Rab
Rab
VI.1 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6 189,596.00 208,375.75
A Tenaga 51,700.00 56,950.00
L.01 0.6 OH Pekerja 55000 60000 33,000.00 36,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 80,000.00 85,000.00 1,600.00 1,700.00
L.04 0.03 OH Mandor 70,000.00 75,000.00 2,100.00 2,250.00
B Bahan 120,660.00 132,482.50
140 Buah Bata Merah 520 575 72,800.00 80,500.00
18.5 Kg Portland Semen (PC) 1,400.00 1,425.00 25,900.00 26,362.50
0.122 m3 Pasir Pasang (PP) 180,000.00 210,000.00 21,960.00 25,620.00
C PERALATAN
D Jumlah A + B + C 172360 189432.5
E Overhead & Profit (contoh 1 0.1 17,236.00 18,943.25
F Harga Satuan Pekerjaan (D+E) 189,596.00 208,375.75
VI.2 1 m2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II 673,640.00 724,625.00
A Tenaga 307,500.00 345,750.00
L.01 1.00 OH Pekerja 55,000.00 60,000.00 55,000.00 60,000.00
L.02 3.00 OH Tukang Kayu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.30 OH Kepala Tukang 80,000.00 90,000.00 24,000.00 27,000.00
L.04 0.05 OH Mandor 70,000.00 75,000.00 3,500.00 3,750.00
B Bahan 304,900.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.050 kg Lem Kayu 18,000.00 20,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 612,400.00 658,750.00
E Overhead & Profit (contoh 1 10% 61,240.00 65,875.00
F Harga Satuan Pekerjaan (D+E) 673,640.00 724,625.00
C PERALATAN
D Jumlah A + B + C 74,450.00 80,375.00
E Overhead & Profit (contoh 1 10% 7,445.00 8,037.50
F Harga Satuan Pekerjaan (D+E) 81,895.00 88,412.50
XVIII.2 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 16,586.90 19,257.70
2 lap. Cat Penutup)
A Tenaga 6,539.00 7,347.00
L.01 0.020 OH Pekerja 55,000.00 60,000.00 1,100.00 1,200.00
L.02 0.063 OH Tukang Cat 75,000.00 85,000.00 4,725.00 5,355.00
L.03 0.006 OH Kepala Tukang 80,000.00 90,000.00 504.00 567.00
L.04 0.003 OH Mandor 70000 75000 210.00 225.00
B Bahan 8,540.00 10,160.00
0.1000 Kg Plamir 24,000.00 32,000.00 2,400.00 3,200.00
0.1000 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.2600 Kg Cat Penutup 2 kali 19,000.00 21,000.00 4,940.00 5,460.00
C PERALATAN
D Jumlah A + B + C 15,079.00 17,507.00
E Overhead & Profit (contoh 10%) 0.1 1,507.90 1,750.70
F Harga Satuan Pekerjaan (D+E) 16586.9 19257.7
Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 67,100.00
Rp 53,000.00
Rp 53,000.00
Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 47,100.00
Rp 33,000.00
Rp 33,000.00
Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 79,100.00
Rp 65,000.00
Rp 65,000.00
Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 104,100.00
Rp 90,000.00
Rp 90,000.00
Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 131,625.00
Rp 129,000.00
