INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: July 17, 2022
CSI Improvement/Corrective Action Plan
Page 1 of 16
Table of Content
1. Objective:
1 Work Permit 1 - - 2
2 Excavation & Shoring - - - -
3 Confined Space - - - -
4 Traffic & Vehicle Safety - - - -
5 Safety Officer - - - 1
6 Road Works - - -
7 Work at Height/Fall Protection - - - -
8 PPE - -
9 Mechanical & Heavy Equipment 1 - 1
D. Root Causes.
Corrective Action (Training was conducted by 3rd. party and evidence submitted
through FSIR closure certificate for the required personals).
All Site Engineers, Supervisors/Foreman, safety officers and WPR will be held
responsible and charged equal penalty and warning as per “SINOHYDRO Disciplinary
Action/ Procedure” in case of any safety violation (unsafe acts or unsafe condition) by
their crew / area, especially below listed but not limited, to the action requested by the
HSE department. whereas on good safety practices reward and appreciation certificates
will be issued by the management on monthly basis.
Project Name: KING SALMAN ENERGY PARK (SPARK) Doc. No.: DOC-IMB-SH-HSE-0027
INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: June 27, 2022
CSI Improvement/Corrective Action Plan
Page 7 of 16
Project Name: KING SALMAN ENERGY PARK (SPARK) Doc. No.: DOC-IMB-SH-HSE-0027
INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: June 27, 2022
CSI Improvement/Corrective Action Plan
Page 8 of 16
Project Name: KING SALMAN ENERGY PARK (SPARK) Doc. No.: DOC-IMB-SH-HSE-0027
INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: June 27, 2022
CSI Improvement/Corrective Action Plan
Page 9 of 16
On the other hand, contempt of Strict disciplinary actions, an appreciation and incentive plan
will be exercised as per below and company policy. Contractor is going to encourage the
workforce who contribute to enhance safety compliance at site first week of every quarter.
Any employee/worker (despite of position) observed on site with good safety practicing
during ‘Safety campaign’ by SAPMT / SINOHYDRO management will be nominated for
appreciation letter with incentive money.
HSE team will nominate the workers / employees from their work site on monthly basis, and
every quarter, (5) best safety workers will be selected and rewarded appreciation certificate
with incentive during “Quarterly Safety Award Ceremony”.
SAPMT may also suggest the names for safety award.
Appreciation awards selection / nominees will be finalized by HSE Manager/ HSE committee
base on below important points.
1. The worker has no warning / disciplinary action previously/
2. The worker has no previous record of safety violations
3. The worker will not be nominated second time within (3) months.
4. The nominee is a good practitioner of PPE’S and safety rules and regulations.
5. The nominee is following safety guidelines.
6. The nominee is not involved or observed in unsafe acts and conditions.
7. The nominee is supporting to spread safety culture.
8. The nominee is often observed with positive safety practices.
Project Name: KING SALMAN ENERGY PARK (SPARK) Doc. No.: DOC-IMB-SH-HSE-0027
INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: June 27, 2022
CSI Improvement/Corrective Action Plan
Page 10 of 16
c. To improve Work Permit System, all work permit issuers and receivers need re-
evaluation / counselling meeting with all issuers and receivers.
d. Site supervisor, safety officer and WPR is responsible for proper and complete work
permit on job site, with all required documents.
e. Safety supervisor will be responsible to inspect/ audit all areas permit early in the
morning.
f. Site supervisor is responsible to conduct daily TBT and 100 % assure the all tools and
equipment’s inspection, permit and documents available before to start of any activity.
g. Site supervisor, WPR and safety officer will not leave his site (Without proper
delegation of permit).
h. Site supervisor, WPR and safety officer will be proactive to their all, job site safety
requirements and will not sit in vehicle/bus/coaster during the execution of job.
i. Site supervisor, WPR will not allow any activity until all requirements have been
completed as per approve MOS / JSA and SA safety requirements, like SA permit, pre
checklist and inspections etc.
j. Site supervisor, WPR and safety officer are responsible to assure all check lists, Fire
extinguishers inspection, 3rd party sticker, operators’ certification, training ID, PPE’S,
MOS, JSA, MSDS etc.
