2 Plesteran 1Pc : 5Pp 918 m2
3 Acian 918 m2
VI. Pekerjaan Kayu
1 Pekerjaan Kusen Pintu dan Jendela 1.53 m3
2 Pekerjaan Daun Pintu 16.26 m2
VII. Pekerjaan Beton
1 Pekerjaan Footplat 0.75 m3
2 Pekerjaan Sloof 5.433 m3
3 Pekerjaan Kolom 14.67 m3
4 Pekerjaan Balok 14.258 m3
5 Plat Lantai 34.503 m3
6 Pekerjaan Tangga 4.388 m3
VIII Pekerjaan Pembesian
1 Pembesian Footplat 43.6906 kg
2 Pembesian Sloof 140.2115 kg
3 Pembesian Kolom 232.9957 kg
4 Pembesian Balok 179.63 kg
5 Pembesian Lantai 15.1267 kg
6 Pembesian Tangga 12.9365 kg
IX. Pekerjaan Bekisting
1 Bekisting Footplat 4.8 m²
2 Bekisting Sloof 18.113 m²
3 Bekisting Kolom 31.776 m²
4 Bekisting Balok 17.305 m²
5 Bekisting Lantai 23.8025 m²
6 Bekisting Tangga 1.5859 m²
X. Pekerjaan Penutup Atap dan Langit - Langit
1 Pemasangan Atap Genteng Beton 231.875 m2
2 Pemasangan Nok Genteng Beton 64.39 m2
3 Pekerjaan Plafond Gypsum Board 340.640 m2
4 Pekerjaan List Gypsum 266.300 m2
XII. Pekerjaan Sanitair
1 Pasangan Closet Duduk 4 buah
2 Pasangan Westafel Meja 2 buah
3 Urinoir 1 unit
4 kran air biasa 9 buah
6 Pasangan Floor Drain 8 buah
7 Pipa PVC 3/4" 74.05 m'
8 Pipa PVC 2" 30.5 m'
9 Pipa PVC 3" 28.75 m'
10 Tandon Air 1 buah
11 Septictank kapasitas 5 m3 1 buah
XIII Pekerjaan Baja dan Alumunium
1 Pekerjaan kuda-kuda baja profil ┘└ 70.70.7 299.997 kg
2 Pekerjaan kuda-kuda baja profil ┘└ 60.60.6 198.643 kg
3 Pekerjaan kuda-kuda baja profil ┘└ 50.50.5 53.911 kg
4 Pekerjaan kuda-kuda baja profil ┘└ 40.40.4 84.7 kg
5 Pekerjaan baja gording atap 944.64 kg
6 Pekerjaan baja track stang 1.425 kg
7 Pipa galvanis Ø4” tp 5 mm’ 203.28 kg
8 Usuk Baja Ringan C 75/100 2204.16 kg
9 Reng Baja Ringan C 75/100 3660.48 kg
10 Pekerjaan Kusen dan Daun pintu Alumunium 23.72 m2
XIV. Pekerjaan penggantung kunci dan Kaca
1 Kunci Tanam Biasa 12 buah
2 Engsel Pintu dan jendela 80 buah
3 Engsel Kait Angin 89 buah
4 Pemasangan Grendel 48 buah
5 Pekerjaan Kaca 5 mm 13.416 m2
6 Pekerjaan cermin 5 mm 2 buah
XV. Pekerjaan Penutup Lantai
1 Keramik Tile 40 x 40 polished 312.375 m2
2 Keramik Tile 30 x 30 polished 12 m2
3 Keramik kamar mandi 20 x 20 58.857 m2
XVI. Pekerjaan Elektrikal Mekanikal
1 lampu gantung 16 buah
2 Lampu SL 18 watt 9 buah
3 Lampu Baret + TL. Ring 32 W 20 buah
4 Lampu Pijar 40 W 11 buah
5 TL 2 x 18W 8 buah
6 Lampu Exterior Sudut 19 buah
7 Saklar Tunggal 11 buah
8 Saklar Ganda 8 buah
9 Stop Kontak 19 buah
MAN POWER