Rp 129,000.00
Rp 2,625.00
Rp 1,275.00
Rp 1,350.00
Rp 29,100.00
Rp 15,000.00
Rp 15,000.00
Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 29,100.00
Rp 15,000.00
Rp 15,000.00
Rp 14,100.00
Rp 12,750.00
Rp 1,350.00
Rp 17,625.00
Rp 15,000.00
Rp 15,000.00
Rp 2,625.00
Rp 1,275.00
Rp 1,350.00
Rp 1,050,000.00
RENCANA ANGGARAN BIAYA
PEKERJAAN RUMAH TINGGAL 2 LANTAI
SEMARANG
TAHUN ANGGARAN 2016
Vol Sat Harga Satuan Harga X. Pekerjaan Penutup Atap dan Langit - Langit
No Jenis Pekerjaan
Pek. Pek. Pekerjaan Pekerjaan 1 Pemasangan Atap Genteng Beton 231.875 m2 Rp 109,626.00 Rp 25,419,528.75
I. Pekerjaan Persiapan 2 Pemasangan Nok Genteng Beton 64.39 m2 Rp 112,486.00 Rp 7,242,973.54
1 Permbersihan Lahan 296.525 m2 Rp 11,550.00 Rp 3,424,863.75 3 Pekerjaan Plafond Gypsum Board 340.640 m2 Rp 40,084.00 Rp 13,654,213.76
2 Pembuatan Direksi Keet 32 m2 Rp 2,823,151.38 Rp 90,340,844.00 4 Pekerjaan List Gypsum 266.300 m2 Rp 40,084.00 Rp 10,674,369.20
3 Pembuatan Pagar Keliling 69.9 m Rp 2,030,239.94 Rp 141,913,771.98 JUMLAH Rp 56,991,085.25
4 Gudang Bahan/Peralatan 9 m2 Rp 3,228,682.88 Rp 29,058,145.88
5 Pemasangan Bouwplank 61.5 m Rp 93,236.00 Rp 5,734,014.00 XIV. Pekerjaan penggantung kunci dan Kaca
5 Listrik Penerangan Proyek 1 ls Rp 5,000,000.00 Rp 5,000,000.00 1 Kunci Tanam Biasa 12 buah Rp 219,312.50 Rp 2,631,750.00
6 Air Kerja & Air Minum Proyek 1 ls Rp 5,000,000.00 Rp 5,000,000.00 2 Engsel Pintu dan jendela 80 buah Rp 31,968.75 Rp 2,557,500.00
7 Papan Nama Proyek 1 ls Rp 500,000.00 Rp 500,000.00 3 Engsel Kait Angin 89 buah Rp 36,410.00 Rp 3,240,490.00
JUMLAH Rp 280,971,639.61 4 Pemasangan Grendel 48 buah Rp 29,260.00 Rp 1,404,480.00
5 Pekerjaan Kaca 5 mm 13.416 m2 Rp 107,311.88 Rp 1,439,696.12
II. Pekerjaan Tanah 6 Pekerjaan cermin 5 mm 2 buah Rp 349,311.88 Rp 698,623.75
1 Pekerjaan Galian Tanah 111.94 m3 Rp 51,562.50 Rp 5,771,906.25 JUMLAH Rp 11,273,916.12
2 Pekerjaan Urugan Tanah Kembali 32.755 m3 Rp 12,375.00 Rp 405,343.13
JUMLAH Rp 6,177,249.38
XVI. Pekerjaan Elektrikal Mekanikal
III. Pekerjaan Pondasi 1 lampu gantung 16 buah Rp 185,000.00 Rp 2,960,000.00
1 Pasangan Pondasi Batu Kali 1Pc : 6 Pp 65.205 m3 Rp 786,126.00 Rp 51,259,345.83 2 Lampu SL 18 watt 9 buah Rp 53,000.00 Rp 477,000.00
JUMLAH Rp 51,259,345.83 3 Lampu Baret + TL. Ring 32 W 20 buah Rp 33,000.00 Rp 660,000.00
4 Lampu Pijar 40 W 11 buah Rp 65,000.00 Rp 715,000.00
VII Pekerjaan Beton 5 TL 2 x 18W 8 buah Rp 90,000.00 Rp 720,000.00
1 Pekerjaan Footplat 0.75 m3 Rp 1,152,003.31 Rp 864,002.49 6 Lampu Exterior Sudut 19 buah Rp 129,000.00 Rp 2,451,000.00
2 Pekerjaan Sloof 5.433 m3 Rp 1,134,868.78 Rp 6,165,742.07 7 Saklar Tunggal 11 buah Rp 15,000.00 Rp 165,000.00