Project Name: KING SALMAN ENERGY PARK (SPARK) Doc. No.: DOC-IMB-SH-HSE-0027
INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: June 27, 2022
CSI Improvement/Corrective Action Plan
Page 12 of 16
08.3 PPE’s
Site engineer, supervisor, foreman, WPR and safety officer are responsible for his area to
check the compliance of mandatory/required PPEs as per the job requirements.
Strict Disciplinary Action and penalties on Failure to comply Safety requirements will be
imposed as discussed in daily TBT and standby meeting with the all employees and all the
‘Front line management’ (Site Engineers, supervisors/Foreman, Safety officers and work
permit receivers and workers in multi and understandable (Translated in their Native)
languages.
Project Name: KING SALMAN ENERGY PARK (SPARK) Doc. No.: DOC-IMB-SH-HSE-0027
INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: June 27, 2022
CSI Improvement/Corrective Action Plan
Page 13 of 16
09. Responsibilities.
• Ensure necessary work permit from Saudi Aramco Operations has been issued prior to
start the work (if required).
• Must get counter sign from related department when required (if required).
• Conduct safety tool box talk related to activity.
• Ensure HIP and JSA for the specific work location & activity is available.
• Equipment is certified and in well working condition.
• All operators working under his responsibility are trained, experienced and certified
as per requirement.
• All workers involve in activity having and using job required PPE.
• Workers are fully aware through work related hazards.
• No any underground utilities are present in excavation area.
• Ensure safe working environment for safe work execution.
• Always ensure good housekeeping.
• Ensure all workers are fully aware about emergency response procedure.
• Ensure First Aid Kit is available on work site.
• Release workers for necessary training or meeting when required.
• Report immediately all near misses, First Aid cases, fire, heavy equipment accidents
and property damage incidents etc. to safety supervisor and senior management for
necessary Action.
• Always cooperate with safety personnel, by acting on their recommendations
• Coordinate with safety personnel prior to start any critical activity e.g., work beside the
roads, inside the plant and blasting activities etc.
• Don’t start any activity until necessary safety arrangements are completed.
• Don’t allow workers to ride over heavy equipment.
• Don’t allow workers to sit under or beside equipment.
• Don’t allow workers to sit over, inside or beside the pipes.
• Don’t allow workers to get training for heavy equipment on work site.
Project Name: KING SALMAN ENERGY PARK (SPARK) Doc. No.: DOC-IMB-SH-HSE-0027
INFRASTRUCTURE AND MAINTENANCE BUILDING Rev. No.: 00
Date: June 27, 2022
CSI Improvement/Corrective Action Plan
Page 14 of 16
• Participate in work-site layouts to assure adequate work areas, traffic control, parking
areas, lighting levels, receiving areas, etc. Assure that location of offices, shops,
• maintenance areas, fabrication shops, medical, and sanitation facilities reflect safety
considerations.
• Review the work schedules as they are planned to be aware of the number of
contractors and craft workers working in the various areas; anticipate hazards and
implement supporting safety activities.
• Establish personal protective-equipment requirements and recommend requisition for
purchase.
• Plan the safety publicity program and order posters, visual aids, signs, etc.
• Establish and maintain site, Emergency Response Team.
Safety Officer
The safety officer is responsible for implementing the safety program on the project. He is
responsible for monitoring and administering a proactive project safety program in
accordance with the project safety program designed to provide assistance in
recognizing, evaluating, and subsequently eliminating or controlling hazardous acts or
conditions. He works in conjunction with his project/site manager, construction manager
and site safety manager assisting in the implementation of the safety program as it
pertains to the contractor. The Safety officer plays an important role in daily field
monitoring, advice supervisors & craftsmen on safety practices and to recommend on the
spot corrective action to be taken.