Location : Kawasan Industri Mitra (KIM), Jl. Mitra Barat I Blok G.b Mulya Ciampel, Ciampel, Parungmulya, Kec. Ciampel, Karawang, Jawa Barat 41363
Owner : API (UP. BAPAK PROGO)
I Pekerjaan Pondasi Footplate 80 x 150 x 30 cm Beton K-250, Tulangan Utama Besi D12
1 Pek.Galian Tanah m3 0.86 Rp 250,000.00 Rp 216,000.00 0.01%
2 Pek.Urugan Pasir m3 0.09 Rp 600,000.00 Rp 51,840.00 0.00%
3 Pek.Lantai Kerja m3 0.04 Rp 900,000.00 Rp 38,880.00 0.00%
4 Pek. Bekisting Batako m2 41.40 Rp 155,000.00 Rp 6,417,000.00 0.17%
5 Pek. Beton K-250 m3 10.80 Rp 1,700,000.00 Rp 18,360,000.00 0.48%
6 Pek. Urugan Kembali m3 0.73 Rp 250,000.00 Rp 183,600.00 0.00%
7 Pek. Besi kg 1037.50 Rp 21,500.00 Rp 22,306,250.00 0.59%
Sub Total (Pek. Pondasi Footplate) Rp 47,573,570.00 1.25%
V Pekerjaan Tangga
1 Pekerjaan Pondasi Tangga (Besi , Begisting & Beton K-250) Beton K-250 m3 1.20 Rp 5,500,000.00 Rp 6,600,000.00 0.17%
2 Pekerjaan Beton Tangga (Besi , Begisting & Beton K-250) Bondek 0.70mm m3 4.48 Rp 5,500,000.00 Rp 24,640,000.00 0.65%
3 Pekerjaan Balok beton Tangga (Besi , Begisting & Beton K-250) Wiremess M6 m3 0.84 Rp 5,500,000.00 Rp 4,620,000.00 0.12%
Sub Total Rp 35,860,000.00 0.94%
D. PEKERJAAN ATAP
I Pekerjaan atap Baja ringan
1 Pemasangan Rangka atap bajaringan 0,75 Sni,Mode Cremona rangka m2 451.00 Rp 320,000.00 Rp 144,320,000.00 3.80%
2 Pemasangan doblelayer Aluminium Foil peredam panas m2 451.00 Rp 75,000.00 Rp 33,825,000.00 0.89%
3 Penutup Atap Spandek Zingkalum 0,45 m2 451.00 Rp 145,000.00 Rp 65,395,000.00 1.72%
4 Waterproofing membran bakar EX.SIKA / Standard m2 100.00 Rp 200,000.00 Rp 20,000,000.00 0.53%
IV PEKERJAAN PENGECATAN
1Pek. Pengecatan dinding dgn cat tembok interior Ex Jotun m2 612.15 Rp 48,000.00 Rp 29,383,200.00 0.77%
Pek. Pengecatan dinding dgn cat tembok exterior
2 Ex Jotun m2 331.87 Rp 58,000.00 Rp 19,248,460.00 0.51%
wheatershield
Pek. Pengecatan plafond dengan cat tembok
3 Ex Jotun m2 491.02 Rp 48,000.00 Rp 23,568,960.00 0.62%
interior
Sub Total Rp 72,200,620.00 1.90%
IV PEKERJAAN PENGECATAN
1Pek. Pengecatan dinding dgn cat tembok interior Ex Jotun m2 524.51 Rp 48,000.00 Rp 25,176,480.00 0.66%
Pek. Pengecatan dinding dgn cat tembok exterior
2 Ex Jotun m2 643.33 Rp 58,000.00 Rp 37,313,140.00 0.98%
wheatershield
Pek. Pengecatan plafond dengan cat tembok
3 Ex Jotun m2 837.05 Rp 48,000.00 Rp 40,178,400.00 1.06%
interior
Sub Total Rp 102,668,020.00 2.70%
K. PEKERJAAN LAIN-LAIN
I PEKERJAAN FASAD
1 Pek.Kerawanggan GRC Standard m2 49.30 Rp 750,000.00 Rp 36,975,000.00 0.97%
2 Pek. ACP standard m2 105.48 Rp 900,000.00 Rp 94,932,000.00 2.50%