3 Pekerjaan Kolom 14.67 m3 Rp 1,152,003.31 Rp 16,899,888.63 8 Saklar Ganda 8 buah Rp 21,000.00 Rp 168,000.00
4 Pekerjaan Balok 14.258 m3 Rp 1,152,003.31 Rp 16,425,263.26 9 Stop Kontak 19 buah Rp 15,000.00 Rp 285,000.00
5 Plat Lantai 34.503 m3 Rp 1,134,868.78 Rp 39,156,377.44 JUMLAH Rp 8,601,000.00
6 Pekerjaan Tangga 4.388 m3 Rp 1,134,868.78 Rp 4,979,804.20
JUMLAH Rp 83,627,075.60 XVII. Pekerjaan Mesin
1 Pompa Air 100 W 1 buah Rp 1,050,000.00 Rp 1,050,000.00
VIII Pekerjaan Pembesian JUMLAH Rp 1,050,000.00
1 Pembesian Footplat 43.6906 kg Rp 152,916.88 Rp 6,681,030.34
2 Pembesian Sloof 140.2115 kg Rp 152,916.88 Rp 21,440,705.46 XII. Pekerjaan Sanitair
3 Pembesian Kolom 232.9957 kg Rp 152,916.88 Rp 35,628,976.05 1 Pasangan Closet Duduk 4 buah Rp 2,082,949.00 Rp 8,331,796.00
4 Pembesian Balok 179.63 kg Rp 152,916.88 Rp 27,468,459.58 2 Pasangan Westafel Meja 2 buah Rp 771,072.50 Rp 1,542,145.00
5 Pembesian Lantai 15.1267 kg Rp 152,916.88 Rp 2,313,127.80 3 Urinoir 1 unit Rp 725,615.00 Rp 725,615.00
6 Pembesian Tangga 12.9365 kg Rp 152,916.88 Rp 1,978,209.25 4 kran air biasa 9 buah Rp 80,943.78 Rp 728,493.98
JUMLAH Rp 95,510,508.49 6 Pasangan Floor Drain 8 buah Rp 88,412.50 Rp 707,300.00
7 Pipa PVC 3/4" 74.05 m' Rp 22,811.25 Rp 1,689,173.06
IX. Pekerjaan Bekisting 8 Pipa PVC 2" 30.5 m' Rp 44,375.83 Rp 1,353,462.92
1 Bekisting Footplat 4.8 m² Rp 153,516.00 Rp 736,876.80 9 Pipa PVC 3" 28.75 m' Rp 77,036.67 Rp 2,214,804.17
2 Bekisting Sloof 18.113 m² Rp 163,966.00 Rp 2,969,916.16 10 Tandon Air 1 buah Rp 2,500,000.00 Rp 2,500,000.00
3 Bekisting Kolom 31.776 m² Rp 400,378.00 Rp 12,722,411.33 11 Septictank kapasitas 5 m3 1 buah Rp 15,250,000.00 Rp 15,250,000.00
4 Bekisting Balok 17.305 m² Rp 419,518.00 Rp 7,259,758.99 JUMLAH Rp 35,042,790.12
5 Bekisting Lantai 23.8025 m² Rp 558,778.00 Rp 13,300,313.35
6 Bekisting Tangga 1.5859 m² Rp 378,928.00 Rp 600,941.92 XVIII. Pekerjaan Finisihing
JUMLAH Rp 36,989,276.62 1 Pengecatan Tembok 459.245 m2 Rp 19,257.70 Rp 8,844,002.44
2 Pengecatan Plafond 340.64 m2 Rp 19,257.70 Rp 6,559,942.93
JUMLAH Rp 15,403,945.36
I PEKERJAAN PERSIAPAN
1 Permbersihan Lahan 6.8 m2 296.525 30
2 Pembuatan Direksi Keet 6.5 m2
32.000 64 10
3 Pembuatan Pagar Keliling 6.4 m2
69.900 14 1
TOTAL MAN POWER 108 11
II PEKERJAAN TANAH
1 Pekerjaan Galian Tanah 6.1 m3 111.940 84
2 Pekerjaan Urugan Tanah Kembali - m3
32.755 16
IV PEKERJAAN DINDING
1 Pas.Dinding bata merah 6.13 m2 459.43 276 9
TOTAL MAN POWER 276 9
V PEKERJAAN PLESTERAN
1 Plesteran 1Pc : 5Pp 6.3 m2 918.490 367 18
2 Acian 6.27 m2 918.490 184 9
TOTAL MAN POWER 551 28
VI PEKERJAAN KUSEN
1 Pekerjaan Kusen Pintu dan Jendela 6.5 m2 1.530 9 3
