4D ~ Energy Department
Government of Pu'1iab
Pre-Qualification of EPC Applicants
for
Design and Construction of Net Zero Energy Building
Lahore, Punjab
1.0 INTRODUCTION 1
ANNEXURES
A. Letter of Application 17
Forms
Application Form A-I. General Information 20
Application Form A-2. General Experience Record 21
Application Form A-3. Joint Venture Summary 22
Application Form A-4. Particular Experience Record 23
Application Form A-5. Details of Contracts of Similar Nature and Complexity 24
Application Form A-6. Summary Sheet: Current Contract Commitments/
Works in Progress 25
(i)
Pre-Qualification of EPC Contractors for
Design and Construction of Net Zero Energy Building in Lahore, Punjab
(ii)
1.0 INTRODUCTION
1. Serve as an office building for the Energy Department, Government of the Punjab,
and all its affiliate departments that are currently located at more than 6 different
locations across the city.
2. Serve as an educational space for disseminating information on the concept of
Energy Efficiency & Conservation; displaying renewable energy technologies and
possible prototypes in an Exhibition Room; use the auditorium for seminars on
Energy Efficiency & Conservation and all specific topics to be covered under it,
such as energy audits, creation of an Electricity Supply Company (ESCO) market,
standards and labelling of appliances, retrofitting, building codes etc.
The ERC will serve as a model for the first truly Energy Efficient building in
Pakistan that will catalyze the private sector to invest in more Energy Efficiency
& Conservation measures in buildings. The capabilities of the local firms will be
enhanced regarding the approach to design and construction of an Energy
Efficient facility. Cost- efficiency of such building designs will be highlighted to
enable the designing of further sustainable buildings, not only as showcase
projects but also as cost-efficient alternative to standard building designs.
Sr.
No. Description Quantity
4 Auditorium 1
5 Masjid I
(1)
I
Sr.
No. Description Quantity
7 Gymnasium 1
8 Monitoring room 1
9 Library 1
10 Meeting/conference room 1
11 Store room 1
14 Exibition Room 1
The ERC may include other functionalities /features as per modem commercial
buildings and the latest requirements of LEEDs for Gold Certification, 62%
Reduction from Current Average Level (Annual Electricity Consumption per
Square Foot = 18.35 kWhNear/Sqft) for Net Emission (as per ADB's DLI-8).
The Applicant who has been awarded the Contract shall obtain aforementioned
certification and energy reduction from the concerned authority/body for ERC.
(2)
2.0 INVITATION FOR PRE-QUALIFICATION
Contract No.(s) _
1. The PMU Energy Department, Government of Punjab has been entrusted by the
Government of Punjab and provided funds to finance the cost of Design and Construction
of Net Zero Energy Building to eligible payments under the contract(s) for which this
Invitation for Pre-qualification is issued.
2. The PMU Energy Deparment, Government of Punjab hereinafter the Employer intends to
prequalify Applicant for the following Works under this project: Design and Construction
of Net Zero Energy Building in Lahore, Punjab
In addition to above, incase of JV partner solely responsible for Design Services must have
valid licensees) in appropriate category ofPEC or PCATP or any relevant regulatory body.
6. The request must clearly state "Request for Pre-qualification Documents" for Design and
Construction of Net Zero Energy Building in Lahore, Punjab. The documents are available
for a non refundable fee of PKR 5,000/-. The documents if requested by mail will be
promptly dispatched by registered mail for which cost of mail will be borne by the
Applicant, however, under no circumstances the Employer will be responsible for late
delivery or loss of the documents so mailed.
(3)
I
r
Project Director
Net Zero Energy Building
Project Management Unit
House No. 10-11, Block H-3 Johar Town, Lahore
not later than: 1100 hours on January 31, 2024 and be clearly marked "Application for
Pre-qualification for: Design and Construction of Net Zero Energy Building
9. The Energy Department, Government of Punjab reserves the right to not to accept the late
applications.
10. Applicants will be informed, in due course, of the result of the evaluation of applications.
Only the firms of Applicants and joint ventures prequalified under this process will be
invited to bid.
(4)
3.0 INSTRUCTIONS TO APPLICANTS
3.1.1 Applications for pre-qualification (one original and two copies) must be
received in sealed envelopes to be delivered by hand or through registered mail
to:-
Project Director (PMU)
Department, Government of Punjab
3.1.2 The name and mailing address of the Applicant shall be clearly marked left
hand on the envelope.