Jumlah Tenaga Kerja


NO URAIAN PEKERJAAN KODE SATUAN VOLUME
Pekerja K. Tukang T. Kayu T. Besi T. Batu T. Ledeng T. Cat Mandor T.listrik

I PEKERJAAN PERSIAPAN
1 Permbersihan Lahan 6.8 m2 296.525 30 15
2 Pembuatan Direksi Keet 6.5 m2 32.000 64 10 64 32 2
3 Pembuatan Pagar Keliling 6.4 m2 69.900 14 1 28 1

Total
II PEKERJAAN TANAH
1 Pekerjaan Galian Tanah 6.1 m 3
111.940 84 3
2 Pekerjaan Urugan Tanah Kembali - m3 32.755 16 2

Total

III PEKERJAAN PONDASI


1 Pasangan Pondasi Batu Kali 1Pc : 6 Pp 6.9 m3 65.205 98 5 49 5

Total
IV PEKERJAAN DINDING
1 Pas.Dinding bata merah 6.13 m2 459.43 276 9 92 14
Total
V PEKERJAAN PLESTERAN
1 Plesteran 1Pc : 5Pp 6.3 m2 918.490 367 18 184 20
2 Acian 6.27 m2 918.490 184 9 92 9
Total
VI PEKERJAAN KUSEN
1 Pekerjaan Kusen Pintu dan Jendela 6.5 m2 1.530 9 3 28 0
2 Pekerjaan Daun Pintu 6.12 m2 16.260 16 5 49 1
Total

VII PEKERJAAN BETON


1 Pekerjaan Footplat 6.4 m3 0.750 1 0 0 0
2 Pekerjaan Sloof 6.29 m3 5.433 9 0 1 0
3 Pekerjaan Kolom 6.33 m3 14.670 24 0 4 1
4 Pekerjaan Balok 6.33 m3 14.258 24 0 4 1
5 Plat Lantai 6.3 m3 34.503 57 1 9 3
6 Pekerjaan Tangga 6.31 m3 4.388 1 0 0 0
Total
VIII PEKERJAAN PEMBESIAN
1 Pembesian Footplat 6.4 kg 43.6906 3 0 3 0
2 Pembesian Sloof 6.29 kg 140.212 10 1 10 1
3 Pembesian Kolom 6.33 kg 232.996 16 2 16 1
4 Pembesian Balok 6.33 kg 179.630 13 1 13 1
5 Pembesian Lantai 6.3 kg 15.127 1 0 1 0
6 Pembesian Tangga 6.31 kg 12.937 1 0 1 0

IX PEKERJAAN BEKISTING
1 Bekisting Footplat 6.4 m² 4.800 2 0 1 0
2 Bekisting Sloof 6.29 m² 18.113 9 0 5 0
3 Bekisting Kolom 6.33 m² 31.776 21 1 10 1
4 Bekisting Balok 6.33 m² 17.305 11 1 6 1
5 Bekisting Lantai 6.3 m² 23.803 16 1 8 1
6 Bekisting Tangga 6.31 m² 1.586 1 0 1 0
Total
X PEKERJAAN PENUTUP ATAP
1 Pemasangan Atap Genteng Beton 6.4 m2 231.875 46 2 23 2
2 nok genteng beton 6.4 m2 64.390 26 1 13 1

XI PEKERJAAN LANGIT - LANGIT


1 Pekerjaan Plafond Gypsum Board 6.7 m2 340.640 34 2 17 2
2 Pekerjaan List Gypsum 6.7 m2 266.300 27 1 13 1

TOTAL MAN POWER 61 3 30 0 0 0 0 3 0

XII PEKERJAAN SANITASI


1 Pasangan Closet Duduk 6.36 bh 4.000 13 0 4 1
2 Pasangan Westafel Meja 6.1 bh 2.000 2 0 0 0
3 Urinoir 6.2 bh 1.000 1 0 1 0
4 kran air biasa 6.33 bh 9.000 0 0 4 0
5 Pasangan Floor Drain 6.33 bh 8.000 0 0 1 0
6 Pipa PVC 3/4" 6.35 bh 74.050 3 0 4 0
7 Pipa PVC 2" 6.35 bh 30.500 2 0 3 0
8 Pipa PVC 3" 6.35 bh 28.750 2 0 4 0
9 Tandon Air 6.35 bh 1.000 1 1 1 1
10 Septictank kapasitas 5 m3 6.25 m1 1.000 1 1 1 1