2 Pekerjaan Daun Pintu 6.12 m2 16.260 16 5
IX PEKERJAAN BEKISTING
1 Bekisting Footplat 6.4 m² 4.800 2 0
2 Bekisting Sloof 6.29 m² 18.113 9 0
3 Bekisting Kolom 6.33 m² 31.776 21 1
4 Bekisting Balok 6.33 m² 17.305 11 1
5 Bekisting Lantai 6.3 m² 23.803 16 1
6 Bekisting Tangga 6.31 m² 1.586 1 0
TOTAL MAN POWER 61 3
15
64 32 2
28 1
92 0 32 0 0 18 0
3
2
0 0 0 0 0 4 0
49 5
0 0 49 0 0 5 0
92 14
0 0 92 0 0 14 0
184 20
92 9
0 0 276 0 0 29 0
28 0
49 1
76 0 0 0 0 1 0
0 0
1 0
4 1
4 1
9 3
0 0
19 0 0 0 0 5 0
3 0
10 1
16 1
13 1
1 0
1 0
0 44 0 0 0 3 0
1 0
5 0
10 1
6 1
8 1
1 0
31 0 0 0 0 3 0
23 2
13 1
36 0 0 0 0 3 0
17 2
13 1
30 0 0 0 0 3 0
4 1
0 0
1 0
4 0
1 0
4 0
3 0
4 0
1 1
1 1
0 0 9 14 0 3 0
18 1
3 0
5 0
5 0
57 3
0 0
12 1
1 0
0 101 0 0 0 5 0
6 0
12 1
13 1
7 0
2 0
0 0
41 0 0 0 0 2 0
39 4
2 0
26 3
0 0 67 0 0 7 0
2
1
3
2
1
3
2
1
3
0 0 0 0 0 0 18
29 1
21 1
0 0 0 0 50 2 0
2
4.12 2.62
1.5
18.876 2 37.752
0 0 0
0 0 0
0 0 0
37.752
TERBILANG :
REKAP MAN POWER
Lokasi : SEMARANG
15 s/d 21 22 s/d 28 29 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 1 2 s/d 8 9 s/d 15 16 s/d 22 23 s/d 29 30 s/d 5 6 s/d 12 13 s/d 19 20 s/d 26 27 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 31 1 s/d 7 8 s/d 14 15 s/d 21 22 s/d 28
2 Pekerjaan Tanah Rp 6,177,249.375 0.453 105 0.091 0.091 0.091 0.091 0.091 Kalender : 168 hari
4 Pekerjaan Beton Rp 83,627,075.597 6.129 140 0.766 0.766 0.766 0.766 0.766 0.766 0.766 0.766 Masa Pemeliharaan : 60 hari
Rp 95,510,508.490
5 Pekerjaan Pembesian 7.000 89 0.875 0.875 0.875 0.875 0.875 0.875 0.875 0.875
Rp 36,989,276.621
6 Pekerjaan Bekisting 2.711 112 0.339 0.339 0.339 0.339 0.339 0.339 0.339 0.339
7 Pekerjaan Dinding Rp 178,217,619.258 13.061 391 1.633 1.633 1.633 1.633 1.633 1.633 1.633 1.633
8 Pekerjaan Penutup Lantai Rp 193,637,327.152 14.191 215 2.365 2.365 2.365 2.365 2.365 2.365
10 Pekerjaan Baja Rp 279,283,164.699 20.467 237 6.822 6.822 6.822 Kegiatan Kritis
12 Pekerjaan Penggantung Kunci dan Kaca Rp 11,273,916.115 0.826 49 0.207 0.207 0.207 0.207
15 Pekerjaan Sanitasi Rp 35,042,790.121 2.568 54 0.428 0.428 0.428 0.428 0.428 0.428
0 5 10 15 20 25
Rencana minggu ini 0.858 0.091 0.110 0.110 0.110 0.110 1.252 1.252 3.617 5.090 5.090 6.722 12.800 12.800
Row 29 10.863 5.433 5.433 3.453 2.267 1.011 0.583 0.898 0.315 0.000
Komulatif minggu ini 0.858 0.949 1.058 1.168 1.278 1.388 2.640 3.892 7.509 12.599 17.689 24.411 37.211 50.012 60.875 66.307 71.740 75.193 77.460 78.471 79.054 79.952 80.267 80.267
Man Power 10.851 31.804 31.804 31.804 31.804 31.804 63.015 63.015 98.849 101.052 101.052 149.866 191.844 191.844 164.988 124.187 124.187 106.708 80.800 56.596 47.618 56.880 20.113 10.851
260 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851 10.851