3.1.3 The Application shall be typed or written in indelible ink and shall be signed
by a person duly authorized to sign on behalf of the Applicant.
3.1.4 The applications shall be prepared in the English language. Information in any
other language shall be accomplished by its translation in English. Employer
reserves the rights to dis-qualify in case of non-compliance of the above
requirement.
3.1.5 The Applicants must respond to all questions and provide complete
information as advised in this document. Any lapses to provide essential
information may result in dis-qualification of the Applicant.
3.1.6 The clarification meeting will be held. The time, date and place of the meeting
is as follows, where all prospective Applicants may request clarification about
the project and the evaluation criteria. However, the Applicant may seek
clarification post/other communication means not later than five days prior to
the date of submission of Application for Pre-Qualification.
(5)
3.1.7 At any time prior to the deadline for submission of Applications, the Employer
may amend the Prequalification Document by issuing addendum.
Any addendum issued shall be part of the Prequalification Document and shall
be communicated in writing to all who have obtained the Prequalification
Document from the Employer.
3.1.8 To assist in the evaluation of Applications, the Employer may, at its discretion,
ask any Applicant for a clarification of its Application which shall be submitted
within a stated reasonable period of time. Any request for clarification and all
clarifications shall be in writing.
3.1.9 The Employer reserves the right to annul the prequalification process and reject
all Applications at any time, without thereby incurring any liability to
Applicants.
(6)
3.2 Qualification Criteria
3.2.0 EligibilityCriteria
1) An Applicant may be an entity or any combination of entities with a formal
intent to enter into an agreement or under an existing agreement in the form
of a Joint Venture. In the case of a Joint Venture,
2) An Applicant, and all partners constituting the Applicant, shall have the
nationality of Islamic Republic of Pakistan. An Applicant shall be deemed
to have the nationality of Pakistan if the Applicant is constituted,
incorporated, or registered and operates in conformity with the provisions
of the laws of Pakistan. [See definition of Pakistani Constructor at PEC
Constrution and Operation of Engineering Works Byelaws No. 2Ua)]
3) An Applicant (in case of JV, all Partners to JV) shall be duly licenced by
the Pakistan Engineering Council (PEC). The sole firm or lead partner of
the JV shall be registered in Category 'C-A' for works, whereas, the other
partners to JV shall have valid license in the appropriate category relevant
to their share/nature of works. In case validity of licence has expired, the
Applicant must had applied for renewal of licence before submission of its
application and furnish the evidence/receipt of the renewal fee.
(7)
b) two or more Applicants partially or wholly owned or directed by
common individuals, regardless of extent of their shares or interest
shall not be eligible to participate in the prequalification process. Either
only one such Applicant may participate or such Applicants may form a
joint venture to participate as one venture; and
The Applicant who do not meet all of the above Eligibility Criteria shall be
disqualifedfrom the Pre-Qualification process.
3.2.1 General
(8)
Sr. No. Catezorv Weightage/Marks
l. General Experience 50
2. Personnel Capabilities 20
3. Equipment Capabilities 10
4. Financial Position 20
Total: 100
3.2.2 GeneralExperience
Sr. Marks
Description Explanation for Marks Obtained
No. Assigned
i. Building Projects in last ten 20 • A = 10 Marks are given if the Applicant
years either as sole contractor has completed 2 projects of similar
or as partner to JV only. nature in last ten years.
(9)
Sr. Marks
Description Explanation for Marks Obtained
No. Assigned
II. EPC based Projects in last ten 20 • A = 10 Marks are given if the Applicant
years as prime contractor or as has completed 2 projects of similar
partner to JV only. nature in last ten years.
A = (nl2) xlO
Projects of similar nature
n= No. of Projects completed in last
means
ten years
(Each of which has min.
contracted value of PKR 400 if number of completed projects are less
Millions) than one then total marks (C) shall be
Zero.
• If the Applicant has two (2) projects
other than those stated above, either
inhand or completed, Marks weightage
shall be used as
B= (nl2)xI0
n= No. of Projects inhand or
completed in last ten years
Total Marks (C) = A+B
111. Number of LEED Certified 5 • A = 2.5 Marks are given if the Applicant
projects during the last ten has completed 1 project of similar nature
years. in last ten years.
if number of completed projects are less
Projects of similar nature
than one then total marks (C) shall be
means
Zero.