3 Bata Tempel Ekspose Bata Tempek m2 63.46 Rp 500,000.00 Rp 31,730,000.00 0.84%
4 neon sign ( MASJID AL-HIDAYAH) Neon sign huruf Timbul Akrilic ,Led huruf 15.00 Rp 450,000.00 Rp 6,750,000.00 0.18%
Sub Total Rp 170,387,000.00 4.49%
- Air & listrik kerja ditanggung oleh owner selama pekerjaan berlangsung FURNILIO
- Scope Item Pekerjaan Sesuai Dengan yang tercantum dalam RAB, Jika ada item pekerjaan yang belum masuk ke RAB Approval,
maka akan dihitung ulang berdasarkan kesepakatan bersama
- Harga Penawaran Berlaku 6 Hari Kalender, Terhitung sejak dibuatnya RAB
Pekerjaan Arsitektur
Lantai Satu
1 Volume Pekerjaan Bata Apakah cukup? Hanya 301 m2
2 Begitupun volume plesteran dan acian
Pekerjaan MEP
1 Pekerjaan Plumbing Lantai Dak g ada? Torrent, air bersih air hujan roofdrain dll
2 Bobot RAB MEP bisa di naikkan lagi karena hanya 6,7% dari total project di tambah + sanitary didalamnya. Mungkin
75241000
Project : Pembangunan Kantin & Musola
Location : Kawasan Industri Mitra (KIM), Jl. Mitra Barat I Blok G.b Mulya Ciampel, Ciampel, Parungmulya, Kec. Ciampel, Karawang, Jawa Barat 41363
Owner : API (UP. BAPAK PROGO)
I Pekerjaan Pondasi Footplate 80 x 150 x 30 cm Beton K-250, Tulangan Utama Besi D12
1 Pek.Galian Tanah m3 0.86 Rp 250,000.00 Rp 216,000.00 0.01%
2 Pek.Urugan Pasir m3 0.09 Rp 600,000.00 Rp 51,840.00 0.00%
3 Pek.Lantai Kerja m3 0.04 Rp 900,000.00 Rp 38,880.00 0.00%
4 Pek. Bekisting Batako m2 41.40 Rp 155,000.00 Rp 6,417,000.00 0.15%
5 Pek. Beton K-250 m3 10.80 Rp 1,700,000.00 Rp 18,360,000.00 0.43%
6 Pek. Urugan Kembali m3 0.73 Rp 250,000.00 Rp 183,600.00 0.00%
7 Pek. Besi kg 1037.50 Rp 21,500.00 Rp 22,306,250.00 0.53%
Sub Total (Pek. Pondasi Footplate) Rp 47,573,570.00 1.12%
II Pekerjaan Sloof 20 x 40 cm Beton K-250, Tulangan Utama Besi 6 D13, Cincin Besi ø8 Polos Jarak 18 cm
Beton K-250, Tulangan Utama Besi 16D13, Cincin Besi 8 Polos Jarak 15 cm
III Pekerjaan Kolom Pedestal
Tumpuan, 18cm Lapangan
1 Pek.Beton K-250 m3 5.76 Rp 1,700,000.00 Rp 9,792,000.00 0.23%
2 Pek.Bekisting m2 57.60 Rp 370,000.00 Rp 21,312,000.00 0.50%
3 Pek. Besi Kg 923.11 Rp 21,500.00 Rp 19,846,947.09 0.47%
4 Pek. Grouting Kolom m3 0.36 Rp 5,000,000.00 Rp 1,800,000.00 0.04%
Sub Total Rp 52,750,947.09 1.25%
V Pekerjaan Tangga
1 Pekerjaan Pondasi Tangga (Besi , Begisting & Beton K-250) Beton K-250 m3 1.20 Rp 5,500,000.00 Rp 6,600,000.00 0.16%
2 Pekerjaan Beton Tangga (Besi , Begisting & Beton K-250) Bondek 0.70mm m3 4.48 Rp 5,500,000.00 Rp 24,640,000.00 0.58%
3 Pekerjaan Balok beton Tangga (Besi , Begisting & Beton K-250) Wiremess M6 m3 0.84 Rp 5,500,000.00 Rp 4,620,000.00 0.11%