105 20.954 20.954 20.954 20.954 20.954
156 52.164 52.164 52.164
140 17.479 17.479 17.479 17.479 17.479 17.479 17.479 17.479
391 48.814 48.814 48.814 48.814 48.814 48.814 48.814 48.814
215 35.835 35.835 35.835 35.835 35.835 35.835
111 36.888 36.888 36.888
237 78.866 78.866 78.866
114 38.066 38.066 38.066
49 12.157 12.157 12.157 12.157
19 9.263 9.263
0 0.000 0.000 0.000 0.000
54 8.978 8.978 8.978 8.978 8.978 8.978
74 24.610 24.610 24.610
0.000 0.000
0.000 0.000 0.000 0.000
10.851 31.804 31.804 31.804 31.804 31.804 63.015 63.015 98.849 101.052 101.052 149.866 191.844 191.844 164.988 124.187 124.187 106.708 80.800 56.596 47.618 56.880 20.113 10.851
12.00
MAN POWER
J 10.00
U
M
L
A
H
8.00
T
E
N
A
G
A 6.00
K
E
R
J
A 4.00
2.00
0.00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
MINGGU
TIME SCHEDULE
Lokasi : SEMARANG
15 s/d 21 22 s/d 28 29 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 1 2 s/d 8 9 s/d 15 16 s/d 22 23 s/d 29 30 s/d 5 6 s/d 12 13 s/d 19 20 s/d 26 27 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 31 1 s/d 7 8 s/d 21
1 Pekerjaan Persiapan Rp 280,971,639.61 17.093 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 0.78 Jangka Waktu
Rp 95,510,508.49 5.810
6Pekerjaan Pembesian 1.937 1.937 1.937 1.937 1.937 1.937
Rp 36,989,276.62 2.250
7Pekerjaan Bekisting 0.750 0.750 0.750 0.750 0.750 0.750
8 Pekerjaan Dinding Rp 178,217,619.26 10.842 3.61 3.61 3.61
16 Pekerjaan Mekanikal Elektrikal Rp 8,601,000.00 0.523 0.13 0.13 0.13 0.13 Jangka Waktu
JUMLAH
Rp 1,643,809,317.928 100.000
Rencana minggu ini 0.78 0.90 0.90 0.90 2.34 2.34 4.31 4.31 4.31 4.31 7.26 7.39 13.47 13.47 11.71 10.80 9.74 2.97 2.51 1.09 1.09 1.09
Komulatif minggu ini 0.78 1.68 2.58 3.48 5.82 8.16 12.47 16.78 21.09 25.40 32.66 40.05 53.52 66.99 78.71 89.51 99.24 102.22 104.73 105.82 106.91 100.00
15 s/d 21 22 s/d 28 29 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 1 2 s/d 8 9 s/d 15 16 s/d 22 23 s/d 29
1 Pekerjaan Persiapan Rp 280,971,639.606 17.427 260 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79
2 Pekerjaan Tanah Rp 6,177,249.375 0.383 105 0.13 0.13 0.13
3 Pekerjaan Pondasi Rp 51,259,345.830 3.179 156 1.59 1.59
4 Pekerjaan Beton Lantai 1 Rp 41,813,537.799 2.594 70 0.86 0.86 0.86
5 Pekerjaan Beton lantai 2 Rp 41,813,537.799 2.594 70 0.86 0.86
6pekerjaan Pembesian Rp 95,510,508.490 5.924 89 0.987 0.987 0.987 0.987 0.987
7Pekerjaan Bekisting Rp 36,989,276.621 2.294 112 0.382 0.382 0.382 0.382 0.382
8 Pekerjaan Dinding Rp 178,217,619.258 11.054 391
9 Pekerjaan Baja Rp 279,283,164.699 17.323 884
10 Pekerjaan Penutup Lantai Rp 193,637,327.152 12.010 215 3.00 3.00
11 Pekerjaan Kusen Rp 30,490,209.750 1.891 111