(Each of min. 4-Storeyed • if the Applicant has two (2) projects
Building Work or building other than those stated above, either
area of at least 90,000 sq ft.) inhand or completed, Marks weightage
shall be used as
B = (nl2) x2.5
n= No. of LEED Certified Projects
inhand or completed in last ten years
Total Marks (C) = A+B
• 5 Marks for Platinum/Gold Certified
Building
Categories of completed • 2.5 Marks for each Silver Certified
IV. 5
LEED Certified Building Building
• Upper score limit under this category
shall be 5
Total Marks Allocated 50
Credit Marks shall be awarded under this category using the following criteria:
(10)
Marks
Sr. No. Description Explanation for Marks Obtained
Assianed
i. LEED Accredited 5 • 5 Marks shall be awarded for LEED
Professional(s) Accredited Professional on the Project
Team
ii. M.Sc/M.S/B.ScfB.E 13 Experience (-Marks):
Engineers registered with Project Staff:
Pakistan Engineering • 2 Marks will be given if the Project
Council (PEC) Manager has M.Sc Civil/ Construction
Domain of Engineers Management Engineering, Professional
• Civil Engineer status as per PEC, and has
• Planning relevant experience of 15 years or
• Electrical above.
• Mechanical • 2 Marks will be given if the Construction
• Enviromental Manager has M.Sc Civil/ Construction
• Geotechnical Management Engineering, has
Professional Engineer status as per PEC,
• Structural and has relevant experience of 15 years
• HSE or above.
• 1 Mark will be given if the Planning
Manager has B.Sc Civil Engineering, has
Registered Engineer status as per PEC,
and has relevant experience of 7 years or
above and must have 5 years experience
of Primavera.
• 2 Mark will be given if the Firm has 02
B.Sc Electrical with Registered Engineer
status as per PEC, and has relevant
experience of 7 years or above.
• 2 Mark will be given if the Firm has 02
B.Sc Mechanical with Registered
Engineer status as per PEC, and has
relevant experience of 7 years or above.
• 1 Mark will be given if the Firm has 01
M.Sc Structural with Registered
Engineer status as per PEC, and has
relevant experience of7 years or above.
• 1 Mark will be given if the Firm has 01
B.Sc Environmental Engineering!
Sciences with Registered Engineer status
as per PEC, and has relevant experience
of7 years or above.
• 1 Mark will be given if the Firm has 01
M.Sc Geotechnical Engineering with
Registered Engineer status as per PEC,
and has relevant experience of 7 years or
above.
• 1 Mark will be given if the Firm has
OSHAINEBOSH Certified HSE
Manager and has relevant experience of
7 years or above.
No point is awarded in case of non-compliance to
the requirement. ---
(11 )
Marks
Sr. No. Description Explanation for Marks Obtained
Assigned
Ill. Associates Engineers (DAE) 2 .0.5 Marks will be given for 02 Civil
Civil, Electrical, DAEs
Mechanical, Quantity .0.5 Marks will be given for 02 Electrical
Surveyors DAEs
·0.5 Marks will be given for 02
Mechanical DAEs
.0.5 Marks will be given for 01 Quantity
Surveyors
Credit Marks shall be granted on the basis of the following criteria for various
kinds of equipment relevant for the Project:
Marks
Sr. No. Description Explanation for Marks Obtained
Assigned
I. 30 Cubic MeterlHour 5 • 5 Marks for each equipment are given
Capacity Batching Plant (0 I if the Applicant meets the minimum
No.) requirements given In the
11. Concrete Pumps (03 Nos.) 5 prequalification document for each
item.
Ill. 30 Tonne Capacity Crane 5 • If the available quantity of each
Mobile (01 No.) equipment is less than specified limit
IV. 30 Meter Boom Crane Tower 5 give weightage as.
(01 No.) 5 x (A / Required Quantity)
v. Dumper Trucks (03 Nos.) 5 • If the available quantity of each
equipment is more than the minimum
vi. Shower/ Loader/ Backhoe 5 equipment requirement full marks will
. (03 Nos.) be given.
vii. Steel cutting & Bending 5 A = Available quantity against each
Machine (04 Nos.) Item.
VIII. 06 Cubic Meter/ Hour 5 • Total Marks =
Concrete Transit Mixer (Sum of Marks Obtained against each
(06 Nos.) Sr.No/60) * 10
IX. 1500 kg Capacity Cabin 5
Hoist (02 Nos.)
x. 15 HP Capacity Air 5
Compressor (04 Nos.)
xi Formwork (30,000 sft) 5
(12)
3.2.5 Financial Position
Sr. Marks
Description Criteria for Marks Obtained
No. Assizned
• 6 Marks are given if the Net Financial
Resources are equal to or more than PKR
Net Financial Resources 500 Million.