TOTAL MAN POWER 25 2 0 0 9 14 0 3 0

XIII PEKERJAAN BESI & ALUMINIUM


Pekerjaan kuda-kuda baja profil ┘└ 70.70.7 6.11 kg 299.997 18 2 18 1
1 Pekerjaan kuda-kuda baja profil ┘└ 60.60.6 6.13 kg 53.911 3 0 3 0
2 Pekerjaan kuda-kuda baja profil ┘└ 50.50.5 6.13 kg 84.700 5 1 5 0
3 Pekerjaan kuda-kuda baja profil ┘└ 40.40.4 6.13 kg 84.700 5 1 5 0
4 Pekerjaan baja gording atap 6.11 kg 944.640 57 6 57 3
5 Pekerjaan baja track stang 6.12 kg 1.425 0 0 0 0
6 Pipa galvanis Ø4” tp 5 mm’ 6.12 kg 203.280 27 5 12 1
7 Pekerjaan Kusen dan Daun pintu Alumunium 23.72 kg 23.720 1 0 1 0
TOTAL MAN POWER 117 14 0 101 0 0 0 5 0

XIV PEKERJAAN KUNCI & KACA


Kunci Tanam Biasa 6.17 bh 12.000 0 0 6 0
1 Engsel Pintu dan jendela 6.17 bh 80.000 1 1 12 1
2 Engsel Kait Angin 6.5 bh 89.000 1 1 13 1
3 Pemasangan Grendel 6.11 bh 48.000 1 1 7 0
4 Pekerjaan Kaca 5 mm 6.9 m2 13.416 0 0 2 0
5 Pekerjaan cermin 5 mm 6.9 bh 2.000 0 0 0 0
TOTAL MAN POWER 3 3 41 0 0 0 0 2 0

XV PEKERJAAN PENUTUP LANTAI


Keramik Tile 40 x 40 polished 6.9 m2 312.375 78 4 39 4
1 Keramik Tile 30 x 30 polished 6.9 m2 12.000 3 0 2 0
2 Keramik kamar mandi 20 x 20 6.9 m2 58.857 53 3 26 3
3
TOTAL MAN POWER 134 7 0 0 67 0 0 7 0

XVI MEKANIKAL ELEKTRIKAL


1 lampu gantung 6.8 buah 16 0 2
2 Lampu SL 18 watt 6.8 buah 9 0 1
3 Lampu Baret + TL. Ring 32 W 6.8 buah 20 0 3
4 Lampu Pijar 40 W 6.8 buah 11 0 2
5 TL 2 x 18W 6.8 buah 8 0 1
6 Lampu Exterior Sudut 6.8 buah 19 0 3
7 Saklar Tunggal 6.8 buah 11 0 2
8 Saklar Ganda 6.8 buah 8 0 1
9 Stop Kontak 6.8 buah 19 0 3
TOTAL MAN POWER 0 0 0 0 0 0 0 0 18

XVII PEKERJAAN PENGECATAN


Pengecatan Tembok 6.14 m2 459.245 9 3 29 1
1 Pengecatan Plafond 6.1 m2 340.640 7 2 21 1
2
TOTAL MAN POWER 16 5 0 0 0 0 50 2 0
2
4.12 2.62
1.5

0.6 19.8 64.944 129.8116


10.8644 33 108.24
3.296118929893 6 19.77671 3.28 64.867621

18.876 2 37.752
0 0 0
0 0 0
0 0 0

37.752

0.786 5.47 6.256


Jumlah Hari Produktivitas

35

21

You might also like