12 Pekerjaan Baja Rp 279,283,164.699 17.323 237
13 Pekerjaan Penutup Atap Rp 25,419,528.750 1.577 114
14 Pekerjaan Penggantung Kunci dan Kaca Rp 11,273,916.115 0.699 49
15 0 Rp - 0.000 97
16 Pekerjaan Mekanikal Elektrikal Rp 8,601,000.000 0.533 19 0.13 0.13 0.13
17 Pekerjaan Sanitasi Rp 35,042,790.121 2.174 54
18 Pekerjaan Finisihing Rp 15,403,945.365 0.955 74
20 Pekerjaan Mesin Rp 1,050,000.000 0.065
JUMLAH Rp 1,612,237,761.428 100.000
Rencana minggu ini 0.79 0.92 0.92 0.92 2.38 2.38 3.03 3.03 3.16 6.16 6.16
Komulatif minggu ini 0.79 1.71 2.63 3.55 5.93 8.32 11.34 14.37 17.53 23.69 29.85
Man Power 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
Realisasi minggu ini
Komulatif minggu ini
Mengetahui Disetujui
DULE
Keterangan
12 13 14 15 16 17 18 19 20 21 22
30 s/d 5 6 s/d 12 13 s/d 19 20 s/d 26 27 s/d 3 4 s/d 10 11 s/d 17 18 s/d 24 25 s/d 31 1 s/d 7
0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79
0.86
0.987
0.382
3.68 3.68 3.68
5.77 5.77 5.77
3.00 3.00 Kegiatan Kritis
0.47 0.47 0.47 0.47
8.66 8.66
0.79 0.79
0.23 0.23 0.23
0.00 0.00
0.13
1.09 1.09
0.32 0.32 0.32
0.03 0.03
6.40 13.49 10.48 10.25 11.01 11.01 2.05 2.05 1.11 1.11 1.11
36.25 49.74 60.22 70.47 81.48 92.50 94.55 96.60 97.71 98.82 99.93
0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
154 21
0 0 0 154 7 28
keterangan Pekerjaan LT
ESD EFD
LT = Lead Time
14
28 14
21
77 98 Pekerjaan Mesin 8
14 14
70 84
21 Pekerjaan Pondasi 14 Pekerjaan Beton 21 Pek. Penutup Lantai 14 pek kusen 42 Pekerjaan Finising
FINISH
14 42 28 21 21
42 14
70 84
21 14 14
Durasi 14
42
56 98
14
Pekerjaan Finishing
Pekerjaan Persiapan 7 Pekerjaan Tanah 21 Pekerjaan Pondasi 14 Pekerjaan Beton LT 1 21 Pekerjaan lantai 14 Pek. Kunci dan kaca 42 Pek. Sanitasi 14
START FINISH
21
154 21 14 21 42 14 14
21 14
pek plesteran 0 Pekerjaan Lain-lain
21 14
0 0 14 14
Pekerjaan Beton Lt 2 21 pekerjaan dinding 14 pek baja 21 pek,penutup atap Pekerjaan Mesin
keterangan
Pekerjaan LT Pekerjaan 21 21 14 21 14
Jalur Kritis Durasi Durasi 63 84 84 105 98 112 119 140 0 119 133
0 - 7
ESD - EFD
KEGIATAN
DURASI
LSD - LFD
FF TF
0 0
0 0 0 - 7
Pek.Persiapan 7
start
7
0 - 7
FF TF
ESD - EFD
KEGIATAN
DURASI
LSD - LFD
Jalur Kritis
7 - 28 28
7 Pek.Tanah Pek.Pondasi
21 14
7 - 28 28
FF TF FF TF
0 0 0 0
7 - 28 28 - 42
Pek.Tanah Pek.Pondasi
21 14
7 - 28 28 - 42
FF = Free Float
TF = Total Float
ESD = Earliest Start Date
EFD= Earliest Finish date
0 0 0
42 - 56 56
Pek.Pembesian Pek.Bekisting
14 14
49 - 63 70
63 - 91
Pek.Penutup Lantai
28
77 - 105
84 - 98
Pek.penggantung kunci
14
105 - 119
63 - 84 84 - 105
Pek.Beton Lt 2 Pek.Dinding
21 21
63 - 84 84 - 105
84 - 105
Pek.Plesteran
21
98 - 119