1. 6
(Form A-I0) • For Net Financial Resources of less than
PKR 500 Million, no points shall be
awarded .
11. Available Bank Credit Line • A = 4 Marks are given if the available bank
credit line limit is equal to PKR 500
Million.
The applicant should submit 6 if the available credit line is less than
valid documentary evidence PKR 500 Million then total marks (C)
shall be Zero .
i) The lead partner shall meet not less than 50% percent of all
qualifying criteria given in paras 3.2 and 3.4 heretofore.
(13)
ii) Each of the partners shall meet not less than 25% percent of all total
criteria given in paras 3.2 and 3.4 heretofore. Or, if partner to N is
Design Consultant, it shall meet not less than 50% percent of the
criteria given in Sub-Clause 3.2.2 (iii & iv) & 3.2.3 (i).
iii) The joint venture must collectively satisfy the criteria of paras 3.2,
and 3.3, for which purpose the relevant figures for each of the
partners shall be added together to arrive at the N's total capacity.
Individual members must satisfy each of the requirements of paras
3.4 and 3.5 heretofore.
3.3.2 The prequalification of a N does not necessarily prequalify any of its partners
individually or as a partner in any other JV or association. In case of dissolution
of a N, each one of the constituent firms may prequalify if they meet all the
prequalification requirements and any partner of J.V has requested/shall request
for the same and then his prequalification shall be subject to the written
approval of the Employer.
3.4.1 Bidders shall be required to update the financial, personnel and equipment
information used for prequalification at the time of submitting their bids, to
confirm their continued compliance with the qualification criteria and
verification of the information provided at the time of prequalification. A bid
shall be rejected if the Applicant's qualification thresholds are no longer met at
the time of bidding.
3.5.1 Only firms and JVs that have been prequalified under this procedure shall be
invited to bid. A qualified firm or a member of a qualified IV may participate
only in one bid for the contract. If a firm submits more than one bid, singly or
(14)
as a JV, all bids including that bidder will be rejected. This rule will not apply
in respect of bids which include specialist sub-contractors who are used by
more than one bidder.
a) Amend the scope and value of any contract(s) to be bid, in which event
the bidder(s) will only bid among those prequalified bidders who meet the
requirements of the contract(s) as amended. However the Employer has to
review the disqualified bids who originally do not meet the specified
criteria for Pre-qualification.
The Employer shall neither be liable for any such actions nor be under any
obligation to inform the Applicant of the grounds for rejection, however, may
be debriefed if solicited.
3.5.3 Applicants will be informed in writing by fax or mail within 30 days of the date
for submission of applications (para 8 of Chapter 2.0, Invitation for
Prequalification) of the result of their applications and may be debriefed if
solicited.
(15)
4.0 EVALUATION CRITERIA
Applicants meeting the rmrumum requirements mentioned in Para 3.2 and 3.3 besides other
factors shall be considered for pre-qualification. No compromise shall be made on minimum
requirements of 30% score in each category by the JV alongwith passing score of cumulative 60%
of the total.
(16)
Annex-A
Letter of Application
Date: .
Sirs,
the place of registration and the nationality of the owners (for applicants who are
partnerships or individually-owned firms).
3. Your Agency and its authorized representatives are hereby authorized to conduct any
inquiries or investigations to verify the statements, documents, and information submitted
in connection with this application, and to seek clarification from our bankers and clients
regarding any financial and technical aspects. This Letter of Application will also serve as
authorization to any individual or authorized representative of any institution referred to in
For applications by joint ventures, all the information requested in the prequalification documents is to be
provided for the joint venture, if it already exists, and for each party to the joint venture separately. The lead
partner should be clearly identified. Each partner in the joint venture shall sign the letter.
(17)
the supporting information, to provide such information deemed necessary and requested
by yourselves or the authorized representative to verify statements and information
provided in this application, or with regard to the resources, experience, and competence
of the Applicant.
4. Your Agency and its authorized representatives may contact the following persons for
further information", if needed.
Contact 1 Telephone 1
Contact 2 Telephone 2
Personnel Inquiries
Contact 1 Telephone 1
Contact 2 Telephone 2
Technical Inquiries
Contact 1 Telephone 1
Contact 2 Telephone 2
Financial Inquiries
Contact 1 Telephone 1
Contact 2 Telephone 2
(i) amend the scope and value of any contract under this project; in such event
bids will only be called from prequalified bidders who meet the revised
requirements; and
(ii) reject or accept any application, cancel the prequalification process, and reject
applications; and
2
Application by joint ventures should provide information on a separate sheet information for each party to the
application.