Sub Total Rp 35,860,000.00 0.85%
II Pekerjaan Struktur Beton Beton K-250, Tulangan Utama Wiremess M8 Bondek 0,75
1 Pek. Struktur Lantai Beton T=12cm (Besi , Begisting & Beton K-250) m3 59.09 Rp 5,250,000.00 Rp 310,243,500.00 7.33%
Sub Total Rp 310,243,500.00 7.33%
JUMLAH. C Rp 834,990,245.50 19.73%
D. PEKERJAAN ATAP
I Pekerjaan atap Baja ringan
1 Pemasangan Rangka atap bajaringan 0,75 Sni,Mode Cremona rangka m2 451.00 Rp 320,000.00 Rp 144,320,000.00 3.41%
2 Pemasangan doblelayer Aluminium Foil peredam panas m2 451.00 Rp 75,000.00 Rp 33,825,000.00 0.80%
3 Penutup Atap Spandek Zingkalum 0,45 m2 451.00 Rp 145,000.00 Rp 65,395,000.00 1.54%
4 Waterproofing membran bakar EX.SIKA / Standard m2 100.00 Rp 200,000.00 Rp 20,000,000.00 0.47%
IV PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dgn cat tembok interior Ex Jotun m2 612.15 Rp 48,000.00 Rp 29,383,200.00 0.69%
Pek. Pengecatan dinding dgn cat tembok exterior
2 Ex Jotun m2 331.87 Rp 58,000.00 Rp 19,248,460.00 0.45%
wheatershield
Pek. Pengecatan plafond dengan cat tembok
3 Ex Jotun m2 491.02 Rp 48,000.00 Rp 23,568,960.00 0.56%
interior
Sub Total Rp 72,200,620.00 1.71%
IV PEKERJAAN PENGECATAN
1 Pek. Pengecatan dinding dgn cat tembok interior Ex Jotun m2 524.51 Rp 48,000.00 Rp 25,176,480.00 0.59%
Pek. Pengecatan dinding dgn cat tembok exterior
2 Ex Jotun m2 643.33 Rp 58,000.00 Rp 37,313,140.00 0.88%
wheatershield
Pek. Pengecatan plafond dengan cat tembok
3 Ex Jotun m2 837.05 Rp 48,000.00 Rp 40,178,400.00 0.95%
interior
Sub Total Rp 102,668,020.00 2.43%
II PEKERJAAN SANITARY
1 Pek.Closet Duduk TOTO CW 420 J unit 4.00 Rp 3,000,000.00 Rp 12,000,000.00 0.28%
2 Pek.Kran Air Onda unit 35.00 Rp 250,000.00 Rp 8,750,000.00 0.21%
3 Pek.Floor Drain Onda unit 5.00 Rp 150,000.00 Rp 750,000.00 0.02%
Sub Total Rp 21,500,000.00 0.51%
JUMLAH. J Rp 41,000,000.00 0.97%
K. PEKERJAAN LAIN-LAIN
I PEKERJAAN FASAD
1 Pek.Kerawanggan GRC Standard m2 49.30 Rp 750,000.00 Rp 36,975,000.00 0.87%
2 Pek. ACP standard m2 105.48 Rp 900,000.00 Rp 94,932,000.00 2.24%
3 Bata Tempel Ekspose Bata Tempek m2 63.46 Rp 500,000.00 Rp 31,730,000.00 0.75%
4 neon sign ( MASJID AL-HIDAYAH) Neon sign huruf Timbul Akrilic ,Led huruf 15.00 Rp 450,000.00 Rp 6,750,000.00 0.16%
Sub Total Rp 170,387,000.00 4.03%
- Air & listrik kerja ditanggung oleh owner selama pekerjaan berlangsung FURNILIO
- Scope Item Pekerjaan Sesuai Dengan yang tercantum dalam RAB, Jika ada item pekerjaan yang belum masuk ke RAB Approval,
maka akan dihitung ulang berdasarkan kesepakatan bersama
- Harga Penawaran Berlaku 6 Hari Kalender, Terhitung sejak dibuatnya RAB