63 - 91 91 - 105
Pek.ME Pek.Sanitasi
28 14
77 - 105 105 - 119
TF FF TF
0 0 0
- 70 42 - 63
Pek.Bekisting Pek.Beton Lt 1
14 21
- 84 42 - 63
91 - 119
Pek.Kusen
28
105 - 133
98
` Pek.Mesin
14
119
105 - 119
Pek.Langit langit
14
119 - 133
105 - 119
Pek.Lain - lain
14
119 - 133
NETWORK PLANNING
PRECEDENCE DIAGRAM
FF TF
14 14
63 - 91
Pek.Penutup Lantai
28
77 - 105
FF TF FF TF
0 0 0 0
63 - 84 84 - 105
Pek.Beton Lt 2 Pek.Dinding
21 21
63 - 84 84 - 105
FF TF FF TF
14 14 14 14
63 - 91 91 - 105
Pek.ME Pek.Sanitasi
28 14
Pek.Mesin
14
- 133
14 14
91 - 119
Pek.Kusen
28
105 - 133
FF TF FF TF
21 21 21 21
84 - 98 98 - 112
Pek.penggantung kunci Pek.Mesin
14 14
FF TF
0 0
105 - 119
Pek.Baja
14
105 - 119
FF TF FF TF
0 0 0 0
21 14
FF TF
14 14
105 - 119
Pek.Lain - lain
14
119 - 133
154 - 154
FINISH
154 - 154
FF TF FF TF
0 0 0 0
0 0
154 - 154
FINISH
154 - 154
Pek.Persiapan
0 0 0 7
start 0
7
ESD - EFD
KEGIATAN
DURASI
LSD - LFD
Pek.Tanah Pek.Pondasi
7 28 28
21 14
56 - 77 77 -
ek.Pondasi Pek.Beton Lt 1
42 42 63
21
91 91 - 112
63 91
28
140 - 154
Pek.Beton Lt 2 Pek.Dinding
63 84 84 105
21 21
Pek.Plesteran
84 105
21
119 - 140
Pek.ME Pek.Sanitasi
63 91 91 105
28 14
154 -
Pek.Baja Pek.Penutup atap
105 105 105
14 14
140 - 154
Pek.Lain - lain
105 105
14
154 - 154
Pek.Mesin
98
154
Penutup atap Pek.Finishing FINISH
105 105 105 105
21
- 154
Vol Sat
No Jenis Pekerjaan
Pek. Pek.
I. Pekerjaan Persiapan
1 Permbersihan Lahan 296.525 m2
2 Pembuatan Direksi Keet 32 m2
3 Pembuatan Pagar Keliling 69.9 m
4 Gudang Bahan/Peralatan 9 m2
5 Pemasangan Bouwplank 61.5 m
5 Listrik Penerangan Proyek 1 ls
6 Air Kerja & Air Minum Proyek 1 ls
7 Papan Nama Proyek 1 ls
II. Pekerjaan Tanah
1 Pekerjaan Galian Tanah 111.94 m3
2 Pekerjaan Urugan Tanah Kembali 32.755 m3
III. Pekerjaan Pondasi
1 Pasangan Pondasi Batu Kali 1Pc : 6 Pp 65.205 m3
IV-V Pekerjaan Pasangan
1 Pas.Dinding bata merah 459.425 m2
2 Plesteran 1Pc : 5Pp 918 m2
3 Acian 918 m2
VI. Pekerjaan Kayu
1 Pekerjaan Kusen Pintu dan Jendela 1.53 m3
2 Pekerjaan Daun Pintu 16.26 m2
VII. Pekerjaan Beton
1 Pekerjaan Footplat 0.75 m3
2 Pekerjaan Sloof 5.433 m3
3 Pekerjaan Kolom 14.67 m3
4 Pekerjaan Balok 14.258 m3
5 Plat Lantai 34.503 m3
6 Pekerjaan Tangga 4.388 m3
VIII Pekerjaan Pembesian
1 Pembesian Footplat 43.6906 kg
2 Pembesian Sloof 140.2115 kg
3 Pembesian Kolom 232.9957 kg
4 Pembesian Balok 179.63 kg
5 Pembesian Lantai 15.1267 kg
6 Pembesian Tangga 12.9365 kg
IX. Pekerjaan Bekisting
1 Bekisting Footplat 4.8 m²
2 Bekisting Sloof 18.113 m²
3 Bekisting Kolom 31.776 m²
4 Bekisting Balok 17.305 m²
5 Bekisting Lantai 23.8025 m²
6 Bekisting Tangga 1.5859 m²
X. Pekerjaan Penutup Atap dan Langit - Langit
1 Pemasangan Atap Genteng Beton 231.875 m2