(18)
(c) your Agency shall not be liable for any such actions and shall be under no
obligation to inform the Applicant of the grounds for actions at 5(b) hereabove.
(d) your Agency shall not be liable for consequence of, and shall be under no
obligation to inform the applicant of the grounds for, actions taken under para 5(b)
hereabove.
Applicants who are not joint ventures should delete para 6&7 and initial the
deletions.
7. We confirm that in the event that we bid, that bid as well as any resulting contract will be.
(a) signed so as to legally bind all partners, jointly and severally; and
(b) submitted with a Joint Venture agreement providing the joint and several liability
of all partners in the event the contract is awarded to us.
8. The undersigned declare that the statements made and the information provided in the duly
completed application are complete, true, and correct in every detail.
Signed Signed
Name Name
(19)
Application Form A-I Page_ of __ Pages
General Information
All individual firms and each partner of a joint venture applying for prequalification are
requested to complete the information in this form. Nationality information is also to be provided
for applicants who are forming part of the Joint Ventures as required under the PEC Bye-Laws as
a Partnership/Joint Venture.
Where the Applicant proposes to use named sub-contractor for critical components of the works,
the following information should also be suppliedfor the specialist subContractor(s).
1. Name of Firm
4. Fax Telex
NATIONALITY OF OWNERS
NAME NATIONALITY
1.
2.
3.
4.
5.
All individual firms and all partners of a joint venture are requested to complete the information
in this form. The information supplied should be the annual turnover of the Applicant (or each
member of a joint venture), in terms of the amounts billed to clients for each year for work in
progress or completed over the past three years.
Annual Turnover
Year Turnover Equivalent Rupees in
(in actual currency) Millions*
1. 2020-2021
2.2021-2022
3.2022-2023
*Converted to PKR at the rate of exchange prevailing twenty-eight (28) days prior to deadline
for submission of Applications
(21)
Application Form A-3 Page_ of __ Pages
2. Partner
3. Partner
1. Lead
Partner
2. Partner
3. Partner
Total:
(22)
.•.
Application Form A-4 Page_ of __ Pages
To prequalify, the Applicant shall be required to pass the specified requirements applicable to this
form, as set out in the.' Instructions to Applicants ".
On a separate page, using the format of Application Form A-5, each applicant or partner of a
Joint Venture is required to list all contracts of a value equivalent to Pak Rs 1,000 million, or of
similar nature and complexity to the contract for which the Applicant wishes to qualify,
undertaken during the last ten years. The information is to be summarized, using Application
Form A-5, for each contract completed or under execution by the Applicant or by each partner of
a Joint Venture.
Where the Applicant proposes to use named sub-contractor for critical components of the works,
the information in the afore-mentioned forms should also be supplied for each specialist sub-
Contractor.
I. The Applicant shall submit authenticated documentary evidence which include but not
limited to Contract Agreements, Project Scope, Taking Over Certificate/Completion
Certificate of the contracts being claimed
(23)
Application Form A-S Page_ of __ Pages
I. Name of Contract
Country
2. Name of Employer
3. Employer Address
4. Nature of works and special features relevant to the contract for which the Applicant wishes to
prequalify
(a) Sole Contractor (b) Lead Partner to JV (c) Partner in a Joint Venture
6. Value of the total contract (in specified currencies) at completion, or at date of award for current
contract
7. Equivalent in PakJRs.
8. Date of Award
9. Date of Completion
Years Months
Applicants and each partner to an application should provide information on their current
commitments on all contracts that have been awarded, or for which a letter of intent or
acceptance has been received, or for contracts approaching completion, but for which substantial
Completion Certificate has yet to be issued.
Value of
Value of
Outstanding
Employer's Outstanding Estimated
Work
No. Name of Contract Contact Address, Work** Completion
[Respective
Tel, Fax [PKR Date
Currency _]
Equivalent)*
* Converted to PKR at the rate of exchange prevailing twenty-eight days prior to deadline for
submission of Applications.
** The Applicant shall substantiate the above information for next four months with documentary
evidence, i.e., Award of Contract & Approved Project Schedule(s) etc.
(25)
Application Form A-7 Page_ of __ Pages
Personnel Capabilities
I Name of Applicant
For specific positions essential to contract implementation, Applicants should provide the names
of candidates qualified to meet the specified requirements stated for each position. The data on
their experience should be supplied on separate sheets using one Form for each candidate
(Application Form A-8).
1. Title of Position
2. Title of Position
3. Title of Position
4. Title of Position
,'i'',"'-'
''C1\(\ gS
'.J~;
~
e,,,.
~~ .. i
(26) ?\"'t-", ~
'c~~n~ .
Application Form A-8 Page_ of __ Pages
Candidate Summary
I Name of Applicant
3. Professional Qualification
Address of employer
Fax Telex
From To
(27)
Application Form A-9 Page_ of __ Pages
Equipment Capabilities
I Name of Applicant
The Applicant shall provide adequate information to demonstrate clearly that he has the
capability to meet the requirements for each and all items of equipment listed in the Instructions
to Applicants. A separate Form shall be prepared for each item of equipment listed in para 3.2.4
of the Instructions to Applicants, or for alternative equipment proposed by the Applicant.
Item of Equipment
Equipment 1. Name of manufacturer 2. Model and power rating
information
9. Address of owner
Fax Telex
(28)
Application Form A-IO Page_ of __ Pages
Financial Capability
Applicants, including each partner of a joint venture, should provide financial information to
demonstrate that they meet the requirements stated in the Instructions to Applicants. Each
applicant or partner of a joint venture must fill-in this form. If necessary, use separate sheets to
provide complete banker information. A copy of the audited financial statements should be
attached.
Address of banker
Fax Telex
Summarize assets and liabilities in Pak Rupees (Equivalent at the current rate of exchange at the
end of each year) for the previous three years, based upon known commitments
Information from Financial Data for Previous Years from 2021 to 2023
Balance Sheet Year 1 Year 2 Year 3
(2020-2021) (2021-2022) (2022-2023)
1. Total Assets
(TA)
2. Total Liabilities
(TL)
3. Net Worth =
TA-TL
4. Current Assets
(CA)
5. Current
Liabilities (CL)
6. Working
Capital = CA -
CL ------ ~
..••.~n"~
-"'v~.
,.?;/'\"".~ ~~
(29) .r "3
" "".
Information from Income Statement for Previous Years from
2021 to 2023
Year 1 Year 2 Year 3
(2020-2021) (2021-2022) (2022-2023)
l.Total Revenues
2.Profit Before
Taxes
3.Profit After
Taxes
Financial Resources
Specific proposed sources of financing such as liquid assets (Cash & Bank balances and
marketable security only), unencumbered real assets, line of credit, and other financial means to
meet the cash flow of the Project, net of current commitments (Instructions to Applicants, para
3.2.5).
Total
o Attached are copies of financial statements (balance sheets including all related
notes, and income statements) ,for individual applicant or each partner to JV, for the
last three years, as indicated above, complying with the following conditions.
• All such documents reflect the financial situation of the firm.
• Historic financial statements must be audited by a certified accountant! firms.
• Historic financial statements must be complete, including all notes to the financial
statements.
Historic financial statements must correspond to accounting periods already completed
and audited (no statements for partial periods shall be requested or accepted).
Note: Firms owned by individuals, and partnerships, may submit their balance sheets certified by
a registered accountant/firm, and supported by copies of tax returns, if audits are not required by
the laws of their countries of origin in case offoreignfirms.
(30)
Application Form A-ll Page_ of __ Pages
Litigation History
Name of Applicant or Partner of a Joint Venture
Applicants, including each of the partners of a joint venture, should provide information on any
history of litigation or arbitration resulting from contracts executed in the last five years or
currently under execution (Instructions to Applicants, para 3.2. O. 7). A separate sheet should be
usedfor each partner ofjoint venture.
(31)
Application Form A-12 Page_ of __ Pages
We, insert name of the Bidder, hereby undertake that if Contract is awarded to us, we guarantee
acquiring ofLEED Gold Certification (BD+C) and 62% Reduction from Current Average Level
(Annual Electricity Consumption per Square Foot = 18.35 kWhNear/Sqft) for Net Emission (as
per ADB's DLI-8) for the ERC building. In case of failure in acquiring aforementioned
certification, energy efficiency and reduction in net emission for ERC, the Employer has the
right to encash guarantee(s), and withhold payments (as determined by the Employer) due to the
Contractor.
Note: The Applicant shall submit this undertaking on 100 Rs. Duly notarized affidavit.
(32)