2 Pemasangan Nok Genteng Beton 64.39 m2
3 Pekerjaan Plafond Gypsum Board 340.640 m2
4 Pekerjaan List Gypsum 266.300 m2
XII. Pekerjaan Sanitair
1 Pasangan Closet Duduk 4 buah
2 Pasangan Westafel Meja 2 buah
3 Urinoir 1 unit
4 kran air biasa 9 buah
6 Pasangan Floor Drain 8 buah
7 Pipa PVC 3/4" 74.05 m'
8 Pipa PVC 2" 30.5 m'
9 Pipa PVC 3" 28.75 m'
10 Tandon Air 1 buah
11 Septictank kapasitas 5 m3 1 buah
XIII Pekerjaan Baja dan Alumunium
1 Pekerjaan kuda-kuda baja profil ┘└ 70.70.7 299.997 kg
2 Pekerjaan kuda-kuda baja profil ┘└ 60.60.6 198.643 kg
3 Pekerjaan kuda-kuda baja profil ┘└ 50.50.5 53.911 kg
4 Pekerjaan kuda-kuda baja profil ┘└ 40.40.4 84.7 kg
5 Pekerjaan baja gording atap 944.64 kg
6 Pekerjaan baja track stang 1.425 kg
7 Pipa galvanis Ø4” tp 5 mm’ 203.28 kg
8 Usuk Baja Ringan C 75/100 2204.16 kg
9 Reng Baja Ringan C 75/100 3660.48 kg
10 Pekerjaan Kusen dan Daun pintu Alumunium 23.72 m2
XIV. Pekerjaan penggantung kunci dan Kaca
1 Kunci Tanam Biasa 12 buah
2 Engsel Pintu dan jendela 80 buah
3 Engsel Kait Angin 89 buah
4 Pemasangan Grendel 48 buah
5 Pekerjaan Kaca 5 mm 13.416 m2
6 Pekerjaan cermin 5 mm 2 buah
XV. Pekerjaan Penutup Lantai
1 Keramik Tile 40 x 40 polished 312.375 m2
2 Keramik Tile 30 x 30 polished 12 m2
3 Keramik kamar mandi 20 x 20 58.857 m2
XVI. Pekerjaan Elektrikal Mekanikal
1 lampu gantung 16 buah
2 Lampu SL 18 watt 9 buah
3 Lampu Baret + TL. Ring 32 W 20 buah
4 Lampu Pijar 40 W 11 buah
5 TL 2 x 18W 8 buah
6 Lampu Exterior Sudut 19 buah
7 Saklar Tunggal 11 buah
8 Saklar Ganda 8 buah
9 Stop Kontak 19 buah
MAN POWER
I PEKERJAAN PERSIAPAN
1 Permbersihan Lahan 6.8 m2 296.525 30 15
2 Pembuatan Direksi Keet 6.5 m2 32.000 64 10 64 32 2
3 Pembuatan Pagar Keliling 6.4 m2 69.900 14 1 28 1
Total
II PEKERJAAN TANAH
1 Pekerjaan Galian Tanah 6.1 m 3
111.940 84 3
2 Pekerjaan Urugan Tanah Kembali - m3 32.755 16 2
Total
Total
IV PEKERJAAN DINDING
1 Pas.Dinding bata merah 6.13 m2 459.43 276 9 92 14
Total
V PEKERJAAN PLESTERAN
1 Plesteran 1Pc : 5Pp 6.3 m2 918.490 367 18 184 20
2 Acian 6.27 m2 918.490 184 9 92 9
Total
VI PEKERJAAN KUSEN
1 Pekerjaan Kusen Pintu dan Jendela 6.5 m2 1.530 9 3 28 0
2 Pekerjaan Daun Pintu 6.12 m2 16.260 16 5 49 1
Total
IX PEKERJAAN BEKISTING
1 Bekisting Footplat 6.4 m² 4.800 2 0 1 0
2 Bekisting Sloof 6.29 m² 18.113 9 0 5 0
3 Bekisting Kolom 6.33 m² 31.776 21 1 10 1
4 Bekisting Balok 6.33 m² 17.305 11 1 6 1
5 Bekisting Lantai 6.3 m² 23.803 16 1 8 1
6 Bekisting Tangga 6.31 m² 1.586 1 0 1 0
Total
X PEKERJAAN PENUTUP ATAP
1 Pemasangan Atap Genteng Beton 6.4 m2 231.875 46 2 23 2
2 nok genteng beton 6.4 m2 64.390 26 1 13 1
18.876 2 37.752
0 0 0
0 0 0
0 0 0
37.752
35
21